Resolved
That the minutes of the special meeting held on 13 th February 2018 be confirmed as a correct record and signed. That the minutes of the special meeting held on 13 th February 2018 be confirmed as a correct record and signed.
Cabinet decided this item on Tuesday 13 March 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That the minutes of the special meeting held on 13 th February 2018 be confirmed as a correct record and signed. That the minutes of the special meeting held on 13 th February 2018 be confirmed as a correct record and signed.
SOUTHEND-ON-SEA BOROUGH COUNCIL
Meeting of Cabinet
Date: Tuesday, 13th February, 2018 Place: Committee Room 1 - Civic Suite
Present: Councillor J Lamb (Chair) Councillors A Holland (Vice-Chair), T Byford, J Courtenay, T Cox, M Flewitt, A Moring and L Salter
In Attendance: Councillors N Folkard, D Norman MBE and C Mulroney J K Williams, A Griffin, A Lewis, J Chesterton, J Ruffle, C Gamble, I Ambrose, E Cooney, S Crowther, S Houlden and C Robinson
Start/End Time: 2.15 - 2.45 pm
741 Apologies for Absence
There were no apologies for absence.
742 Declarations of Interest
The following interests were declared at the meeting:
(a) Councillor D Norman MBE – Minute 743 (Better Queensway) – Non- pecuniary interest – Council appointee to the South Essex Homes Board.
743 Better Queensway
The Cabinet received a report of the Deputy Chief Executive (Place) that sought approval of the final parameters for the Better Queensway regeneration project, including the proposed highways alignment, so as to commence procurement to secure a partner(s) to fund, develop and manage the scheme.
Resolved:-
1. That the results of the public consultation be noted.
2. That the plan in Appendix 4 of the submitted report be approved as the preferred indicative highways alignment for the regeneration area to be included in the procurement process.
3. That the approach to the planning application is adjusted so that the application is made by the partnership formed following procurement.
4. That the site indicated in Appendix 5 of the submitted report be included within the redline boundary for the procurement and that continuance of the Council’s income stream it derives from the site is placed as a requirement of the partnership.
5. That the site boundary, as per the plan in Appendix 6 of the submitted report, be agreed as the regeneration area for which a partner(s) is sought. 6. That the level of affordable housing provided on the site shall be required to be above the current 441 affordable units and that tenderers are required to put forward their proposition to increase this provision, demonstrating how this is viable.
7. That the updated procurement objectives, set out in section 7.3 of the submitted report, are agreed in principle to be used as the basis for the procurement and that the Deputy Chief Executive (Place) and the Deputy Chief Executive (People) shall each be individually authorised, in consultation with the Portfolio Holder for Culture, Tourism and the Economy, to refine and confirm the final wording of the objectives.
8. That the principle of a second lot “Lot 2” be agreed for inclusion in the procurement and that the Deputy Chief Executive (Place) and the Deputy Chief Executive (People) shall each be individually authorised, in consultation with the Director of Finance and Resources and the Portfolio Holder for Culture, Tourism and the Economy to agree its inclusion or exclusion in the procurement process and the final wording of the Lot 2 procurement documents.
9. That the Better Queensway Project Board be authorised to approve a variation of existing professional consultant contractual arrangements in accordance with Contracts Procedure Rules 9.2 to 9.4 to accommodate additional in-scope work in support of the project up to the sum of £427k.
10. That the Better Queensway Project Board be authorised to seek extensions of existing contractual arrangements under Contract Procedure Rules 9.5 and 9.6 in 12 month increments up to a maximum of 4 more years in accordance with the terms thereof and subject to the approved financial resources.
11. That the Better Queensway Project Board be authorised to purchase any further work necessary to support the Project which is either included in the scope or defined as out of scope of the current contracts from the contracted consultants via framework agreement call-offs in accordance with Contracts Procedure Rule 8.3 in line with the approved financial resources available.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of the special meeting held 13th February 2018Minutes | 62 KB | DownloadRead as text |
Follow Cabinet at Southend-on-Sea and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Oct 2026 | Minutes of the Meeting held on Monday, 7 September 2026That the Minutes of the Meeting held on Monday 7 September 2026 be amended to correct the typographical error in minu... | Decided | Open |
| 12 Oct 2026 | Decisions taken by, or in consultation with, Cabinet MembersThat the decisions taken by, or in consultation with, the relevant Cabinet Members since the last Cabinet meeting be ... | Noted | Open |
| 12 Oct 2026 | Official Feed and Food Control Service Plan 2026-27That the achievements delivered against the Official Feed and Food Control Service Plan 2025/26 be noted. 2. That the... | Noted | Open |
| 12 Oct 2026 | Income Contract with Castle Point Borough Council for CCTV System ManagementThat it be agreed to enter into a contract with Castle Point Borough Council for the provision of CCTV Services to Ca... | Agreed | Open |
| 12 Oct 2026 | Procurement of a Stairlift Installation, Maintenance & Removal ServiceThat approval be given to undertake a procurement exercise to establish a Framework Agreement for the provision of a ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.