Report to MCA - Transport and the Environment Board
Executive summary
This report provides the Board with the latest performance information on the Transforming Cities Fund 2 (TCF2) and City Region Sustainable Transport Settlement (CRSTS) programmes being delivered on behalf of the MCA. The report is intended to support oversight and scrutiny.
The report notes developments on the TCF programme and the good early progress on the CRSTS programme.
What does this mean for businesses, people and places in South Yorkshire?
The MCA’s investment in South Yorkshire’s travel and transport infrastructure is critical to delivering upon the region’s broader aspirations. Performance information supports the robust oversight and management of this delivery. Recommendations
That Board members consider the performance information provided: 1. To advise on any additional information that would assist in monitoring performance; and, 2. To identify future performance deep-dives or significant areas of risk.
Consideration by any other Board, Committee, Assurance or Advisory Panel
None
Background
1.1The South Yorkshire Mayoral Combined Authority currently has 115 projects within the TCF and CRSTS programmes with an aggregate value of £736.30m.
This report gives an overview on the performance of programmes and the projects within them, highlighting management actions being taken to mitigate risks.
2. Current Position by Funding Stream
2.1TCF2 TCF is a £166m programme that was announced in March 2020, shortly before the nation moved into pandemic related restrictions.
Previous reporting has flagged issues with the pace of the TCF programme. These issues largely reflect the early stage of development of schemes at the time of bidding; the challenging delivery timetable; and known pressures across the supply chain and labour market following the pandemic. These issues are prevailing across the nation and are exacerbated by the inflationary environment. £7.25m was included within CRSTS to enable some of the larger, transformational schemes to progress which is included in the figures provided in Appendix 1.
Whilst progress has been a concern more schemes are now beginning to move into the contracting and delivery stages (53%).
The programme now consists of 32 schemes. 11 (34%) schemes in delivery with a value of £52.30m – an increase of £40.55m since the last report. 6 (18%) schemes fully approved and going into contract with a value of £13.62m; 1 scheme undergoing final assurance ahead of submission for approvals; and, 12 (37.5%%) schemes remain in development.
Following the agreement at Board to give more local flexibility to partners to manage their project pressures within programme funding envelopes has enabled some schemes facing inflationary pressures to progress. The current forecast expenditure for the current financial year is £62.12m. This is significantly behind the base budget of £137m. The programme level forecast against original profile is included in the graphs in Appendix A
2.2CRSTS CRSTS has 66 schemes within the programme with an aggregated value of £482.19m. The settlement was announced by Government at £570m reflecting the final year of the TCF being rolled into the CRSTS settlement period.
Good progress has been made in the delivery of this programme: • 10 schemes (15%) are fully approved or already in delivery; • 5 schemes (8%) are developing their full business cases (FBC); and, • 51 schemes (77%) are in early development.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow MCA - Transport and the Environment Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Extension to the £2 Fare Cap on TramRESOLVED that the Board: 1. Approve the extension of the £2 fare cap on tram consistent with the timescales of the na...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.