Resolved
RESOLVED to note the Budget Monitoring Report for April to September 2023.
Cabinet noted this item on Thursday 21 December 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to note the Budget Monitoring Report for April to September 2023.
Agenda Item 9
Cabinet Report
Report of Head of Finance Author: Richard Spraggett Telephone: 01235 422498 Textphone: 18001 01235 422498 E-mail: [email protected] Wards affected: All South Cabinet member responsible: Pieter-Paul Barker Tel: 01844 212438 E-mail: [email protected] To: CABINET Date: 21 December 2023
Budget monitoring April 2023 – September 2023 Recommendation Cabinet is recommended to note the contents of the report
Purpose of report 1. To report the revenue and capital expenditure against budget for the period April 2023 to September 2023 and the latest year end outturns forecast by heads of service.
Corporate objectives 2. The allocation of financial resources within the revenue and capital budgets needs to match the objectives agreed by the council. The budget monitoring report shows how these resources have been allocated during the first six months of the financial year.
Background 3. This report reviews the council’s revenue and capital expenditure performance to the end of month six (September). Year-end outturn forecasts were worked on during October/ November and are based on heads of service’s best knowledge at that time.
Page 2 Agenda Item 9
Revenue budget monitoring
4. On 16 February 2023, Council agreed a net revenue budget for 2023/24 of £18.548 million. This has subsequently increased to £22.784 million. This reflects the carry forward of unspent one-off project budgets from 2023/23 and additional grant funded budgets.
5. Table 1 below shows, summarised at service level, both the revenue position as at the end of September 2023 and the forecast position at year end.
Table 1: Revenue budget monitoring position as at September 2023 Service Working Spend to Variance Working Forecast Variance budget Date budget spend for year to date full year year £000 £000 £000 £000 £000 £000 Strategic management team 442 467 25 872 875 3 Corporate services 1,549 1,591 42 2,987 3,099 112 Development and corporate landlord 700 (273) (973) 997 772 (225) Finance 616 769 153 875 934 59 Housing and environment 2,647 2,092 (555) 6,686 6,430 (256) Legal and democratic 826 852 26 1,605 1,554 (51) Partnerships 1,138 6,077 4,939 2,276 2,276 0 Planning 218 603 385 431 1,061 630 Policy and programmes 3,339 2,536 (803) 6,678 3,846 (2,832) Contingency (312) 6 318 (623) 0 623 Total 11,163 14,720 3,557 22,784 20,847 (1,937)
6. The forecast variance is further broken down in table 2 below.
Table 2: summary of forecast major variances against revenue budget Working Working Forecast Variance Employee Other budget full budget after spend for costs year carry year Service forwards removed £000 £000 £000 £000 £000 £000 Strategic Management 872 872 875 3 (33) 36 Corporate Services 2,987 2,987 3,099 112 (28) 140 Development & Corporate Landlord 997 779 772 (7) (265) 258 Finance 875 875 934 59 71 (12) Housing & Environment 6,686 6,686 6,430 (256) 53 (309) Legal & Democratic 1,605 1,605 1,554 (51) (58) 7 Partnerships 2,276 2,276 2,276 0 0 0 Planning 431 431 1,061 630 (116) 746 Policy & Programmes 6,678 3,926 3,846 (80) (82) 3 Contingency (623) (623) 0 623 723 (100) 22,784 19,813 20,847 1,034 264 770
7. Excluding carry forwards of £2.971 million the projected overspend is forecast to be £1.034 million. Treasury income achieved in year however is anticipated to be ahead of budget by over £2 million and net expenditure is therefore forecast to be under budget.
Budgets forecast to be carried forward to 2024/25
8. As explained above there is forecast to be slippage of £2.971 million in one-off budgets. These will be requested as carry forwards at the end of the financial year. The anticipated carry forwards are shown in appendix 1.
Page 3 Agenda Item 9
Employee costs
9. An overspend of £264,000 in employee costs is forecast:
Development and Corporate Landlord has a £92,000 budget saving to September for facilities salaries which has been extrapolated to year end.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix 1Appendix 1 | 218 KB | Download |
PDF |
Budget monitoring: quarter 2 2023/24Report | 282 KB | DownloadRead as text |
Follow Cabinet at South Oxfordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2026 | Budget monitoring April 2026 - June 2026that Cabinet noted the contents of the report. | Noted | Open |
| 17 Sep 2026 | Nature and Climate Action Plan - Annual 2025/26 performance update and 2026/27 action plan reviewthat Cabinet adopt the updated joint Nature and Climate Action Plan 2025-26 for the delivery year 2026/27. | Approved | Open |
| 17 Sep 2026 | Joint council policy on commemorative benches and treesthat Cabinet: a) Approves the joint policy ‘Commemorative benches and trees’ with no changes. b) Subject to approval ... | Approved | Open |
| 17 Sep 2026 | Car Park Management from 2027a) That Cabinet recommends to Full Council to extend the contract with Saba Park Services UK Limited (Saba) to provid... | Decided | Open |
| 2 Jul 2026 | Waste and street cleansing vehicle selection and procurement policyThat Cabinet: a) Approves the updated waste and street cleansing vehicle selection and procurement policy, which incl... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.