The Cabinet considered a report of the Deputy Chief Executive (People) providing an update on the current position regarding the future provision for Secondary School places across the Borough from 2018-2020 and beyond. The decision to revert to an expansion as opposed to a free school has been taken for a number of reasons as set out in the submitted report. Other options: The decision previously taken by Cabinet was in effect the alternative option. Note: This is an Executive Function. Eligible for call-in to: People Scrutiny Committee Executive Councillor: Cllr Courtenay The decision to revert to an expansion as opposed to a free school has been taken for a number of reasons as set out in the submitted report. Other options: The decision previously taken by Cabinet was in effect the alternative option. Note: This is an Executive Function. Eligible for call-in to: People Scrutiny Committee Executive Councillor: Cllr Courtenay *Called-in to:- People Scrutiny Committee
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
This report is to update Cabinet on the current position regarding the future provision for Secondary School places across the Borough 2018-2020 and beyond.
Recommendations
a. That Cabinet notes the position regarding the provision of sufficient secondary school places. b. That Cabinet approve the decision to reverse its decision to pursue a Free School option in favour of expansion in existing secondary schools.
Background
Cabinet has for some years been informed of the impending requirement for additional school places from 2018 onwards in secondary schools. This followed on from the primary school growth in previous years, combined with other demographic changes in Southend.
In essence, this will require an additional 3 forms of entry (90 pupils) in 2018; 6 forms of entry (180) in 2019 and a further 2 in 2020 (60). In all, this will require 330 addition places each year for the next 5 years.
We have been working very closely with Essex County Council (ECC) to consider mobility across the South Essex boarder, both for learners attending a Grammar School from out of Southend, but also for whatever reason, a Southend resident choosing an Essex school. This information from Essex has fluctuated, but is currently estimated to be 250 pupils a year being educated in South Essex from Southend. ECC originally gave a very clear message that in 2018 these places would increasingly no longer be available.
Secondary School Places Page 1 of 4 As a result of the known numbers increasing, for some years officers had worked through the School Places Working Party to ask schools to expand, with very limited success.
Therefore, the decision was taken by Cabinet in Sept 2017 to pursue an additional school, which would have to be a free school. This was due to be funded by the Wave 13 Free School Capital route, but this has yet to be announced. The only other alternative would be for the Council to fund the capital build through a presumption route, in addition to relinquishing the identified land in St Laurence.
As a result of this Free School direction, the collective of non-selective secondary schools made a late proposal to expand to the required number, on the condition that the Free School option was discontinued. Meetings with the Leader and Executive Portfolio holder followed, where a commitment to reverse the Free School decision was given, the purpose of this report.
Currently, given Cabinet’s approval of this report, officers are pursuing the expansion route. Bearing in mind that the first set of places are required for September 2018, the timeline is very tight, and will almost certainly have to result in temporary mobile solutions in a number of projects. This will escalate costs. In addition, constraints and conditions placed upon the projects by planning control make for additional complications and delays.
Currently, for 2018, the additional places of one form of entry each are progressing at Shoeburyness; Belfairs, St Thomas More leaving no surplus places, however through the successful project to attract more Southend residents to our Grammar Schools, an additional form of entry has also accessed local places within the Grammar schools enabling Southend to meet late and in-year secondary applications.
Officers are continuing to confirm the expansion plans with schools for 2019 and 2020. Whilst this paper seeks Cabinet approval to reverse the previous decision to pursue a Free School option for this period, the demographic situation beyond 2020 with the projected need for 10,000 houses for Southend within the next ten years may require an additional school into the future as it is unlikely these numbers could be met by further expansion of existing schools.
4. Other Options
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.