CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Southend-on-Sea Borough Council
Cabinet, Monday 15 June 2026 at 6.00pm

Annual Treasury Management Report 2025/26

Approved Executive 1 paper

AI summaryCabinet approved Southend's 2025/26 Annual Treasury Management Report, noting £58.161m of capital spending was financed £7.003m below budget, PWLB borrowing held at £339.3m, and £4.246m earned in investment income at 3.72%.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedAnnual Treasury Management Report 2025/26 noted as compliant
Money£58.161m capital; £4.246m investment incomeCapital spend below £65.164m budget; interest earned below £4.957m forecast
What happens nextQuarterly Cabinet reports on treasurySet in 2025/26 Treasury Management Policy Statement
Who it affectsCouncil borrowing and investment portfoliosAffects HRA, General Fund and invest-to-save schemes

What was decided

Cabinet approved the Annual Treasury Management Report for 2025/26 and the outturn Prudential Indicators. Report 2.1

Cabinet noted that £58.161m of 2025/26 capital expenditure was financed in line with the schedule in Table 1, with no new external borrowing taken. Report 2.2, P21, P24

Cabinet noted that capital financing and treasury management were carried out in line with statutory requirements and the CIPFA Prudential Code, with £4.246m of investment income earned at 3.72% (combined return 3.82%) and PWLB borrowing held at £339.3m. Report 2.3, 2.4, P8, P9

Why

The CIPFA Code of Practice for Treasury Management requires local authorities to report treasury activity after the financial year and review performance against the Prudential Indicators. Report 3.1, 3.2, P13

The report demonstrates the Council has remained within its Authorised Limit of £390m, Operational Boundary of £380m and other prudential indicators throughout 2025/26. Report P43, P44, P45, P46

Active management of loan and investment portfolios aimed to minimise cost, maximise interest earned and keep risk low, in compliance with the Council's investment strategy approved on 20 February 2025. Report P7, 5.1, 5.2, 7.7

What happens next

Quarterly treasury management reports will continue to be submitted to Cabinet during 2026/27, in line with the Treasury Management Policy Statement. Report 10.1, P166

An Extraordinary General Meeting of the Patrizia Hanover Property Unit Trust is planned for 18 June, with a vote on whether the proposed merger proceeds on 30 June; if it fails, unitholders will vote on terminating the Trust. Report 9.5

The Treasury Management and Prudential Indicators Report will be taken to Cabinet in February 2026/27 to forecast the likely activity for the forthcoming year. Report 3.2, P13

The money

  • £58.161m Actual 2025/26 capital expenditure, £7.003m below revised budget Report P21, P23, P190
  • £65.164m Revised 2025/26 capital expenditure budget Report P21, P190
  • £14.550m Capital expenditure financed by borrowing in 2025/26, all internal Report P21, P24
  • £4.246m Interest and income distributions earned on all investments in 2025/26 Report P8
  • £0.116m Net increase in externally managed fund values from unit price changes Report P8, P109
  • 3.72% Average rate on investment interest and income distributions in 2025/26 Report P8, 7.5
  • 3.82% Combined investment return including unit price movements Report P8
  • £4.957m Budgeted investment interest, £0.711m higher than the £4.246m actually earned Report 7.6
  • £339.3m PWLB borrowing held flat across 2025/26 (HRA £72.0m, General Fund £267.3m) Report P9, P81, P89
  • £11.611m Total PWLB interest payments in 2025/26, in line with original budget Report 6.8
  • £355.934m Total gross debt at 31 March 2026, including PWLB, invest to save and finance leases Report P36, P39
  • £468.724m Capital Financing Requirement at 31 March 2026, against £467.606m budget Report P30, P190
  • £7.83m Invest to save financing at start of 2025/26 Report P10
  • £7.59m Invest to save financing at end of 2025/26 Report P10
  • £390.000m Authorised borrowing limit for 2025/26 Report P43, P191
  • £380.000m Operational Boundary for 2025/26 Report P43, P191
  • 10.69% General Fund financing costs as a proportion of net revenue stream, against 10.37% budget Report P43, P46
  • 2.31% Net income from commercial and services investments to net revenue stream, against 2.21% budget Report P51, P191
  • £0.161m Interest free loans taken from Salix Finance Ltd for energy efficiency projects Report 6.11

Options considered

  • Chosen: Continue active management of loan and investment portfolios to minimise cost, maximise interest and keep risk low. In line with CIPFA Code and the Council's 2025/26 Treasury Management Investment Strategy approved on 20 February 2025 Report P7, 5.1, 5.2, 7.7
  • Chosen: Take no new PWLB borrowing during 2025/26 and rely on internal borrowing. Council chose to delay borrowing and use internal funds while cash balances allowed Report P24, 6.8, 7.6
  • Rejected: Restructure or repay PWLB debt early to take advantage of lower current rates. Higher PWLB repayment rates made early redemption uneconomical and offered no benefit
  • Rejected: Invest in-house funds for periods over 365 days. No internally managed funds were invested for over 365 days in 2025/26; long term investments use external fund managers instead Report P58, P59

Implications

  • Financial: Capital spending came in £7.003m below the £65.164m revised budget, largely because schemes were deferred following capital challenge sessions with the Cabinet Member for Finance and Transport. Report P21, P25
  • Financial: Investment income was £0.711m below the £4.957m budget as the Council held less in-house cash than forecast to delay borrowing. Report 7.6
  • Financial: The bank base rate fell from 4.50% to 3.75% during 2025/26, reducing returns on in-house cash investments. Report 7.14
  • Financial: General Fund financing costs reached 10.69% of net revenue stream, 0.32 percentage points above the revised budget of 10.37%. Report P46
  • Legal: Treasury management activity complied with the Local Government Act 2003, statutory guidance, and the CIPFA Code of Practice for Treasury Management in the Public Sector. Report 3.2, 13.1, 13.2, 13.3
  • Risk: Loan and investment portfolios were actively managed with external advisers to keep risk low; gross borrowing stayed within the Authorised Limit of £390m and the Operational Boundary of £380m throughout 2025/26. Report P7, P44, P45, 5.1, 5.2
  • Risk: A merger vote on the Patrizia Hanover Property Unit Trust is scheduled for 18 June; if rejected, unitholders will vote on terminating the Trust, which could affect property fund holdings. Report 9.5
  • Climate: The LED Street Lighting and Illuminated Street Furniture Replacement Project, partly funded by invest to save finance, continues to reduce the Council's carbon impact. Report 16.1, P177
  • Equalities: No equalities implications arise from this report. Report 17.1, P179

Who and where

  • Southend-on-Sea City Council's General Fund, with £267.3m of PWLB borrowing and borrowing costs at 10.69% of net revenue stream Report P9, P43, P46
  • Housing Revenue Account, with £72.0m of PWLB borrowing and £101.247m total borrowing (including £29.277m internal) at 31 March 2026 Report P9, P26
  • Council taxpayers and council housing tenants, as revenues support borrowing and invest to save schemes such as LED lighting Report 6.10, P93, 16.1
  • External fund managers (Payden & Rygel, AXA, Royal London, Patrizia, UBS Triton and the terminated Lothbury Property Trust) holding pooled investments on the Council's behalf Report P100, P108, 9.5, 9.6
  • Essex County Council, which continues to manage the £8.0m of transferred debt reimbursed by Southend Report 6.4, P81, P88

Timeline

  • 20 February 2025: Council approved the 2025/26 Annual Treasury Management Investment Strategy Report 7.7
  • 31 March 2025: Opening balances, including £339.3m PWLB borrowing and £5.054m Payden Sterling Reserve Fund Report P79, P134
  • During 2025/26: Bank base rate fell incrementally from 4.50% to 3.75%, reducing in-house investment returns
  • 1 April 2025 to 31 March 2026: Reporting period for the Annual Treasury Management Report Report 1.1, 3.1
  • 31 March 2026: Closing position: £339.3m PWLB borrowing, £355.934m gross debt, £468.724m Capital Financing Requirement, £73.303m total investments Report P36, P40, P100
  • 18 June (2026): Extraordinary General Meeting of Patrizia Hanover Property Unit Trust to vote on the proposed merger Report 9.5
  • 30 June (2026): Planned effective date for the Patrizia Hanover Property Unit Trust merger, if approved Report 9.5
  • February (2026/27): Treasury Management and Prudential Indicators Report to be taken to Cabinet to forecast the forthcoming year Report 3.2, P13

Plain English for the jargon

  • PWLB: Public Works Loan Board, the UK government body that lends to local authorities.
  • CIPFA: The Chartered Institute of Public Finance and Accountancy, which publishes the Prudential Code and Treasury Management Code.
  • CFR: Capital Financing Requirement, the Council's underlying need to borrow to fund capital spending not yet charged to revenue.
  • MRP: Minimum Revenue Provision, the statutory charge to revenue to repay capital debt over time.
  • HRA: Housing Revenue Account, the ringfenced account for council housing.
  • ECC transferred debt: Debt relating to services transferred from Essex County Council on 1 April 1998, still managed by ECC and reimbursed by Southend.
  • SONIA: Sterling Overnight Index Average, a benchmark for short term sterling interest rates.
  • Authorised Limit: The affordable borrowing limit set under the Local Government Act 2003, the outer boundary of the Council's borrowing.
  • Operational Boundary: The expected maximum borrowing position during the year, set within the Authorised Limit.
  • Invest to save: Capital projects funded by borrowing or finance where predicted revenue savings cover the financing costs, such as the LED street lighting project.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

- 1. That the Annual Treasury Management Report for 2025/26 and the outturn Prudential Indicators for 2025/26, be approved. 2. That it be noted that the financing of 2025/26 capital expenditure of £58.161m has been funded in accordance with the schedule set out in Table 1 of section 4 of the submitted report. 3. That it be noted that Capital Financing and Treasury Management were carried out in accordance with statutory requirements, good practice and in compliance with the CIPFA (The Chartered Institute of Public Finance and Accountancy) Prudential Code during 2025/26. 4. That the following in respect of the return on investment and borrowing, be noted: · The loan and investment portfolios were actively managed to minimise cost and maximise interest earned, whilst maintaining a low level of risk. · £4.246m of interest and income distributions for all investments were earned during 2025/26 at an average rate of 3.72%. Also, the value of the externally managed funds increased by a net of £0.116m due to the changes in the unit price, giving a combined return of 3.82%. (Section 7 of the submitted report). · The level of borrowing from the Public Works Loan Board (PWLB) (excluding debt relating to services transferred from Essex County Council on 1st April 1998) started the year at £339.3m and remained at that level throughout the year (Housing Revenue Account (HRA): £72.0m, General Fund (GF): £267.3m). · The level of financing for ‘invest to save’ schemes decreased from £7.83m to £7.59m by the end of 2025/26. .
Word for word from the decision Southend-on-Sea published for this meeting. Source: democracy.southend.gov.uk

Follow this further

Built from Southend-on-Sea's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1The Annual Treasury Management Report covers the treasury activity for the period from April 2025 to March 2026 and reviews performance against the Prudential Indicators for 2025/26.

Recommendations

It is recommended that Cabinet;

2.1Approves the Annual Treasury Management Report for 2025/26 and the outturn Prudential Indicators for 2025/26.

2.2Notes that the financing of 2025/26 capital expenditure of £58.161m has been funded in accordance with the schedule set out in Table 1 of section 4.

2.3Notes that Capital Financing and Treasury Management were carried out in accordance with statutory requirements, good practice and in compliance with the CIPFA (The Chartered Institute of Public Finance and Accountancy) Prudential Code during 2025/26.

2.4Notes the following in respect of the return on investment and borrowing;

• The loan and investment portfolios were actively managed to minimise cost and maximise interest earned, whilst maintaining a low level of risk.

Annual Treasury Management Report – Page 1 of 23 2025/26 • £4.246m of interest and income distributions for all investments were earned during 2025/26 at an average rate of 3.72%. Also, the value of the externally managed funds increased by a net of £0.116m due to the changes in the unit price, giving a combined return of 3.82%. (Section 7).

• The level of borrowing from the Public Works Loan Board (PWLB) (excluding debt relating to services transferred from Essex County Council on 1st April 1998) started the year at £339.3m and remained at that level throughout the year (Housing Revenue Account (HRA): £72.0m, General Fund (GF): £267.3m).

• The level of financing for ‘invest to save’ schemes decreased from £7.83m to £7.59m by the end of 2025/26.

Background

3.1The CIPFA Prudential Code requires the Council to set Prudential Indicators for its capital expenditure and treasury management activities and to report on them after the end of the financial year.

3.2This Council has adopted the ‘CIPFA Code of Practice for Treasury Management in the Public Sector’ and operates its treasury management service in compliance with this Code. The Code requires the reporting of treasury management activities to:

• Review actual activity for the preceding year (this report); and • Forecast the likely activity for the forthcoming year (in the Treasury Management and Prudential Indicators Report in February).

3.3The Prudential Code is the key element in the system of capital finance that was introduced from 1st April 2004 as set out in the Local Government Act 2003. The Code has been developed to support Local Authorities in taking capital investment decisions and to ensure that these decisions are supported by a framework which ensures proportionality, prudence, affordability and sustainability.

3.4To demonstrate compliance with these objectives of proportionality, prudence, affordability and sustainability each local authority is required to produce a set of prudential indicators and to update these annually as part of setting the Council’s budget.

Annual Treasury Management Report – Page 2 of 23 2025/26 4. Prudential Indicators

4.1Appendix A provides a schedule of the prudential indicators.

4.2Capital Expenditure

The first of these is the amount of capital expenditure in the year on long term assets. The table below shows this and the ways it has been financed.

Table 1: Capital Expenditure and Financing

2025/26 2025/26 2025/26 Revised Actual Variance Budget £m £m £m General Fund 54.728 45.406 (9.322) Housing Revenue Account 10.436 12.755 2.319 Total Capital Expenditure 65.164 58.161 (7.003) Financed by: Borrowing(1) 18.978 14.550 (4.428)

Invest to Save Financing(1) 0.946 0.577 (0.369)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Annual Treasury Management Report 2025/26Report 483 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 18 attended
DC
Councillor Daniel CowanChair, present
MS
Councillor Maxine SadzaVice-Chair, present
PC
Councillor Paul CollinsCommittee Member, present
MD
Councillor Matt DentCommittee Member, present
IF
Councillor Irene FergusonCommittee Member, present
CN
Councillor Cheryl NevinCommittee Member, present
MO
Councillor Mandy O'ConnorCommittee Member, present
KR
Councillor Kevin RobinsonCommittee Member, present
CW
Councillor Chris WebsterCommittee Member, present
RW
Councillor Ron WoodleyCommittee Member, present
SW
Councillor Steven WakefieldDeputy, present
CA
Colin AnsellOfficer, in attendance

All 18 on the meeting page

On this subject at Southend-on-Sea

Search all
  1. Annual Treasury Management Report 2025/26This decision
  2. Treasury Management Report – Quarter One 2026/27Approved
  3. Annual Treasury Management Report 2025/26Noted
  4. Quarter Three Treasury Management Report - 2025/26Noted
  5. Treasury Management Policy 2026/27Approved
  6. Treasury Management Report - Quarter 3 2025/26Noted

More from Southend-on-Sea Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 Minutes of the Meeting held on Monday, 7 September 2026That the Minutes of the Meeting held on Monday 7 September 2026 be amended to correct the typographical error in minu... Decided Open
12 Oct 2026 Decisions taken by, or in consultation with, Cabinet MembersThat the decisions taken by, or in consultation with, the relevant Cabinet Members since the last Cabinet meeting be ... Noted Open
12 Oct 2026 Official Feed and Food Control Service Plan 2026-27That the achievements delivered against the Official Feed and Food Control Service Plan 2025/26 be noted. 2. That the... Noted Open
12 Oct 2026 Income Contract with Castle Point Borough Council for CCTV System ManagementThat it be agreed to enter into a contract with Castle Point Borough Council for the provision of CCTV Services to Ca... Agreed Open
12 Oct 2026 Procurement of a Stairlift Installation, Maintenance & Removal ServiceThat approval be given to undertake a procurement exercise to establish a Framework Agreement for the provision of a ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies