Transforming Cities Fund and Intra City Transport Fund
AgreedCommittee1 paper
MCA - Transport and the Environment Board agreed this item on Thursday 4 March 2021. Below is the council's own wording, with the papers it was decided on.
RESOLVED – That the Board:- i) Discussed the findings of the TCF Programme review. ii) Agreed the proposed remedial actions for the TCF Programme as detailed in section 2.4 of the report. iii) Agreed the proposed approach to the flexible management of capital programmes in relation to the end of the TCF Programme and the start of investment from the Intra-City Transport Fund as detailed in Section 2.5 of the report. iv) Endorsed the creation of a prioritised pipeline of transport schemes in anticipation of the ICTF programme for consideration at a future TEB meeting.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting.Source: governance.southyorkshire-ca.gov.uk
Follow this further
Built from South Yorkshire Mayoral Combined Authority's papers
Report to MCA - Transport and the Environment Board
Purpose of report
This report provides a progress update on the Transforming Cities Fund Tranche 2 (‘TCF Programme’) review and the new Intra-City Transport Fund
Thematic Priority
Secure investment in infrastructure where it will do most to support growth
Freedom of Information
This paper will be available under the Combined Authority Publication Scheme
Recommendations
• To discuss the findings of the TCF Programme review • Agree the proposed remedial actions for the TCF Programme as detailed in 2.4 below • Agree the proposed approach to the flexible management of capital programmes in relation to the end of the TCF Programme and the start of investment from the Intra City Transport Fund as detailed in 2.5 below • To endorse the creation of a prioritised pipeline of transport schemes in anticipation of the ICTF programme for consideration at a future TEB meeting.
1. Introduction
1.1In March 2020 the Department for Transport (‘DfT’) approved a grant award of £166.3m for the MCA’s Transforming Cities Fund Tranche 2 programme (‘TCF Programme’) aspirations. This grant was allocated from April 2019 to March 2023 resourcing a programme of transformational public transport, active travel and rail initiatives.
1.2By September 2020 a TCF Programme review had commenced to test deliverability of the Programme against funding timelines. This review identified a number of concerns around the pace of activity and the ability of a number of schemes to complete within the funding deadline of March 2023. Addressing the findings of that exercise, the TEB approved the following recommendations - • MCA to support promoters in business case development and managing resource capability • Consider phased delivery for bigger projects • Develop a pipeline and an over programming position • Integration of the risk pot into project costs
1.3This report details - • the outcome of the TCF Programme review and proposed remedial actions • an update on early discussions with DfT and HM Treasury (‘HMT’) officials on the interface between the TCF Programme and the new Intra City Transport Fund (‘ICTF’), including a proposal to gain some flexibility between funds in order to support the delivery of transformational TCF Programme schemes as well as develop a robust pipeline of schemes for the new fund.
2. Proposal and justification
TCF Programme Review
2.1In undertaking the second TCF Programme review, 3 strands of activity were focused on: 1. Delivery progress 2. Delivery confidence 3. Proposed remedial actions Meetings were held with promoters to discuss the granular detail of the review returns and strategic priorities. The findings of the review are summarised in sections 2.2 and 2.4 below.
2.2Delivery Progress Claims totalling c.£0.9m and 12 business cases have now been submitted. However, as the pace of grant drawdown and the passage of business cases through assurance gateways has been slower than forecast, programme risk subsequently remains high.
In summary - • Since the release of development costs was approved in June 2020, 20% of the contracts remain unsigned and c.31% of the available £2.9m has been claimed • Of the 2020/21 baseline expenditure target of £29.3m, c.£4.2m (c.14%) spend is now forecast, with the claims submitted to date equating to c.3% against the baseline • Nine (c.43%) of the Outline Business Cases due in 2020/21 have been received, with two approved. Three Full Business Cases have also been received in 2020/21, with one approved. The forecast submission profiles are -
2.3Delivery Confidence The TCF Programme review indicates that without further mitigation the DfT Baseline spend target of £166.3m will be missed by £3.2m.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow MCA - Transport and the Environment Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Extension to the £2 Fare Cap on TramRESOLVED that the Board: 1. Approve the extension of the £2 fare cap on tram consistent with the timescales of the na...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.