Resolved
that the Board: 1. Approve a SYMCA led p roject change request for “Z ero Emission Buses” a nd commitment of a further £0.28m to be funded from the CRSTS ZEBRA allocation, as detailed in 1.3 2. Approve a Barnsley Metropolitan Borough Council led project change request for “Market Gate Bridge” and commitment of a further £1m to be funded from recycled Local Growth Fund, as detailed in 1.4 3. Note the update on the ZEBRA 2 s ubmission to the Department for Transport (DfT) and requests approval to accept any resulting grant. 4. Note the update on Project O0214 detailed in Appendix B and request acceptance of grant award. 5. Accept £3.99m of additional highways capital maintenance funding f rom DfT and onward award. 6. Accept £0.33m of Traffic Signal Obsolescence grant funding from DfT and onward award. Progress “Bike Works Active Travel Hub” from Outline Business Case to Full Business Case and in principle approval to award £0.95m to Barnsley Metropolitan Borough Council subject to the conditions set out in the Assurance Summary D elegate authority to the Head of Paid Service in consultation with the Section 73 and Monitoring Officer to enter into legal agreements f or the schemes above that the Board: 1. Approve a SYMCA led p roject change request for “Z ero Emission Buses” a nd commitment of a further £0.28m to be funded from the CRSTS ZEBRA allocation, as detailed in 1.3 2. Approve a Barnsley Metropolitan Borough Council led project change request for “Market Gate Bridge” and commitment of a further £1m to be funded from recycled Local Growth Fund, as detailed in 1.4 3. Note the update on the ZEBRA 2 s ubmission to the Department for Transport (DfT) and requests approval to accept any resulting grant. 4. Note the update on Project O0214 detailed in Appendix B and request acceptance of grant award. 5. Accept £3.99m of additional highways capital maintenance funding f rom DfT and onward award. 6. Accept £0.33m of Traffic Signal Obsolescence grant funding from DfT and onward award. Progress “Bike Works Active Travel Hub” from Outline Business Case to Full Business Case and in principle approval to award £0.95m to Barnsley Metropolitan Borough Council subject to the conditions set out in the Assurance Summary D elegate authority to the Head of Paid Service in consultation with the Section 73 and Monitoring Officer to enter into legal agreements f or the schemes above