SCR Transport Strategy Implementation Plans

Noted Committee 1 paper

SCR - Transport Board noted this item on Friday 25 October 2019. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

That the Board: (i) Note the report. (ii) Approve the Roads Implementation Plan priorities as detailed within the report.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting. Source: governance.southyorkshire-ca.gov.uk

Follow this further

Built from South Yorkshire Mayoral Combined Authority's papers

What the report saysPro

Report to SCR - Transport Board

Purpose of report

This report provides an update on the development of the SCR Transport Strategy Implementation Plans.

Freedom of Information

This paper will be available under the Combined Authority Publication Scheme

Recommendations

The Board are asked to note the approach taken to the development of the Implementation Plans.

The Board are asked to approve the proposed Roads Implementation Plan priorities.

1. Introduction

1.1As reported at previous Transport Board meetings work is underway to develop the future work programmes to take forward the interventions identified within the Transport Strategy. This report provides an update on the progress in developing these implementation plans and the intended timescale for completion.

1.2Following the adoption of the Integrated Rail Plan, work is progressing on the development of the Roads Implementation Plan, the Active Travel Implementation Plan (ATIP) and Mass Transit Implementation Plan. It is proposed that these are now developed at the same time in order to maximise an integrated approach.

1.3The Implementation Plans will reflect the Government’s commitment to achieving a net zero greenhouse gas target by 2050 and the declaration of Climate Emergencies in Local Authorities through a clear articulation of a future where active travel is enabled, where mass transit is supported to be efficient and reliable and the focus of road investment is primarily to enable this.

2. Proposal and justification

2.1Following the adoption of the Transport Strategy, SCR is working through the future work programmes to develop a pipeline of interventions in response to the vision, goals and policies described in the document. The Implementation Plans will provide this scheme level detail which will provide a comprehensive work programme for SCR and local authority partners over the next few years. The plans set out the top ten challenges with the existing rail network in the SCR and the future opportunities and needs. From these challenges and opportunities, a series of objectives have been set along with interventions for delivery that are grouped into the following timeframes; • Interventions that are either committed for delivery, or which we need to see delivered, in the next five years • Interventions for which we aim to complete business cases in the next five years, with the aim of these interventions being delivered from the mid-2020s onwards • Interventions for which we will do more investigation work and develop options for, in the next five years, such that these interventions could be delivered from the late 2020s onwards.

2.4Roads Implementation Plan

In light of rising concerns over climate change, the declaration of climate change emergencies and continued air quality challenges the emerging draft Roads Implementation Plan incorporates new transport priorities which are: - Fit it first - focus on existing roads rather than building new ones; - An integrated approach - redesigning roads to prioritise public transport, walking and cycling - Environmental leadership - and delivering carbon emission reductions, improved air quality and biodiversity. These are adopted from the Campaign for Better Transport’s priorities for improving road networks. The Roads Plan’s amended objectives have been fed back to Local Authority Transport leads for discussion.

Within the Roads Plan the Key Route Network for SCR is also being reviewed, and the scope of that network agreed. The Key Route Network will form an important part of delivering improved bus service outcomes and will be reflected in the Mass Transit Implementation Plan.

Stakeholder engagement is key to developing this document and partners have been asked to add detail regarding the local challenges and opportunities they are aware of, relating to the highway they are responsible for. Once the challenges and amended objectives have been finalised, work can commence on the development of the intervention mapping.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
SCR Transport Strategy Implementation PlansPlan 106 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 19 attended
MD
Mayor Dan JarvisChair, present
CR
Councillor Chris ReadVice-Chair, apologies
DL
Councillor Dave LeechCommittee Member, present
JB
Councillor Joe BlackhamCommittee Member, present
BJ
Councillor Bob JohnsonCommittee Member, absent
SE
Stephen EdwardsCommittee Member, present
PK
Peter KennanCommittee Member, present
AK
Alison KinnaCommittee Member, apologies
ML
Mark LynamCommittee Member, apologies
AL
Alex LintonGuest, in attendance
SN
Sarah NormanCommittee Member, present
CF
Councillor Chris FurnessGuest, in attendance

All 19 on the meeting page

More from South Yorkshire Mayoral Combined Authority SCR - Transport Board

All decisions
MeetingDecisionOutcome
4 Sep 2020 Minutes of the Previous MeetingRESOLVED – That the minutes of the meeting of the Board held on 3 rd July 2020 be agreed as a true record. Agreed Open
4 Sep 2020 Bus Review Response WorkRESOLVED – That the Board approve the approach to delivering the Bus Review Response work programme through the work ... Approved Open
4 Sep 2020 Integrated Rail Plan For The Midlands And The NorthRESOLVED – That the Board approve the Rail Needs Prospectus, attached to the report, for submission to the Department... Approved Open
4 Sep 2020 Roads Implementation Plan And Approach To The Key Route NetworkRESOLVED – That the Board: a) Note the work undertaken to date with the Local Authorities to develop the SCR Roads Im... Noted Open
4 Sep 2020 Dearne Valley Regeneration RouteRESOLVED – That the Board: a) Note the progress made to date in developing the Strategic Outline Business Case. b) Su... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies