- That ENFORCEMENT ACTION be AUTHORISED to secure the removal of the unauthorised Upvc framed windows installed to the ground and first floor front elevation of this property on the grounds that they harm the appearance of the property. The authorised enforcement action to include (if/as necessary) the service of an Enforcement Notice under Section 172 of the Town and Country Planning Act 1990 and the pursuance of proceedings whether by prosecution or injunction to secure compliance with the requirements of said Notice. When serving an Enforcement Notice the local planning authority must ensure a reasonable time for compliance. In this case, any delay in manufacture and installation is likely to be the dictated by the suppliers lead time. A compliance period of 3 months is deemed reasonable.
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
Without planning permission, the replacement of the existing Breaches of Control side hung timber windows at ground and first floor level in the front elevation with Upvc windows. (Article 4 Direction)
Address: 6 New Road, Leigh on Sea, Essex. SS9 2EA
Case Opened: 15th December 2016
Case Officer: Steve Jones
Recommendation: AUTHORISE ENFORCEMENT ACTION
6 New Road, Leigh on Sea, Essex
Development Control Report This item was deferred from the 12 September 2018 Development Control Committee at staffs’ request to verify the report content. The report is unchanged.
1 Site and Surroundings
1.1No 6 is a two storey mid terraced cottage constructed sometime between 1875 and 1897, lying to the north side of New Road facing across the C2C railway line towards Old Leigh. It forms part of a wider stretch of cottages where some have lost their original windows to inappropriate styles and materials. The majority of these were replaced over 4 years ago and are now immune from enforcement action. The property lies within the Leigh Conservation Area and is subject of an Article 4 Direction controlling window alterations to a dwelling house.
2 Lawful Planning Use
2.1The lawful planning use is as a dwelling house within Class C3 of the Town and Country Planning Use Classes Order 1987 (as amended)
3 Present Position
3.1A complaint was received on 13th December 2016 concerning the alleged installation of replacement windows with Upvc frames.
3.2A site inspection was carried out on 16th December 2016 by Enforcement Staff which confirmed that Upvc framed replacement windows had been installed to the front elevation of the property at ground and first floor level.
3.3On 16th December 2016, a letter was sent to the property owner advising that the Upvc framed windows did not benefit from Permitted Development rights and advised that a retrospective planning application should be submitted by 27th January 2017.
3.4On 10th January 2017 Enforcement Staff received an email from the property owner advising of their intention to submit a retrospective planning application.
3.5On 31st January 2017 a retrospective planning application was received by the Local Planning Authority (LPA) but on submission was invalid.
3.6The owner was informed that the planning application was invalid and following this there was an exchange of communication between the owner and the Planning Service concerning the requirements in order to validate the application.
3.7On 11th May 2017 Enforcement Staff emailed the owner advising that the application had still not been validated and that the matter would be referred to the Development Control Committee to seek authority to issue an Enforcement Notice.
3.8On 11th May 2017 the owner emailed Enforcement Staff advising they thought everything required had been submitted.
Development Control Report 3.9 On 11th July 2017 a retrospective planning application to retain two windows to the front elevation under Ref 17/00140/FULH was refused. (A copy of that report is attached at appendix 3)
3.10On 26th July 2017 Enforcement Staff emailed the property owner reminding them that the application had been refused and requesting clarification of whether it was their intention to lodge an appeal.
3.11On 30th July 2017 the property owner advised they would be lodging an appeal against the LPA decision.
3.12On 24th October 2017 Enforcement Staff emailed the property owner asking if an appeal had been lodged as they would otherwise be out of time.
3.13On 24th October 2017 the owner emailed Enforcement Staff advising they didn’t submit an appeal due to family circumstances.
3.14On 13th November 2017 Enforcement Staff received an email from the owner advising that an appeal had now been lodged.
3.15On 13th November 2017 Enforcement Staff emailed the owner advising the enforcement case would pend the outcome of the Planning Inspectorate decision.
3.16On 13th April 2018 Enforcement Staff emailed the owner requesting an update on the appeal progress.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.