Resolved
RESOLVED – That the Board approve the current TCF Monitoring and Evaluation and Benefits Realisation Plans as the frameworks for assessing the performance and learning from the TCF programme.
MCA - Transport and the Environment Board approved this item on Thursday 7 January 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the Board approve the current TCF Monitoring and Evaluation and Benefits Realisation Plans as the frameworks for assessing the performance and learning from the TCF programme.
To endorse the Transforming Cities Fund - Benefits Realisation and Monitoring and Evaluation Plans.
Thematic Priority
Secure investment in infrastructure where it will do most to support growth.
That members of the Transport Board:
• Approve the current TCF Monitoring and Evaluation and Benefits Realisation Plans as the frameworks for assessing the performance and learning from the TCF programme.
1. Introduction
1.1The Strategic Outline Business Case (SOBC) for the Transforming Cities Fund (TCF) programme was submitted to the Department for Transport (DfT) on 27th November 2019. The subsequent acceptance of the £166m grant from DfT was reported at the MCA meeting on 1st June 2020.
1.2The following objectives were defined for the TCF programme:
• To better connect the areas of transport poverty with areas of opportunity in a safe and sustainable way • To affect a mode shift away from the private car on those corridors where new opportunities are likely to see an increase in demand or where growth could be stifled • To create a cultural shift towards making cycling and walking the natural choice for shorter journeys • To achieve the above in ways that address current health issues and improve air quality across the SCR
1.3As part of the TCF guidance from the DfT, there was an expectation that bidders would monitor and evaluate programme interventions as both the Department and city regions have a shared interest in evaluating the effectiveness of the fund over time. This requirement is in line with the MCA’s current agreed Assurance Framework. 1.4 The shape for the national TCF programme evaluation is still being developed by the DfT, but guidance was provided for the bid submission and suggested a general outline for monitoring and evaluation based around five elements:
• Establish a ‘theory of change’ for interventions • Develop a counterfactual (usually a before and after study) • Collect baseline data • Plan what monitoring is needed • Plan for data
1.5The basis of the TCF Benefits Realisation and associated Monitoring and Evaluation plans were included in the November 2019 submission to DfT and have since been developed in partnership with Local Authority and PTE scheme promoters.
2. Proposal and justification
2.1Monitoring and evaluation of the TCF programme helps to ensure the benefits of the investment are fully realised and the programme is value for money in terms of delivering economic growth and quality of life outcomes that can be demonstrated.
2.2The TCF Benefits Realisation and Monitoring and Evaluation Plans are ‘live’ documents that will change over time to respond to programme or policy changes. For example, there will be a need to reaffirm links into the wider Active Travel Implementation Plan monitoring and evaluation plan currently under development. Therefore, the MCA Exec will review and, where required, update the monitoring and evaluation plan to ensure it remains in accordance with other relevant plans and objectives.
2.3The programme of monitoring and evaluation needs to demonstrate the extent to which the TCF objectives were met, monitor performance of the individual elements of the programme and ensure that any potential issues post implementation are identified and addressed. The plans also seek to enable an assessment of the entire TCF programme whilst providing flexibility to define more bespoke monitoring and evaluation plans for the individual packages that will be delivered. The process will also enable the MCA to:
• Provide transferable evidence that may be used to inform future decision making on similar investment programmes • Improve the efficiency and effectiveness in the delivery of future investment programmes based on the lessons learnt from the programme
2.4The following sections consider the two documents in more detail.
Benefits Realisation Plan
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Benefits Realisation Plan: Objectives, Outputs, Outcomes and ImpactsAppendix 1 | 9 KB | Download |
PDF |
Benefits Realisation Plan: Full documentAppendix 2 | 543 KB | Download |
PDF |
Monitoring and Evaluation plan: Key outcome and impact metricsAppendix 3 | 168 KB | Download |
PDF |
Monitoring and Evaluation plan: Full documentAppendix 4 | 2.5 MB | Download |
PDF |
Transforming Cities Fund: Benefits Realisation and Monitoring and Evaluation PlanReport | 157 KB | DownloadRead as text |
Follow MCA - Transport and the Environment Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Mar 2023 | Extension to the £2 Fare Cap on TramRESOLVED that the Board: 1. Approve the extension of the £2 fare cap on tram consistent with the timescales of the na... | Approved | Open |
| 17 Mar 2023 | Minutes of the Last MeetingRESOLVED that the minutes of the meeting held on 9 February be approved. | Approved | Open |
| 17 Mar 2023 | Matters Arising / Action LogRESOLVED that the Action Log be noted. | Noted | Open |
| 17 Mar 2023 | Transport UpdateRESOLVED that the Transport Update be noted. | Noted | Open |
| 17 Mar 2023 | Bus Recovery Grant ExtensionRESOLVED that Transport and Environment Board members: Note the recent funding extension by DfT of Bus Recovery Grant... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.