Resolved
RESOLVED – That the Committee considered the progress updates against risk management actions scheduled for quarter four.
Audit, Standards and Risk Committee decided this item on Thursday 18 April 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the Committee considered the progress updates against risk management actions scheduled for quarter four.
This paper is presented to ensure the Audit and Standards Committee has appropriate oversight of MCA strategic risk management arrangements.
Freedom of Information and Schedule 12A of the Local Government Act 1972
Under the Freedom of Information Act this paper and any appendices will be made available under the Mayoral Combined Authority Publication Scheme. This scheme commits the Authority to make information about how decisions are made available to the public as part of its normal business activities.
The Committee is asked to consider the progress updates against risk management actions scheduled for quarter four, and identify any issues.
1. Introduction
1.1The Mayoral Combined Authority Constitution specifies that the Audit and Standards Committee should oversee the effectiveness of the Authority’s risk management arrangements.
1.2SCR MCA’s strategic risk management approach focusses on the effectiveness of, and compliance with, the components of the governance and control framework. This approach was endorsed by the Audit Committee in January 2017. Since then, the Committee has played a key role in ensuring this approach has been embedded and, in monitoring its effectiveness.
1.3Strategic Risks are owned by the Statutory Officers Group and managed through Strategic Risk Management Action Plans. These plans capture the controls already in place to manage the risk, an assessment of whether the controls are adequate and effective, and any further actions required to reduce the likelihood of the risk occurring and to reduce the impact of the risk should it occur. 2. Proposal and justification
2.1Statutory Officers of the Authority ran a workshop with senior members of the SCR Executive Team in December 2018 to refresh the strategic risks and review the actions plans.
2.2A report was presented to the Audit and Standards Committee in January that provided an overview of the key actions that had been identified to manage each strategic risk over the next quarter. This report updates the Committee on the progress of each action. This can be found at appendix A.
2.3A supplementary reading pack of Risk Management Action Plans has been provided for members. Each plan acts as a tool for risk owners and officers to monitor the effectiveness of controls in place to manage each strategic risk, and record any actions identified to provide further mitigation.
2.4Next steps
In line with Mayoral Combined Authority AGM procedures, Risk Owners will be reviewed further to any changes of Statutory Officer responsibilities.
3. Consideration of alternative approaches
3.1SCR’s approach to strategic risk management has been endorsed by the Audit and Standards Committee and approved by the MCA.
4. Implications
4.1Financial
Failure to manage significant risks could result in fines, loss of revenue etc.
4.2Legal
Failure to manage significant risks could result in legal action.
Risk management is vitally important to the successful delivery of SCR MCA / LEP objectives. Therefore, a defined risk management process is a key component of the governance and control framework that underpins this. The Audit and Standards Committee plays a vital role in providing assurance to the MCA of the effectiveness of risk management arrangements.
4.4Equality, Diversity and Social Inclusion
There are no equality, diversity or social inclusion implications. 5. Communications
5.1Strategic risks, and the progress of their management, are communicated internally via Statutory Officer Group meetings, Senior Leadership team meetings and staff briefings.
6. Appendices/Annexes
6.1Appendix A – Update on quarter four risk management actions
REPORT AUTHOR Claire James POST Governance & Compliance Officer Officer responsible Ruth Adams Organisation Sheffield City Region Email [email removed] Telephone 0114 220 3442
Background papers used in the preparation of this report are available for inspection at: 11 Broad Street West, Sheffield S1 2BQ
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Risk Management MonitoringReport | 263 KB | DownloadRead as text |
Follow Audit, Standards and Risk Committee at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Jul 2026 | Appointment of Chair and Vice-Chair, appointments to Transport Risk Working GroupThat Councillor Mike Levery be appointed Chair and David Phillips be appointed Vice-Chair of the Audit, Standards and... | Decided | Open |
| 9 Jul 2026 | Questions from Members of the PublicThat the questions and responses be noted. | Noted | Open |
| 9 Jul 2026 | Terms of ReferenceThat the report be noted. | Noted | Open |
| 9 Jul 2026 | Health and Safety UpdateThat the report be noted. | Noted | Open |
| 9 Jul 2026 | Bus Franchising UpdateThat the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.