The Cabinet considered a report of the Deputy Chief Executive (Place) presenting the draft Southend . There is a need to develop sub-regional elements of the Shoreline Management Plan into a more in-depth strategy for the Borough. Adopting a comprehensive strategy and submitting it to the EA Large Project Review Group will enable the Council to maximise access to supporting funds. Other options: None. Note: This is an Executive Function Eligible for call-in to: Place Scrutiny Committee Executive Councillor: Cllr Cox There is a need to develop sub-regional elements of the Shoreline Management Plan into a more in-depth strategy for the Borough. Adopting a comprehensive strategy and submitting it to the EA Large Project Review Group will enable the Council to maximise access to supporting funds. Other options: None. Note: This is an Executive Function Eligible for call-in to: Place Scrutiny Committee Executive Councillor: Cllr Cox *Called-in to :- Place Scrutiny Committee
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
1.1The purpose of this report is to present the draft Southend Shoreline Strategy to Members for approval, to seek approval to submit to Environment Agency (EA) and to establish on-going governance and implementation.
Recommendation
2.1That Members adopt the document, subject to approval by Environment Agency, as its strategy for managing the Borough’s coastal defences into the future.
2.2Members authorise the Portfolio Holder in Consultation with the Deputy Chief Executive, Place, to approve the final strategy, following Environment Agency approval.
2.3That Members note the total value of the Strategy at £410m (Present Value £134m) over a 100 years period, of which part will need to be funded from the Council’s Capital programme whilst other funding may include Flood Defence Grant-in-Aid and other external sources.
2.4That Members agree that the Strategy will be supported by an appropriate governance process, as set out in Paragraph 6.
2.5To approve the submission of the Strategy to the EA Large Project Review Group (LPRG) in June 2018.
Background
3.1The Shoreline Strategy is being developed by the Council in partnership with other organisations which share coastal interests in the area. These include Natural England and the Environment Agency. Participation in the development of the Shoreline Strategy is not limited to these organisations and contributions have and will continue to be welcomed from any organisation or individual with an interest. The Strategy outlines the work undertaken to date for the coast of Southend-on-Sea and the plans to manage flood and coastal erosion risks for the frontage.
Southend Shoreline Strategy 2018 Page 1 of 11 Report No: 18/013 3.2. The Shoreline Strategy will aim to be sustainable into the future and therefore will consider as far as 100 years ahead. However, the Shoreline Strategy will be regularly reviewed as more information about future conditions becomes available.
3.3The provision and maintenance of flood defences and coast protection works in England fall under the supervision of the Environment Agency (EA). EA has an established procedure to manage investment in such works to provide flood and erosion security at optimum cost to the taxpayer, in the face of high demand on limited resources. The procedure is based on a hierarchy of strategic policy documents and stages:
National Strategy for Overarching national strategy developed by the Flood and Coastal EA. Erosion Risk Management
Shoreline Management Regional coastal plans which divide the entire Plans (SMP) coastline into “Management Units”. Southend falls into the 2010 Essex and South Suffolk Shoreline Management Plan (SMP2), as management unit J, with a “management intent” over the life of the Plan to “Hold the line” and sustain the current Standards of Protection.
Shoreline Strategies Management-Unit-scale documents which seek to develop an optimised strategy for tidal flood- and erosion protection to deliver the SMP management policy.
Projects Works at individual sections of the frontage which are identified in the Strategy.
3.4The Essex and South Suffolk Shoreline Management Plan (SMP2) indicates that the coastal defences of the Borough should be retained on their present alignments and enhanced at appropriate times in the future to counter the effects of sea level rise. The time span of the Plan is 100 years, although it will be subject to review at regular intervals.
3.5The Thames Estuary 2100 project (TE2100), published by EA in 2012, overlaps SMP2 at Southend and the entire intertidal area of the coast in Southend is internationally designated for nature conservation purposes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.