RESOLVED – That the Board agree to the proposal from the Transport Executive Board for the deferral of ITB funding for five projects and for further work to be done to develop options for the other projected unspent allocations and future business case development funding as detailed within the report.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting.Source: governance.southyorkshire-ca.gov.uk
Follow this further
Built from South Yorkshire Mayoral Combined Authority's papers
To present Board with the outcome of the Integrated Transport Block (ITB) 2019/20 programme review commissioned through Transport Executive Board (TEB), advise of the projected year-end financial position and present TEB’s recommendations for use of funding which is not expected to be spent within the financial year.
Thematic Priority
6. Secure investment in infrastructure where it will do most to support growth
Freedom of Information
This paper does not have any exemptions under Part II of the Freedom of Information Act 2000.
Recommendations
Board are recommended to agree the proposal from TEB for the deferral of ITB funding for five projects that require this to complete works in 2020/21 and for further work to be done to develop options for the other projected unspent allocations and future business case development funding.
1. Introduction
1.1The ITB is an annual allocation paid by DfT for delivery of local transport capital interventions. The settlement is paid to SCR and then distributed to the four South Yorkshire local authorities and SYPTE for delivery.
1.2In May 2019 SCR requested a review of the 2019/20 ITB allocation. This looked at four areas; strategic contribution, internal audit review findings, deliverability and capacity to re-allocate funding to alternative uses. The review was conducted by the LTP Central Team and presented to TEB in July.
1.3The outcome from July’s report was an agreement that a follow up review should be completed providing further scrutiny to the higher risk projects, with this to be presented back to Board at the end of quarter two. Board agreed that any funding that is identified for re-allocation through this process should be placed in a central pot and options for use of it presented to this Board for consideration.
1.4The full ITB programme has been reviewed again by the LTP Central Team in consultation with Strategic Transport Group and project sponsors. This has re-evaluated the projected spend and delivery profiles for the year and produced a revised year-end position for each individual project. 1.5 It is important to note that while every effort has been made to ensure the year-end projections are accurate it is not possible to guarantee these figures and they could be subject to change over the remainder of the year. Project conditions are continually evolving and factors outside the ITB programme delivery will influence the outturn position. For example, variations in the resource requirement for TCF; if the commitment required is lower than expected capacity to commit to ITB will increase, if the TCF requirements increase resources for ITB are likely to be reduced.
2. Proposal and justification
2.1The latest position is that across the ITB programme there are eight projects where the full annual allocation is not expected to be spent within this financial year. Five of these projects have identified that planned works will complete but are going to be deferred into 2020/21. The other three projects have identified that the original planned works will no longer complete, resulting in an unused allocation which could be considered for alternative purposes.
2.2The projects with deferred completion are listed below:
The planned works are for interventions on the A61 corridor which is also within the TCF submission so ITB funded works have been added as match to the TCF package. Resources for 2019/20 are committed to TCF development so the sponsor’s preferred option would be to defer the ITB allocation for delivery in 2020/21.
• Rotherham Local Safety Schemes – Projected unspent allocation £80-100k
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow SCR - Transport Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Dearne Valley Regeneration RouteRESOLVED – That the Board: a) Note the progress made to date in developing the Strategic Outline Business Case. b) Su...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.