MCA - Education, Skills and Employability Board approved this item on Tuesday 8 March 2022. Below is the council's own wording, with the papers it was decided on.
RESOLVED – That the Board consider and approves: i) Progression of an extension and variation to the existing agreement with Calderdale College for the continuation of Skills Bank Extension of “Skills Bank Interim programme”. Delegated authority be given to the Head of Paid Service in consultation with the Section 73 and Monitoring Officer to enter into a legal agreement for the scheme above.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting.Source: governance.southyorkshire-ca.gov.uk
Follow this further
Built from South Yorkshire Mayoral Combined Authority's papers
Report to MCA - Education, Skills and Employability Board
Executive summary
This paper seeks approval for an extension and variation of an existing agreement with Calderdale College for the continuation of delivery of the current Skills Bank Programme until the new programme is fully operational. The paper also seeks approval for delegated authority to be granted to the Head of Paid service in consultation with the Section 73 Officer and the Monitoring Officer to enter into legal agreement for the schemes.
What does this mean for businesses, people and places in South Yorkshire?
This report is seeking approval to extend the existing skills Bank which will support the MCA’s aspirations and provide support needed to enable businesses upskill their workforce which, for some, is critical in planning for future growth whilst recovering from the impact of the pandemic
Recommendations
The board consider and approve: 1. Progression of an extension and variation to the existing agreement with Calderdale College for the continuation of Skills Bank Extension of “Skills Bank Interim programme”. 2. Delegated authority be given to the Head of Paid Service in consultation with the Section 73 and Monitoring Officer to enter into a legal agreement for the scheme above 1. Background
1.1On the 2nd March 2021 the board agreed for interim arrangements to be explored to enable the current Skills Bank programme to continue until the new Skills Bank programme had been developed and implemented.
1.2Skills Bank was originally delivered on behalf of the MCA by Calderdale College who were recruited through a full procurement exercise in 2018. They were contracted directly with the ESFA with a separate contract in place for the MCA element of the programme. The contract between the MCA and Calderdale College was extended to June 2022 with all training to have commenced by March 2022.
2. Proposal and Justification
2.1The current Skills Bank programme is currently performing well against its contracted outputs. Despite the difficulties experienced from the Covid-19 pandemic demand remains high with over 107 business applications received and 998 learners approved for training with 273 already supported so far this year.
2.2So far this year (21/22) £386k has been invested in training support from Skills Bank funds along with £412k employer contributions and the programme is on track to fully achieve programme outputs. Pipeline activity means we also have the potential to considerably overachieve on learner starts.
2.3All training in the interim model is to have commenced in March 2022 but due to completion of the current Skills Bank procurement exercise this report is seeking approval to extend the programme for a further 3 months which would require a further investment of £188k. This would enable the programme to continue the offer to businesses without a break in provision.
3. Options Considered and Recommended Proposal
3.1Option 1
Do not approve the recommendations in this report.
3.2Option 1 Risks and Mitigations
If the Skills Bank programme were to close at the end of March this would leave many businesses without the support needed to upskill their workforce which, for some, is critical in planning for future growth whilst recovering from the Impact of the pandemic.
3.3Option 2
Approve the recommendation.
3.4Option 2 Risks and Mitigations
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow MCA - Education, Skills and Employability Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.