MCA - Transport and the Environment Board approved this item on Thursday 1 September 2022. Below is the council's own wording, with the papers it was decided on.
That the Board considered and endorsed: 1. The progression of ‘T0003 A61 Royston Active Travel Scheme’ Full Business Case (FBC) to the MCA for full approval and award of £5.2m grant to Barnsley Metropolitan Borough Council (BMBC) subject to the conditions set out in the Assurance Summary attached at Appendix A1. 2. The progression of ‘T0012 A635 Active Travel Scheme’ FBC to the MCA for full approval and award of £2.4m grant to Barnsley Metropolitan Borough Council (BMBC) subject to the conditions set out in the Assurance Summary attached at Appendix A2. 3. The change requests of ‘L0039 A630 Parkway Widening’ and ‘T0024 Parkgate’. 4. That delegated authority should be given to the Head of Paid Service in consultation with the Section 73 and Monitoring Officer to enter into legal agreements for the schemes considered above.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting.Source: governance.southyorkshire-ca.gov.uk
Follow this further
Built from South Yorkshire Mayoral Combined Authority's papers
Report to MCA - Transport and the Environment Board
Executive summary
This paper requests endorsement to progress 2 schemes for full approval at the MCA Board subject to the conditions set out in the Assurance Summaries.
The paper also requests delegated authority to enter into necessary legal agreements for the schemes.
What does this mean for businesses, people and places in South Yorkshire? This report is seeking approval to progress business cases and enter into contract for a number of investment proposals which will support the MCA’s aspirations.
Recommendations The Board consider and endorse: 1. Progression of ‘T0003 A61 Royston Active Travel Scheme’ Full Business Case (FBC) to the MCA for full approval and award of £5.2m grant to Barnsley Metropolitan Borough Council (BMBC) subject to the conditions set out in the Assurance Summary attached at Appendix A1.
2. Progression of ‘T0012 A635 Active Travel Scheme’ FBC to the MCA for full approval and award of £2.4m grant to Barnsley Metropolitan Borough Council (BMBC) subject to the conditions set out in the Assurance Summary attached at Appendix A2.
3. Delegated authority be given to the Head of Paid Service in consultation with the Section 73 and Monitoring Officer to enter into legal agreements for the schemes covered above.
Consideration by any other Board, Committee, Assurance or Advisory Panel Assurance Panel 20 July 2022 Assurance Panel 19 August 2022
Background
1.1This report seeks approval for the progression of 2 fully funded schemes and will be resourced from previously committed TCF2 grant funding, and approval of 2 change requests.
1.2Progression of schemes to full approval and award of funding
The paper is seeking progression of 2 schemes to MCA for full approval, contract and award of funding. The total amount of funding requested for both schemes is £7.6m grant for schemes located in Barnsley.
Full details of the schemes and risks are included in Appendix A.
1.3Project Change Requests
In recognition of unforeseen circumstances that can arise during the project delivery phase, the approved Assurance Framework establishes a formal process for the acceptance of change requests. These change requests could be financial, requiring reprofiling of funds, or could be to amend deliverables or timescales.
Details of the 2 change requests can be found in Appendix B
2. Options Considered and Recommended Proposal
2.1Option 1 Do not approve the recommendations in this report.
2.2Option 1 Risks and Mitigations Inability to approve the projects presented or release funding may result in the delivery and loss of activity/spend to the programmes. 2.3 Option 2 Award projects a smaller amount of grant funding.
2.4Option 2 Risks and Mitigations: All funding awards associated with the projects have been fully appraised in line with the SYMCA Assurance Framework to ensure value for money. Funding for these projects is timebound by the funding bodies and any deliverability issues will be managed via alternative funding sources.
2.5Option 3 Approve all recommendations
2.6Option 3 Risks and Mitigations: By approving the recommendations, the available programme funding will reduce. However, the projects were included in the bids submitted to the funding bodies and/or are considered a strong strategic fit in line with investment aims.
2.7Recommended Option Option 3
3. Consultation on Proposal
3.1Project sponsors are required to publish business cases on their websites (or an appropriate summary of the submission) and must consider all comments received and reflect this in the stages of the application process.
4. Timetable and Accountability for Implementing this Decision
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow MCA - Transport and the Environment Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Extension to the £2 Fare Cap on TramRESOLVED that the Board: 1. Approve the extension of the £2 fare cap on tram consistent with the timescales of the na...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.