SCR - Transport Board, Friday 25 October 2019 at 10.00am

STAF Funding

Approved Committee 2 papers

SCR - Transport Board approved this item on Friday 25 October 2019. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

That the Board approve the continuation of the current projects in the priority order as detailed in paragraph 2.6 of the report, subject to sufficient allocation being granted by DfT.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting. Source: governance.southyorkshire-ca.gov.uk

Follow this further

Built from South Yorkshire Mayoral Combined Authority's papers

What the report saysPro

Report to SCR - Transport Board

Purpose of report

To seek approval for continuation of current STAF activities for 2020-21, utilising extended funding from DfT.

Thematic Priority

5. Develop the SCR skills base, labour mobility and education performance.

Freedom of Information

This paper does not have any exemptions under Part II of the Freedom of Information Act 2000.

Recommendations

Transport Board are asked to approve the continuation of the current projects in the priority order as detailed in paragraph 2.6 subject to sufficient allocation being granted by DfT.

1. Introduction

1.1At the May 22nd 2019 TEB a paper was presented outlining the implications of the current Sustainable Travel Access Fund (STAF) allocation coming to an end in March 2020. At this stage no successor funding opportunity had been offered by DfT and there were no other known sources of revenue funding to continue this scale of cycling, walking, communication, passenger transport and employment connection activity. This presented several issues for Active Travel within the City Region including, but not limited to; loss of skills and knowledge as staff contracts expired, compromising the strength of the Transforming Cities Fund Bid and contradicting the message on how important Active Travel is to the region.

1.2The recommendation of May’s paper was that Executive Board agree the need for continuation of an active travel revenue-based programme, to support the escalation of this need and to support the sourcing of alternative funding. This issue was then included in the paper on Centrally Managed Local Programmes presented to Transport Board on July 19th.

1.3In September and October the DfT Active Travel Programme Management Office have written to advise of their plans to extend the STAF programme for a further twelve months to cover 2020-21. The latest email sent on 1st October advises:

“Our proposal for the continuation of the Access Fund in 2020/21 was agreed at the Cycling & Walking Investment Strategy (CWIS) Programme Board yesterday. In short, we intend to roll over your 2019/20 allocations on a pro-rata basis, subject to i) Ministerial approval and ii) receiving a suitably robust high-level business case. We aim to reduce burdens on you by only asking for additional detail where your programme of interventions will significantly change in comparison to your initial Access Fund proposals, to ensure value for money is no lower than the original bid”.

This paper is asking Board to approve a proposal to use this new allocation to continue Access Fund activities. This proposal has been presented to Transport Executive Board on Monday 14th and was recommended for approval.

1.4The current STAF award for Sheffield City Region is £2.5m per year, if DfT are able to roll over the programme at current levels this figure should be continued for 2020-21.

2. Proposal and justification

2.1The proposal is that, subject to confirmation of allocation levels and grant conditions, activities from within the current STAF programme are continued for another year, to the end of 2020-21. Each individual current project allocation has been categorised as either High, Medium or Low priority for continuation and these should be supported on an incremental scale dependent on the total allocation secured.

2.2If there is enough funding awarded to support all the high priorities these should be committed to. Then if there is sufficient funding to support the medium priorities these should also be committed to. Any further funding awarded could then be considered for continuation of the lower priorities. However at this largest award level consideration could also be given to alternative allocations, either increasing support for existing projects or identifying new activity for addition into the programme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
STAF Programme Future Funding Priority OptionsAppendix A 101 KB Download
PDF
STAF FundingReport 109 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 19 attended
MD
Mayor Dan JarvisChair, present
CR
Councillor Chris ReadVice-Chair, apologies
DL
Councillor Dave LeechCommittee Member, present
JB
Councillor Joe BlackhamCommittee Member, present
BJ
Councillor Bob JohnsonCommittee Member, absent
SE
Stephen EdwardsCommittee Member, present
PK
Peter KennanCommittee Member, present
AK
Alison KinnaCommittee Member, apologies
ML
Mark LynamCommittee Member, apologies
AL
Alex LintonGuest, in attendance
SN
Sarah NormanCommittee Member, present
CF
Councillor Chris FurnessGuest, in attendance

All 19 on the meeting page

More from South Yorkshire Mayoral Combined Authority SCR - Transport Board

All decisions
MeetingDecisionOutcome
4 Sep 2020 Minutes of the Previous MeetingRESOLVED – That the minutes of the meeting of the Board held on 3 rd July 2020 be agreed as a true record. Agreed Open
4 Sep 2020 Bus Review Response WorkRESOLVED – That the Board approve the approach to delivering the Bus Review Response work programme through the work ... Approved Open
4 Sep 2020 Integrated Rail Plan For The Midlands And The NorthRESOLVED – That the Board approve the Rail Needs Prospectus, attached to the report, for submission to the Department... Approved Open
4 Sep 2020 Roads Implementation Plan And Approach To The Key Route NetworkRESOLVED – That the Board: a) Note the work undertaken to date with the Local Authorities to develop the SCR Roads Im... Noted Open
4 Sep 2020 Dearne Valley Regeneration RouteRESOLVED – That the Board: a) Note the progress made to date in developing the Strategic Outline Business Case. b) Su... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies