AI summarySouth Yorkshire MCA Board approves £11.65m walking and cycling scheme in Doncaster and £2m for University of Sheffield manufacturing start-up programme, plus three revenue grants.
The Board approved progression of Northern Local Centre Improvement to post Outline Business Case in-principle approval and award of £11.65m grant to City of Doncaster Council, subject to conditions in Assurance Summary A. Report P5
The Board approved AMRC Start-up to full approval and award of £2m grant to the University of Sheffield, subject to conditions in Assurance Summary B. Report P5
The Board endorsed submission of a proposal to the Department for Work and Pensions for an Apprenticeship Brokerage Pilot and delegated authority to accept and onward award any subsequent grant. Report P5
Why
The schemes aim to invest in people, businesses and infrastructure in South Yorkshire to deliver economic growth, improve living standards and provide skills for residents. Report P4
The Doncaster scheme addresses severance caused by high traffic on Great North Road and poor walking and cycling links to schools, shops and amenities in the Northern Local Centres. Report P11, P12, P13
The AMRC Start-up programme builds on the FerretWorks pilot to accelerate innovation, commercialisation and business growth, and supports the University of Sheffield Commercialisation Journey. Report P22, P23, P24
What happens next
Officers will enter into legal agreements with funders and project sponsors, with delivery timescales monitored as part of business as usual programme management. Report P47
A delivery plan for the Free Courses for Jobs programme is to be submitted to DBT and DWP by 31st July 2026 following stakeholder engagement. Report P37, P38, P39
The Head of Paid Service, with the Section 73 and Monitoring Officer, is delegated authority to enter into the relevant legal agreements. Report P5
The money
£11.65m Grant to City of Doncaster Council for Northern Local Centre Improvement, at 100% intervention rate against total project costs of £11.65m Report P9, P10
£2m Grant to the University of Sheffield for AMRC Start-up Report P20
c£10m revenue Bid value for the DWP Apprenticeship Brokerage Pilot over three years Report P27, P28
£0.48m Revenue grant from DWP and DBT for Free Courses for Jobs in engineering, clean energy and advanced manufacturing Report P35, P36
£0.17m Regional Investment Framework revenue grant from the Office for Investment for 2026/27 Report P40, P42
Options considered
Chosen: Approve Northern Local Centre Improvement post OBC in-principle approval Report P5
Chosen: Approve AMRC Start-up to full approval Report P5
Chosen: Endorse submission of Apprenticeship Brokerage Pilot proposal to DWP Report P5
Chosen: Accept and onward award £0.48m DWP Free Courses for Jobs revenue grant Report P5
Chosen: Accept £0.17m Regional Investment Framework revenue grant from the Office for Investment Report P5
Implications
Equalities: Equality and diversity implications for capital projects are considered as part of the assurance of project business cases, and for revenue programmes as part of programme development. Report P49
Climate: Climate change implications are considered through the assurance process, with Carbon Impact Assessments included in the business case template for all transport projects. Report P58
Legal: The legal implications of the projects have been considered by a representative of the Monitoring Officer and are included in the recommendations with the relevant Assurance Summaries. Report P55
Financial: Financial and procurement implications are considered on a programme and project basis at the time of business case development. Report P53
Who and where
City of Doncaster Council as project sponsor of Northern Local Centre Improvement Report P9
University of Sheffield as recipient of AMRC Start-up grant Report P20
Residents in Doncaster's Northern Local Centres including Woodlands, Carcroft and Skellow, Norton, Campsall and Askern Report P16, P17
SMEs, training providers, and young people aged 16 to 24 in South Yorkshire, including those who are NEET or at risk of becoming NEET Report P33
University of Sheffield ventures, external founders, and regional manufacturing scale-up businesses Report P22, P23, P24
Timeline
Investment Board 27 May 2026: Earlier consideration of these programmes Report P6
Investment Board 10 June 2026: Earlier consideration of these programmes Report P6
Investment Board 24 June 2026: Earlier consideration of these programmes Report P6
Investment Board 08 July 2026: Earlier consideration of these programmes Report P6
2026/27 Academic Year: Free Courses for Jobs additional places of between 83 and 124 to be delivered Report P36
31st July 2026: Delivery plan for Free Courses for Jobs to be submitted to DBT and DWP Report P39
2026/27: Period covered by the Regional Investment Framework grant allocation Report P42
Plain English for the jargon
OBC: Outline Business Case
AMRC: Advanced Manufacturing Research Centre, a University of Sheffield innovation hub
DWP: Department for Work and Pensions
DBT: Department for Business and Trade
OfI: Office for Investment
RIF: Regional Investment Framework, a flexible RDEL grant administered by the Office for Investment
RDEL: Resource Departmental Expenditure Limit, a category of government revenue spending
FCFJ: Free Courses for Jobs
NEET: Not in Education, Employment or Training
SYMCA: South Yorkshire Mayoral Combined Authority
IS8: A growth potential classification used by the Office for Investment in allocating RIF funding
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item26
Resolved
RESOLVED that the Board: Approved the progression of “Northern Local Centre Improvement” to post Outline Business Case (OBC) in-principle approval and award of £11.65m grant to City of Doncaster Council, subject to the conditions set out in Assurance Summary A. Approved the progression of “AMRC Start-up" to full approval and award of £2m grant, to the University of Sheffield, subject to the conditions set out in Assurance Summary B Endorsed the submission of a proposal of to DWP for “Apprenticeship Brokerage Pilot” and delegate authority to the Executive Director of Growth, Business and Skills, in consultation with the Section 73 and Monitoring Officer to accept and onward award any subsequent grant as detailed in section 2.1 Approved delegated authority to the Executive Director of Growth, Business and Skills, in consultation with the Section 73 and Monitoring Officer for consideration of the following: Approved the acceptance and onward award of £0.48m revenue grant from the Department for Work and Pensions (DWP) for the “Free Courses for Jobs in engineering, clean energy and advanced manufacturing” programme as detailed in section 2.1 Approved the acceptance of £0.17m “Regional Investment Framework (RIF) revenue grant” from the Office of Investment as detailed in section 2.1 Approved delegated authority to the Head of Paid Service in consultation with the Section 73 and Monitoring Officer to enter into legal agreements for the points above
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting.Source: governance.southyorkshire-ca.gov.uk
Follow this further
Built from South Yorkshire Mayoral Combined Authority's papers
1. Progression of 2 investment schemes; 2. Endorsement of 1 submission and; 3. 2 grant acceptances
What does this mean for businesses, people and places in South Yorkshire?
Through the delivery of its funding programmes, SYMCA is investing in the people, businesses and infrastructure of South Yorkshire to deliver economic growth, improve living standards and provide the skills needed for residents to live productive and resilient lives.
Recommendations
That the Board considers: 1. Progression of “Northern Local Centre Improvement” to post Outline Business Case (OBC) in-principle approval and award of £11.65m grant to City of Doncaster Council, subject to the conditions set out in Assurance Summary A. 2. Progression of “AMRC Start-up" to full approval and award of £2m grant, to the University of Sheffield, subject to the conditions set out in Assurance Summary B 3. Endorse the submission of a proposal of to DWP for “Apprenticeship Brokerage Pilot” and delegate authority to the Executive Director of Growth, Business and Skills, in consultation with the Section 73 and Monitoring Officer to accept and onward award any subsequent grant as detailed in section 2.1 4. Delegated authority to the Executive Director of Growth, Business and Skills, in consultation with the Section 73 and Monitoring Officer for consideration of the following: a. Acceptance and onward award of £0.48m revenue grant from the Department for Work and Pensions (DWP) for the “Free Courses for Jobs in engineering, clean energy and advanced manufacturing” programme as detailed in section 2.1 5. Acceptance of £0.17m “Regional Investment Framework (RIF) revenue grant” from the Office of Investment as detailed in section 2.1 6. Delegate authority to the Head of Paid Service in consultation with the Section 73 and Monitoring Officer to enter into legal agreements for the points above
Consideration by any other Board, Committee, Assurance or Advisory Panel Investment Board 27 May 2026 Investment Board 10 June 2026 Investment Board 24 June 2026 Investment Board 08 July 2026
1. Programme Approvals
1.1City Region Sustainable Transport Settlement
Project Sponsor: City of Doncaster Council Scheme Name: Northern Local Centre Improvement Grant Amount - £11.65m Recommendation – Post OBC in-principle approval
This scheme £11.65m against total; project costs of £11.65m at an intervention rate of 100%
This scheme aims to deliver co-designed interventions that address key barriers to increasing walking, wheeling and cycling in Doncaster’s Northern Local Centres. Engagement has shown that public perceptions of safety are low, and the proposed scheme directly tackles these concerns.
High traffic volumes along Great North Road create significant severance between the east and west sides. restricting movement to amenities and green space. Narrow, poor quality walking routes and the absence of a safe continuous cycling infrastructure worsen this effect.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mayoral Combined Authority Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
National Housing Development FundRESOLVED that the Board: 1. Welcome the £118,270,000 National Housing Delivery Fund (NHDF) award to SYMCA as part of ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.