Programme Approvals

Approved Committee 5 papers

Mayoral Combined Authority Board approved this item on Monday 16 November 2020. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

RESOLVED – That the MCA approved:- i) The acceptance of a grant from the Department for Transport totalling £40.16m for the A630 Parkway Widening Scheme, and the onward award of that grant to Rotherham MBC. ii) Progression of Heart of the City Breathing Spaces to full approval and award of £4m grant to Sheffield City Council subject to the conditions set out in the Appraisal Panel Summary Table. iii) Progression of Rotherham Town Centre Masterplan to full approval and award of £2.18m grant to Rotherham Metropolitan Borough Council subject to the conditions set out in the Appraisal Panel Summary Table. iv) Progression of Century BIC II to full approval and award of £2m grant to Rotherham Metropolitan Borough Council subject to the conditions set out in the Appraisal Panel Summary Table. v) Progression of iPort Bridge to Full Business Case and award of up to £546k business case development costs to South Yorkshire Passenger Transport Executive subject to the conditions set out in the Appraisal Panel Summary Table. vi) Project change request from “Digital Engineering Skills Development Network” to agree an extension to works completion from September 2020 to September 2021, reprofile of £1.2m grant from 20/21 to 21/22 and reprofile of outputs and outcomes in accordance with the revised timescales. vii) Project change request from “M1 J37 Phase 2” to agree a reprofile of up to £4.07m grant from 20/21 to 21/22 and reprofile of outputs and outcomes in accordance with the revised timescales. viii) Project change request from” M1 J36 Phase 1 (Hoyland)” to agree an extension to works completion from 20/21 to 21/22, reprofile of up to £544k grant from 20/21 to 21/22 and reprofile of outputs and outcomes in accordance with the revised timescales. ix) Project change request from “Greasbrough Road Corridor” to agree an extension to works completion from April 2021 to September 2021 and reprofile of £1.05m from 20/21 to 21/22 and reprofile of outputs and outcomes in accordance with the revised timescales. x) Project change request from “First Group ... view the full minutes text for item 14.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting. Source: governance.southyorkshire-ca.gov.uk

Follow this further

Built from South Yorkshire Mayoral Combined Authority's papers

What the report saysPro

Report to Mayoral Combined Authority Board

Purpose of report

This paper seeks:

1. Approval of three schemes with a total value of £8.18m Getting Building Fund (GBF) and, 2. Approval of one Transforming Cities Fund (TCF) Outline Business Case with a total value of £5,458,141 and early release of up to £546k development funding, 3. Approval of five change requests for existing Local Growth Fund (LGF) projects; 4. Approval for the acceptance of a grant totalling £40.16m for the A630 Parkway Widening Scheme and the onward award of that grant to Rotherham MBC; and, 5. Approval for delegated authority to be granted to the Head of Paid service in consultation with the Section 73 Officer and the Monitoring Officer to enter into legal agreement for the schemes.

Freedom of Information and Schedule 12A of the Local Government Act 1972

The paper will be available under the Combined Authority Publication Scheme.

Recommendations

The MCA consider and approve: 1. The acceptance of a grant from the Department for Transport totalling £40.16m for the A630 Parkway Widening Scheme, and the onward award of that grant to Rotherham MBC 2. Progression of Heart of the City Breathing Spaces to full approval and award of £4m grant to Sheffield City Council subject to the conditions set out in the Appraisal Panel Summary Table attached at Appendix A 3. Progression of Rotherham Town Centre Masterplan to full approval and award of £2.18m grant to Rotherham Metropolitan Borough Council subject to the conditions set out in the Appraisal Panel Summary Table attached at Appendix B 4. Progression of Century BIC II to full approval and award of £2m grant to Rotherham Metropolitan Borough Council subject to the conditions set out in the Appraisal Panel Summary Table attached at Appendix C 5. Progression of iPort Bridge to Full Business Case and award of up to £546k business case development costs to South Yorkshire Passenger Transport Executive subject to the conditions set out in the Appraisal Panel Summary Table attached at Appendix D 6. Project change request from “Digital Engineering Skills Development Network” to agree an extension to works completion from September 2020 to September 2021, reprofile of £1.2m grant from 20/21 to 2122 and reprofile of outputs and outcomes in accordance with the revised timescales 7. Project change request from “M1 J37 Phase 2” to agree a reprofile of up to £4.07m grant from 20/21 to 21/22 and reprofile of outputs and outcomes in accordance with the revised timescales. 9. Project change request from” M1 J36 Phase 1 (Hoyland)” to agree an extension to works completion from 20/21 to 21/22, reprofile of up to £544k grant from 20/21 to 21/22 and reprofile of outputs and outcomes in accordance with the revised timescales 10. Project change request from “Greasbrough Road Corridor” to agree an extension to works completion from April 2021 to September 2021 and reprofile of £1.05m from 20/21 to 21/22 and reprofile of outputs and outcomes in accordance with the revised timescales 11. Project change request from “First Group Customer Contact” to agree an extension to works completion from March 2021 to March 2022, reprofile of £406K grant from 20/21 to 21/22 and reprofile of outputs and outcomes in accordance with the revised timescales 12. Delegated authority be given to the Head of Paid Service in consultation with the Section 73 and Monitoring Officer to enter into legal agreements for the schemes covered above.

1. Introduction

1.1On 30th June 2020 the MCA was awarded £33.6m GBF to invest in ‘shovel-ready’ projects that will provide stimulus to local economies. The funds need to be defrayed by 31st March 2022 which allows an 18-month delivery window.

Guidance received from Government states that Sheffield City Region will be expected to deliver the agreed projects and any significant changes to the projects will be discussed and agreed with the Government in advance. All investment decisions must be undertaken in line with locally agreed audit and scrutiny arrangements.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appraisal Panel Summary Sheffield Heart of the City Breathing SpacesAppendix A 207 KB Download
PDF
Appraisal Panel Summary Rotherham Town CentreAppendix B 295 KB Download
PDF
Appraisal Panel Summary Century BIC IIAppendix C 281 KB Download
PDF
Appraisal Panel Summary iPort BridgeAppendix D 279 KB Download
PDF
Programme ApprovalsReport 177 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 14 attended
MD
Mayor Dan Jarvis MBEChair, present
CR
Councillor Chris ReadVice-Chair, present
GP
Councillor Garry PurdyCommittee Member, apologies
JD
Councillor Julie DoreCommittee Member, present
MR
Mayor Ros Jones CBECommittee Member, present
SS
Councillor Sir Steve Houghton CBECommittee Member, present
SG
Councillor Simon GreavesCommittee Member, apologies
SF
Councillor Steve FritchleyCommittee Member, apologies
TG
Councillor Tricia GilbyCommittee Member, apologies
AD
Councillor Alex DaleCommittee Member, present
JM
James MuirCommittee Member, apologies
MM
Melanie McCooleMinute Taker, in attendance

All 14 on the meeting page

On this subject at South Yorkshire Mayoral Combined Authority

Search all
  1. Programme ApprovalsThis decision
  2. Programme Performance & Approvals ReportApproved
  3. Programme ApprovalsApproved
  4. Programme Performance and Approvals ReportApproved
  5. Programme Performance and Approvals ReportApproved
  6. Programme ApprovalsApproved

More from South Yorkshire Mayoral Combined Authority Mayoral Combined Authority Board

All decisions
MeetingDecisionOutcome
15 Sep 2026 Minutes of the meeting held on 14 July 2026RESOLVED that the minutes of the meeting held on 14 th July 2026 be approved. Approved Open
15 Sep 2026 South Yorkshire Strategy and Proposed Implementation ApproachRESOLVED that the Board endorses: 1. The South Yorkshire Strategy as the shared regional framework. 2. The proposed c... Agreed Open
15 Sep 2026 City Densification FundRESOLVED that the Board: 1. Notes the Government’s allocation of £85m of ing to South Yorkshire. 2. Endorses the prog... Agreed Open
15 Sep 2026 National Housing Development FundRESOLVED that the Board: 1. Welcome the £118,270,000 National Housing Delivery Fund (NHDF) award to SYMCA as part of ... Noted Open
15 Sep 2026 Governance UpdateRESOLVED that the Board: 1. Notes the recommendation of the Overview & Scrutiny Committee at its meeting on 7th July ... Decided Open