MCA - Housing and Infrastructure Board approved this item on Tuesday 7 December 2021. Below is the council's own wording, with the papers it was decided on.
RESOLVED – That the Board approve:- i) Progression of “ Lundwood Flood Alleviation Scheme (FAS)” project to proceed to OBC (Outline Business Case) for Gainshare Funding to BMBC (Barnsley Metropolitan Borough Council) subject to the conditions set out in the Assurance Summary attached at Appendix A ii) Progression of “Snail Yard” project to proceed to OBC for Gainshare Funding to RMBC (Rotherham Metropolitan Borough Council) subject to the conditions set out in the Assurance Summary attached at Appendix B. iii) Progression of “Heart of the City 2 (block A)” project to MCA to proceed to FBC (Full Business Case) for Gainshare Funding for SCC (Sheffield City Council) subject to the conditions set out in the Assurance Summary attached at Appendix C. iv) Approval of two changes for “West Bar” and “Goldthorpe” which are requesting changes to their approved BHF projects. Delegated authority be given to the Head of Paid Service in consultation with the Section 73 and Monitoring Officer to enter into legal agreements for the schemes 1 – 4 covered above.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting.Source: governance.southyorkshire-ca.gov.uk
Follow this further
Built from South Yorkshire Mayoral Combined Authority's papers
Assurance Summary Scheme Details Project Name Lundwood Flood Alleviation Scheme Type of funding Grant Grant Recipient BMBC Total Scheme Cost £1,307,000 MCA Executive Board Housing and Infrastructure MCA Funding £150,000 Programme name Gainshare % MCA Allocation 11.47%
Part A - Appraisal Summary Strategic Case Project rationale This funding request has been determined within the context of regional need following the 2019 flood event and the subsequent South Yorkshire Flood Priority Programme. This scheme has been identified as one of 8 shovel ready schemes needed to provide improved flood mitigation for some of the most vulnerable residents. This area has been subject to recurring flood events, suffering extensively in 2007, 2012 and 2019.
The project description is unclear and not well defined within the business case and therefore it is not clear what the MCA is being asked to fund.
At different points in the business case the project is defined as the designing of a capital scheme to mitigate flood risk and at other points it is defined as actual physical works to be undertaken on site, as below:
“This project is to provide match funding for the next stage of developing and designing a capital scheme to mitigate / minimise future flood risk… Once designed, the capital scheme is likely to be funded through a mix of EA Grant in Aid and Council resources”
“MCA support is required to progress the on site clearance and repair works of key drainage assets to afford improved protection to local property and businesses…The funding will be used to progress on site exposure of the drainage assets, re-cutting of existing drainage ditches (500m+), removal of vegetation and clearance of the culvert assets including any necessary repairs.”
“The development phase of the project is due to be complete by December 2021. Further timetables will be dependent on the preferred solution.”
If these are preparatory/investigative works required to begin designing the project, this should be explained.
Strategic fit Complete Annex 1 at the end of this form.
Proposed outcomes Short term: measures to address imminent threat from surface water flooding. Long term 90 properties move from high to moderate flood risk
Value for Money The applicant has not been able to put forward an Economic Case for the project. Benefits have not been quantified in economic terms and are expressed at a very basic level. This needs to be discussed and agreed with the MCA Exec prior to the submission of the OBC.
Risk Top 5 risks as presented in the business case:
1. Unforeseen Ground Conditions (Likelihood: Low / Impact: High) 2. Not securing the funding required (Likelihood: Low / Impact: Med) 3. Delays due to adverse weather, the scheme may be affected by further flooding event (Likelihood: Med / Impact: Med) 4. Availability of materials and resources, including labour (Likelihood: Med / Impact: Med) 5. Issues with tendering and appointing contractors (Likelihood: Low / Impact: Med)
Some of the measures proposed to mitigate these risks appear reasonable. These include, risk contingency, agreements in place for majority of funding. However, some mitigations are a confusing and not well explained. These include, extended lead times for material and for tendering/appointing contractors factored into timescales. Given the project is due to complete in Dec 2021 these appear unrealistic.
In addition to the above, although the project is only at SBC stage, cost certainty is still very low at 30%, given the works completion date of Dec 2021. Costs and timescales are therefore likely to change.
Delivery
According to the business case, works have already commenced and due for complete Dec 2021. Therefore, project is likely to complete before approval of MCA funds. Evidence of need therefore needs to be set out accordingly.
Legal
No satisfactory Subsidy Control opinion has been provided. The applicant has not been able to adequately explain why the project is Subsidy Control compliant.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow MCA - Housing and Infrastructure Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.