Resolved
RESOLVED that Board members: Consider the performance information provided to identify future performance deep-dives or significant areas of risk.
MCA - Transport and the Environment Board decided this item on Thursday 27 October 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that Board members: Consider the performance information provided to identify future performance deep-dives or significant areas of risk.
Transport and the Environment Board
27 October 2022
Programme Performance
Is the paper exempt from the press No and public?
Purpose of this report: Monitoring/Assurance
Is this a Key Decision? No
Has it been included on the Yes Forward Plan?
Director Approving Submission of the Report: Gareth Sutton, Chief Finance Officer/s73 Officer
Report Author(s): Sue Sykes – Assistant Director – Procurement, Contracts and Programme Controls [email protected]
Executive Summary This report provides the Board with the latest performance information on Transport and Environment capital programmes being delivered on behalf of the MCA. The report is intended to support oversight and scrutiny.
What does this mean for businesses, people and places in South Yorkshire? The MCA’s investment in South Yorkshire’s travel and transport infrastructure is critical to delivering upon the region’s broader aspirations. Performance information supports the robust oversight and management of this delivery.
Recommendations That Board members: Consider the performance information provided to identify future performance deep-dives or significant areas of risk;
Consideration by any other Board, Committee, Assurance or Advisory Panel None 1. Background
1.1The South Yorkshire Mayoral Combined Authority currently has one hundred and thirty-eight projects which fall within the remit of the Transport and the Environment Board. The schemes are resourced from various funding streams with an aggregate value of £749.23m.
This report gives an overview on the performance of programmes and the projects within them, highlighting management actions being taken to mitigate risks.
1.2The expenditure baseline for 22/23 was initially set at £238.86m with the latest forecasts suggesting outturn expenditure of £158.89m. This level of expenditure will generate a material underspend of £79.97m (33.5%).
2. Current Position by Funding Stream
2.1The table presented below highlights the forecast full-year expenditure profiles set against the baseline targets. The table highlights underspend across the funded programmes of activity, cumulatively totalling £79.97m
2022/23 2022/23 2022/23 Funding Stream Baseline Forecast Variance (£m) (£m) (£m)
CRSTS £41.10 £40.35 -£0.75 Active Travel 2 (ATF2) Cap £4.27 £4.27 £0.00 Active Travel 2 (ATF2) Rev £1.00 £1.00 £0.00 Active Travel Gainshare £1.73 £1.73 £0.00 Transforming Cities Fund 2 (TCF2) £146.26 £70.26 -£76.00 Legacy LGF incl. Retained Major £23.12 £23.12 £0.00 Gainshare £4.90 £4.90 £0.00 Active Travel 3 £0.00 £2.59 £2.59 Capability Fund £1.10 £1.10 £0.00 Mayors Transport fund £12.00 £9.00 -£3.00 Restoring your Railways £0.08 £0.08 £0.00 ZEBRA £0.00 £0.00 £0.00 STAF £0.49 £0.49 £0.00 £238.86 £158.89 -£79.97
The TCF and ATF2 baseline targets are set by government, requiring in-year allocations to be fully defrayed within the financial year. There is no comparative grant conditionality timeline pressure on Gainshare funding, the legacy LGF activity, nor the Retained Major funding for the Parkway widening scheme. The pace of the capital programme in this thematic area has been reported as a concern previously, with performance now likely to be beyond complete mitigation in a number of areas.
Of particular concern is the underspend and delays in Business case submission on the TCF and Active Travel Fund programmes where underspend is reported across all delivery partners, largely reflecting both the challenging timetable and known pressures across the supply chain and labour market.
The TCF programme consists of 32 schemes. Based on schemes in delivery and latest forecast business case submission dates, 7 schemes are forecast to complete this financial year, with a further 13 to commence delivery this financial year, but not complete until next financial year. The final 13 schemes are not forecast to start delivery until next financial year and will complete thereafter.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Programme PerformanceReport | 567 KB | DownloadRead as text |
Follow MCA - Transport and the Environment Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Mar 2023 | Extension to the £2 Fare Cap on TramRESOLVED that the Board: 1. Approve the extension of the £2 fare cap on tram consistent with the timescales of the na... | Approved | Open |
| 17 Mar 2023 | Minutes of the Last MeetingRESOLVED that the minutes of the meeting held on 9 February be approved. | Approved | Open |
| 17 Mar 2023 | Matters Arising / Action LogRESOLVED that the Action Log be noted. | Noted | Open |
| 17 Mar 2023 | Transport UpdateRESOLVED that the Transport Update be noted. | Noted | Open |
| 17 Mar 2023 | Bus Recovery Grant ExtensionRESOLVED that Transport and Environment Board members: Note the recent funding extension by DfT of Bus Recovery Grant... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.