RESOLVED : to (a) approve commencing the procurement process to select a contractor to refurbish the dry side changing facilities at Henley Leisure Centre; and (b) authorise the head of community services, in consultation with the Cabinet member for community services, to award the contract to the winning tenderer, if the tendered sum is within the approved budget of £100,000 and the works comply with the required specification.
Word for word from the decision South Oxfordshire published for this meeting.Source: democratic.southoxon.gov.uk
Report of Head of Community Services Author: Jan Smith Telephone: 01235 422243 E-mail: [email protected] Wards affected: Henley-on-Thames Cabinet member responsible: Councillor Maggie Filipova-Rivers Tel: [phone removed] E-mail: [email protected] To: CABINET Date: 27 June 2019
Henley Leisure Centre - refurbishment works to the dry side changing facilities Recommendations (a) To approve commencing the procurement process to select a contractor to refurbish the dry side changing facilities at Henley Leisure Centre.
(b) To delegate authority to the Head of Community Services, in consultation with the Cabinet Member for Community Services, to award the contract to the winning tenderer, if the tendered sum is within the approved budget of £100,000 and the works comply with the required specification.
Purpose of Report 1. To seek the appropriate approvals to procure for and award a contract for the refurbishment of the dry side changing facilities at Henley Leisure Centre.
Corporate Objectives 2. This project will contribute towards the strategic objective of “Sustainable communities and wellbeing” and corporate priority of ensuring that “we will increase participation in sport and leisure”, specifically by “improving accessibility and availability of leisure facilities in South Oxfordshire
Background 3. The council is seeking to procure a suitable contractor to undertake the refurbishment of the Henley Leisure Centre dry side changing facilities showers and toilets.
Page 7 Agenda Item 6
4. Water from the dry side showers is seeping into the sports hall from adjoining walls and degrading the structure of those walls and possibly the sports hall floor. This is due to the poor laying of the floor tiles and the grout used to waterproof the area.
5. At its meeting on 20 December 2018 Council agreed the recommendations of Cabinet, made at its meeting on 18 December 2018, to use the surplus budget from Henley Leisure Centre changing room budget for the refurbishment of the dry side facilities at Henley Leisure Centre and resolved to create a new capital scheme within the council’s approved capital programme. Council also agreed to vire £19,000 from the existing wet side changing room refurbishment budget into the new capital budget.
6. The total budget available for this project is £100,000, made up of £81,000 from the general repairs and maintenance capital budget and £19,000 from surplus budget that has been vired from the completed wet change refurbishment project completed at Henley leisure centre in 2017.
7. Officers anticipate that all the works can be achieved from this budget, however, cost certainty will be determined once tender evaluation has been completed. The evaluation is based on the approved corporate process of awarding 60% of the evaluation marks for price and 40% of the marks for quality. Each tender will be marked by a number of officers to ensure best value is obtained.
8. To ensure that the appointment of the contractor is taken in a timely manner consistent with the corporate Capita procurement process and timetable, officers are seeking Cabinet approval for the decision to award the contract to be taken by the Head of Community Services in consultation with the Cabinet Member for Community Services.
9. This appointment will only take place if the tender matches the specification for the works required and the cost for those works falls within the approved capital budget of £100,000.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.