Audit, Standards and Risk Committee agreed this item on Thursday 21 January 2021. Below is the council's own wording, with the papers it was decided on.
It was agreed that a report presenting the proposed MCA budget for 2021/22 which was due to be considered by the MCA on 25th January, be circulated to Members via email after today’s meeting. ACTION: G Sutton. Members were informed that the report also included further detail on the MCA’s Financial Strategy and how the MCA was managing budget risks. RESOLVED – That the Committee:- 1. Note the progress of embedding the revised risk management approach across the organisation. 2. Note the update on strategic risks and identified any issues.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting.Source: governance.southyorkshire-ca.gov.uk
Follow this further
Built from South Yorkshire Mayoral Combined Authority's papers
This paper reports on the progress of embedding the revised approach to risk management and provides an update on strategic risks.
Thematic Priority
Cross cutting.
Freedom of Information
Under the Freedom of Information Act this paper and any appendices will be made available under the Mayoral Combined Authority Publication Scheme. This scheme commits the Authority to make information about how decisions are made available to the public as part of its normal business activities.
Recommendations
Audit and Standards Committee Members are asked to:
• Note the progress of embedding the revised risk management approach across the organisation. • Note the update on strategic risks
and identify any issues.
1. Introduction
1.1Following a full internal Management Board review and an Internal Audit Report in 2020, the risk management framework of the MCA was revised and refreshed. The Audit and Standards Committee endorsed the revised policy and process in October and, following their recommendation, it was approved and adopted by the MCA at their meeting in November. This report informs the Committee on the progress made embed the revised approach across the organisation. In addition, the report provides and update on strategic risk. 2. Proposal and justification
2.1Operationalising the Risk Management Policy and Process Since the endorsement of the new approach by the Audit and Standards Committee and subsequent adoption by the MCA a number of activities and actions have been undertaken to begin to embed the revised risk management approach including:
• Consideration of risk has been embedded into the corporate and business planning process. Risk Champions are working with ‘Business Planners’ to ensure the agreed process is applied appropriately. • • The new Programme Management system under development and currently in ‘build/test phase’ has functionality for recording and monitoring risk for all projects and programmes which is aligned to the agreed risk management approach. • • The MCA board paper template has been re-developed to encourage better consideration of risk and regular risk sessions have been built into the Management Board meeting schedule. • Next steps • The business planning process will conclude by the end of Q4, at which point the plans will become operational. At this point the risk register developed during the developmental stages will become the register for the relevant programme of work and will be reviewed and reported on in line with the Risk Management Policy and Process. • • Work will continue on the new Programme Management system to ensure alignment to the agreed approach. • • Risk sections of Business Case documentation will be reviewed to ensure alignment to the agreed approach. • • A staff training/induction module and a dedicated area on the intranet will be developed. • 2.2 Strategic Risk Update The table below provides a summary of the five strategic risk categories. Revised Risk Management Actions Plans are provided at appendix A-E.
Budget Gov & Strategy Org & Fin Prog Comp Focus M'Mt M'Mt M'Mt M'Mt Total
No. of risks in category 5 5 8 7 9 34 Overall/average mitigated probability score P4 2.2 3.375 3 2.1111 Overall/average mitigated impact score 3 2.5 3.4286 3 2.3333 Overall/average mitigated risk score 14.667 5.5 11.571 9.6 4.9259 No. of highly probable risks 1 0 2 0 0 3 No. of new risks added since last report 1 1 0 0 2 No. of risks closed since last report 0 0 0 0 0 0 No. of open actions 6 3 4 3 4 20 No. of actions overdue 3 1 0 2 2 8
2.3Risk Category – Strategy Focus (appendix A) The Risk Management Action Plan continues to have a red risk linked to the strategy for the long-term sustainability of public transport. Despite some additional resource being allocated from central government, this remains a high rated risk. An additional risk (#5) has been added relating to the capacity in the system to develop and deliver an expanding and complex programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Audit, Standards and Risk Committee at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.