Resolved
- That the report to Cabinet be noted. Note: This is an Executive function Cabinet Member: Councillor Cowan
AI summaryScrutiny committee notes a report recommending award of a 7 plus 7 year highway infrastructure and maintenance contract to a preferred bidder, starting 1 April 2026, with the final decision reserved for Cabinet.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
- That the report to Cabinet be noted. Note: This is an Executive function Cabinet Member: Councillor Cowan
1.1The current highway term service maintenance contract contractual end was 31st July 2025. This was extended via cabinet approval in July 2025 until 31st March 2026.
1.2This was due to the additional level of scope to be included within one overall contract (e.g. the inclusion of additional elements like gully emptying/winter maintenance), the finalisation of suitable contract documents delayed the initial planned release of the tender documents.
1.3Final tender submissions were received by 10th September 2025 and have been evaluated in accordance with the evaluation criteria set out in the tender documents.
1.4This report seeks authority to award the contract to the preferred bidder with the relevant delegated authority to proceed to the completion of contracts.
It is recommended that Cabinet:
2.1Approves the award of the contract for highway infrastructure and maintenance to the preferred bidder. The contract will commence on 1st April 2026 for a period of 7 years with an option to extend the contract by a further 7 years. 2.2. Delegates authority to the Executive Director for Environment and Place to finalise and enter into all necessary documentation to facilitate this contract.
3.1The current highways contract was for a 7-year term, with the contractual option of a 3-year extension, based on performance against key indicators, which were achieved and the extension activated. A further extension was approved in July 2025, and the contract comes to an end on 31st March 2026.
3.2The current incumbent contractor is Marlborough Highways Ltd.
3.3The procurement process included early market engagement to help shape the new contract. From this process it was clear that a 7-year term would deliver the best efficiencies for key elements such as vehicle/plant depreciation etc. Therefore, it is proposed to procure a 7 plus 7-year contract term, with the extension based on contract performance and key performance indicator (KPI) outcomes.
3.4In addition, rather than multiple smaller value contracts, all elements of highway and coastal works will be delivered via one contractor. This option will deliver improved efficiencies and quality of service, support more robust contract management and further help to reduce disruption to the network by being able to effectively deliver multiple services at the same time when appropriate.
3.5The new contract also includes additional services which include gully emptying, winter maintenance, verge maintenance, and an extended level of potential professional services.
3.6The tender documents acknowledge that the Service Period will be impacted by Local Government Reorganisation, and a clause has been added that will allow the contract to maximise the efficiency and benefits of such changes. This includes varying the terms of the contract, a change of scope, the right to novate or transfer the contract and termination.
3.7Following the market engagement exercise four bidders submitted expressions of interest and following evaluation two bidders were invited to submit the required tender.
3.8The tender process was undertaken under the Public Contract Regulations 2015 as it was started prior to the release of the new Procurement Act 2023 requirements.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Award of contract for highway, infrastructure and maintenanceReport | 107 KB | DownloadRead as text |
Follow Place Overview & Scrutiny Committee at Southend-on-Sea and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Jun 2026 | Minutes of the Meeting held on Tuesday, 10th February, 2026That the Minutes of the meeting held on Tuesday, 10 February 2026 be confirmed as a correct record. | Decided | Open |
| 18 Jun 2026 | Better Queensway Underpass Closure Impact Assessment UpdateThat the update on the closure of the Better Queensway underpass and associated impact assessment, be noted. Note: Th... | Noted | Open |
| 18 Jun 2026 | Parks and Playgrounds UpdateThat the parks and playgrounds update be noted. | Noted | Open |
| 18 Jun 2026 | Work Programme 2026/27That the work programme of the Committee be noted. This is a Scrutiny function. | Noted | Open |
| 10 Feb 2026 | Minutes of the Meeting held on Tuesday, 2nd December, 2025That the Minutes of the meeting held on Tuesday 2 nd December 2025 be confirmed and signed as a correct record. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.