Resolved
RESOLVED that the Board consider the performance information provided: 1. To advise on any additional information that would assist in monitoring performance; and, 2. To identify future performance deep-dives or significant areas of risk.
MCA - Transport and the Environment Board decided this item on Thursday 15 December 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Board consider the performance information provided: 1. To advise on any additional information that would assist in monitoring performance; and, 2. To identify future performance deep-dives or significant areas of risk.
1.1The South Yorkshire Mayoral Combined Authority currently has 86 projects within the TCF and CRSTS programmes with an aggregate value of £621.54m.
This report gives an overview on the performance of programmes and the projects within them, highlighting management actions being taken to mitigate risks.
2. Current Position by Funding Stream
2.1TCF2 TCF is a £166m programme that was announced in March 2020, shortly before the nation moved into pandemic related restrictions.
Previous reporting has flagged issues with the pace of the TCF programme. These issues largely reflect the early stage of development of schemes at the time of bidding; the challenging delivery timetable; and known pressures across the supply chain and labour market following the pandemic. These issues are prevailing across the nation and are exacerbated by the inflationary environment.
Whilst progress has been a concern more schemes are now beginning to move into the contracting and delivery stages.
The programme now consists of 34 schemes with: 4 (12%) schemes in delivery with a value of £11.75m; 11 (32%) schemes fully approved and going into contract with a value of £57.52m; 5 (15%) schemes undergoing final assurance ahead of submission for approvals; and, 13 (38%) schemes remain in development.
The current forecast expenditure for the current financial year is £59.51m. This is significantly behind the base budget of £137m.
A number of barriers to delivery have now been removed following the agreement at Board to give more local flexibility to partners to manage their project pressures within programme funding envelopes. This has enabled some projects to progress whilst facing challenging inflationary pressures, offsetting against underspends elsewhere. A number of schemes have identified pressures that continue to be monitored.
Concerns around the region’s ability to deliver all its TCF2 activity by March 2023 – the initial funding window – have now abated as the final tranche of TCF funding (£72m) is rolled into the new five-year City Region Sustainable Transport Settlement (CRSTS).
The MCA continues to enjoy good collaboration from partners, with mitigations being considered across a number of projects. The MCA also continues to work with Government to identify compliant flexibilities that could be applied to support the delivery of projects in full.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
13i Appendix AAppendix | 415 KB | Download |
PDF |
13ii Appendix BAppendix | 453 KB | Download |
PDF |
Programme PerformanceReport | 518 KB | DownloadRead as text |
Follow MCA - Transport and the Environment Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Mar 2023 | Extension to the £2 Fare Cap on TramRESOLVED that the Board: 1. Approve the extension of the £2 fare cap on tram consistent with the timescales of the na... | Approved | Open |
| 17 Mar 2023 | Minutes of the Last MeetingRESOLVED that the minutes of the meeting held on 9 February be approved. | Approved | Open |
| 17 Mar 2023 | Matters Arising / Action LogRESOLVED that the Action Log be noted. | Noted | Open |
| 17 Mar 2023 | Transport UpdateRESOLVED that the Transport Update be noted. | Noted | Open |
| 17 Mar 2023 | Bus Recovery Grant ExtensionRESOLVED that Transport and Environment Board members: Note the recent funding extension by DfT of Bus Recovery Grant... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.