Budget monitoring

Noted Executive 3 papers

Cabinet noted this item on Thursday 18 March 2021. Below is the council's own wording, with the papers it was decided on.

Item74

Resolved

RESOLVED : to note the contents of the interim head of finance’s report to Cabinet on 18 March 2021.
Word for word from the decision South Oxfordshire published for this meeting. Source: democratic.southoxon.gov.uk

Follow this further

Built from South Oxfordshire's papers

What the report saysPro

Report to Cabinet

Agenda Item 7

Cabinet Report

Report of Head of Finance Author: Richard Spraggett Telephone: 01235 422505 Textphone: 18001 01235 422505 E-mail: [email protected] Wards affected: All Cabinet member responsible: Leigh Rawlins Tel: 01189 722565 E-mail: [email protected] To: CABINET Date: 18 March 2021

Budget monitoring April 2020 – January 2021 Recommendation Cabinet is recommended to note the contents of the report

Purpose of Report 1. To report the revenue and capital expenditure against budget for the period April 2020 to January 2021 and the latest year end outturns forecast by Heads of Service.

Corporate Objectives 2. The allocation of financial resources within the revenue and capital budgets needs to match the objectives agreed by the Council. The budget monitoring report shows how these resources have been allocated during the first eight months of the financial year.

Background 3. This report reviews the council’s revenue and capital expenditure performance to the end of month ten (January). Year-end outturn forecasts were worked on during February and early March and based on heads of service’s best knowledge at this time.

Page 2 Agenda Item 7

Revenue budget monitoring

4. On 13 February 2020, Council agreed a net revenue budget for 2020/21 of £17.704 million. This has subsequently increased to £21.920 million. This reflects the revised budget agreed by Council on 8 October 2020, and the carry forward of unspent one-off project budgets from 2019/20.

5. Table 1 below shows, summarised at service level, both the revenue position as at the end of January 2021 and the forecast position at year end.

Table 1: Revenue budget monitoring position as at January 2021 Service Working Spend to Variance Working Forecast Variance budget Date budget spend for year to date full year year £000 £000 £000 £000 £000 £000 Strategic management team 829 706 (123) 995 861 (134) Corporate services 3,873 4,257 384 4,901 4,242 (659) Development and regeneration 3,398 987 (2,411) 4,023 1,341 (2,682) Finance 687 (24) (711) 419 593 174 Housing and environment 5,431 5,006 (425) 7,185 6,171 (1,014) Legal and democratic 905 765 (140) 1,086 1,026 (60) Partnerships 2,807 3,906 1,099 3,369 3,337 (32) Planning 1,877 1,323 (554) 2,253 1,517 (736) Policy and programmes 589 544 (45) 706 632 (74) Contingency (2,208) (1,595) 613 (3,017) (2,552) 465 Total 18,188 15,875 (2,313) 21,920 17,168 (4,752)

6. Of the £4.752 million forecast underspend, £3.637 million represents underspends against one-off budgets that will be the subject of carry forward requests. Further detail on the forecast variance is shown in the appendices as follows:

 Appendix 1 provides a summary of the key forecast year end variances

 Appendix 2 details those budgets that will be the subject of carry forward requests

 Appendix 3 provides a service-based analysis of current and forecast variances

7. Officers propose to earmark the year end underspend after carry-forwards to fund further potential losses arising from the Coronavirus pandemic.

Capital Budget Monitoring

8. On 13 February 2020, Council agreed a capital programme for 2020/21 as follows:

 Approved programme - £17.071 million

 Provisional programme (including Cabinet growth proposals) - £9.229 million.

9. As a result of officers prioritising the council’s response to the pandemic, much of the approved capital programme has already been slipped to 2021/22. At the end of January 2021, the approved programme totalled £3.961 million, against which £644,000 had been spent. It is therefore to be expected that there will be further slippage on the approved programme by year end.

Page 3 Agenda Item 7

Financial, legal and any other implications 10. The financial implications are as set out in the body of the report. There are no other implications of this report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 215 KB Download
PDF
Appendix 2Appendix 2 213 KB Download
PDF
Budget monitoringReport 347 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

19 of 19 attended
SC
Sue CooperChair, present
RB
Robin BennettVice-Chair, present
MF
Maggie Filipova-RiversCommittee Member, present
PB
Pieter-Paul BarkerCommittee Member, present
AP
Andrea PowellCommittee Member, present
LR
Leigh RawlinsCommittee Member, present
DR
David RouaneCommittee Member, present
AS
Anne-Marie SimpsonCommittee Member, present
PC
Pat ConnellOfficer, present
SC
Steve CullifordOfficer, present
AD
Adrian DuffieldOfficer, present
MH
Mark HewerOfficer, present

All 19 on the meeting page

On this subject at South Oxfordshire

Search all
  1. Budget monitoringThis decision
  2. Budget monitoring April 2026 - June 2026Noted
  3. Budget monitoring April 2025 - December 2025Noted
  4. Budget monitoring April 2025 – September 2025Noted
  5. Budget monitoring April 2025 - June 2025Noted
  6. Q3 Budget Monitoring reportNoted

More from South Oxfordshire Cabinet

All decisions
MeetingDecisionOutcome
17 Sep 2026 Budget monitoring April 2026 - June 2026that Cabinet noted the contents of the report. Noted Open
17 Sep 2026 Nature and Climate Action Plan - Annual 2025/26 performance update and 2026/27 action plan reviewthat Cabinet adopt the updated joint Nature and Climate Action Plan 2025-26 for the delivery year 2026/27. Approved Open
17 Sep 2026 Joint council policy on commemorative benches and treesthat Cabinet: a) Approves the joint policy ‘Commemorative benches and trees’ with no changes. b) Subject to approval ... Approved Open
17 Sep 2026 Car Park Management from 2027a) That Cabinet recommends to Full Council to extend the contract with Saba Park Services UK Limited (Saba) to provid... Decided Open
2 Jul 2026 Waste and street cleansing vehicle selection and procurement policyThat Cabinet: a) Approves the updated waste and street cleansing vehicle selection and procurement policy, which incl... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies