Southend-on-Sea Council Corporate Risk Register (April 2026)

Decided Executive 2 papers

AI summarySouthend-on-Sea Cabinet notes the revised Corporate Risk Register for April 2026, covering 9 strategic risks, with one risk de-escalated and several updated.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted the April 2026 position and supported management actions.
MoneyNo direct costZurich insurance support attracts no additional cost.
What happens nextNo further steps requiredDecision was to note and support actions already underway.
Who it affectsCouncil-wide strategic prioritiesCovers 9 key risks to delivery of Corporate Plan objectives.

What was decided

Cabinet noted the revised Corporate Risk Register and the April 2026 position set out in Appendix 1. Report 2.1

Cabinet supported the actions being taken to manage the corporate risks. Report 2.1

Why

The Accounts and Audit Regulations 2015 require the council to have effective arrangements for the management of risk. Report 5.1, P11

Sound risk management supports informed decision making, service delivery and value for money, in line with the Government's Orange Book. Report 7.1

Noting the register contributes to assurance that the internal control requirement is being met. Report 5.2

What happens next

Activity to support risk mitigations continues to be updated and tracked in Appendix 1. Report 4.2

No alternative options were considered for this item. Report 6.1, P14

Options considered

  • Chosen: Note the revised Corporate Risk Register and support the management actions. Required to meet the Accounts and Audit Regulations 2015 and support informed decision making Report 2.1, 5.1
  • Rejected: Other options. None identified Report 6.1, P14

Implications

  • Legal: Failure to manage risks may lead to reputational, legal, regulatory, safety, security, environmental, employee, customer and operational consequences. Report 8.1
  • Financial: Failure to manage risks may lead to financial consequences. Report 7.2
  • Climate: Risk F covers insufficient progress on sustainability initiatives against the council's net zero by 2030 commitment for council operations. Report 11.1, P22
  • Equalities: Where risks relate to specific protected groups, impacts will be assessed within an Equality Analysis if necessary. Report 12.1, P24
  • Risk: Risk I relates directly to the council's readiness for vesting day of the new South East Essex Council on 1st April 2028. Report P19
  • Other: Risk B concerns failure to submit the local plan by 31 December 2026, which could require a restart under new regulations. Report P10

Who and where

  • Southend-on-Sea Borough Council staff and leadership (Corporate Leadership Team leads the approach) Report 3.1
  • Council priorities and Corporate Plan delivery Report 1.1, 4.1
  • Children Looked After (Risk E covers placement sufficiency) Report P10
  • Households at risk of homelessness and users of temporary accommodation (Risk D) Report P10

Timeline

  • April 2026: Position of the Corporate Risk Register reported Report 1.2, 2.1
  • 31 December 2026: Deadline under current regulations to submit the local plan (Risk B) Report P10
  • 1st April 2028: Vesting day of the new South East Essex Council (Risk I) Report P19
  • 2030: Council's net zero carbon target for council operations (Risk F) Report 11.1, P22

Plain English for the jargon

  • Corporate Risk Register: Document setting out key strategic risks to the council's priorities and the actions to mitigate them.
  • Residual risk score: The current risk score after management actions are taken into account.
  • LGR (Local Government Reorganisation): The restructuring of local councils, here creating a new South East Essex Council.
  • Vesting day: The date on which the new South East Essex Council formally comes into existence.
  • CLA: Children Looked After by the local authority.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

That Cabinet notes the revised Corporate Risk Register and the position in April 2026 outlined in Appendix 1 and supports the actions being taken to manage the risks.
Word for word from the decision Southend-on-Sea published for this meeting. Source: democracy.southend.gov.uk

Follow this further

Built from Southend-on-Sea's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1The Corporate Risk Register sets out the key risks to the successful delivery of the council’s priorities and objectives and outlines the key management arrangements in place to mitigate and reduce the likelihood of the risks crystallising.

1.2This report presents a revised Corporate Risk Register and the position at April 2026. The Corporate Leadership Team has reviewed and updated the Corporate Risk Register to ensure that the information provided will support informed decision making, which is vital to delivering successful services and transformational change.

1.3Risk is defined as uncertainty, whether positive or negative, that will affect the outcome of an activity or intervention. The term ‘management of risk’ incorporates the activities required to identify and control the exposure to risk that may have an impact on the achievement of the Council’s priorities.

Recommendations

2.1It is recommended that Cabinet note the revised Corporate Risk Register and the position in April 2026 outlined in Appendix 1 and supports the actions being taken to manage the risks.

Background

3.1Effective risk management is a key element of the council’s governance framework and has long been an established an effective tool within the council. 3.2. The council’s strategic approach to risk management is led by the council’s Corporate Leadership Team, with responsibility assigned through all levels of the council’s structure to ensure risk management is integrated into strategic planning and prioritisation to assist in the achievement of outcomes and successfully dealing with challenges. Risk management is an essential and integral part of meeting objectives, improving service delivery and achieving value for money. This approach is supported by the council’s insurance provider Zurich, which is included in the current risk management arrangements and attracts no additional cost.

3.3The corporate risk register reports the key strategic risks to the achievement of the council’s priorities, the ‘residual (current) risk score’ position as assessed by management, and the management actions being taken to mitigate the risks. A direction of travel is assigned to each risk as defined below: • Increasing arrow = the factors impacting the risk are worsening (this may result in an increase in risk score). • Stable arrow = the factors impacting the risk are remaining stable. • Reducing arrow = the factors impacting the risk are improving (this may result in a reduction in risk score).

4. Corporate Risk Register – April 2026

4.1The purpose of the council’s Corporate Risk Register is to set out the key risks to the successful delivery of the council’s priorities and objectives as set out in the Corporate Plan and to outline the key management arrangements in place to mitigate and reduce risks.

4.2The refreshed corporate risk register is attached at Appendix 1 and contains a total of 9 risks which have been identified and assessed. The risk changes outlined below include 1 deescalated risk removed since the last review in October 2025. Activity to support risk mitigations have been updated and is shown in Appendix 1.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate Risk Register: April 2026.FinalAppendix 1 576 KB Download
PDF
Southend-on-Sea Council Corporate Risk Register (April 2026)Report 119 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 18 attended
DC
Councillor Daniel CowanChair, present
MS
Councillor Maxine SadzaVice-Chair, present
PC
Councillor Paul CollinsCommittee Member, present
MD
Councillor Matt DentCommittee Member, present
IF
Councillor Irene FergusonCommittee Member, present
CN
Councillor Cheryl NevinCommittee Member, present
MO
Councillor Mandy O'ConnorCommittee Member, present
KR
Councillor Kevin RobinsonCommittee Member, present
CW
Councillor Chris WebsterCommittee Member, present
RW
Councillor Ron WoodleyCommittee Member, present
SW
Councillor Steven WakefieldDeputy, present
CA
Colin AnsellOfficer, in attendance

All 18 on the meeting page

On this subject at Southend-on-Sea

Search all
  1. Southend-on-Sea Council Corporate Risk Register (April 2026)This decision
  2. Southend-on-Sea Council Corporate Performance Report – Quarter 1Noted
  3. Southend-on-Sea Council Corporate Performance Report – Quarter 1Noted
  4. 25/01792/OUTM - Land North of Bournes Green Chase, Southend-on-Sea (Southchurch Ward)Refused
  5. Southend-on-Sea City Council Annual Report 2025/26Approved
  6. Preserving the City status and historic traditions of Southend-on-SeaAgreed

More from Southend-on-Sea Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 Minutes of the Meeting held on Monday, 7 September 2026That the Minutes of the Meeting held on Monday 7 September 2026 be amended to correct the typographical error in minu... Decided Open
12 Oct 2026 Decisions taken by, or in consultation with, Cabinet MembersThat the decisions taken by, or in consultation with, the relevant Cabinet Members since the last Cabinet meeting be ... Noted Open
12 Oct 2026 Official Feed and Food Control Service Plan 2026-27That the achievements delivered against the Official Feed and Food Control Service Plan 2025/26 be noted. 2. That the... Noted Open
12 Oct 2026 Income Contract with Castle Point Borough Council for CCTV System ManagementThat it be agreed to enter into a contract with Castle Point Borough Council for the provision of CCTV Services to Ca... Agreed Open
12 Oct 2026 Procurement of a Stairlift Installation, Maintenance & Removal ServiceThat approval be given to undertake a procurement exercise to establish a Framework Agreement for the provision of a ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies