Annual report on corporate risk

Noted Finance 2 papers

AI summarySouthwark audit committee notes annual corporate risk report and reviews assurance framework before finalisation by Strategic Director of Resources.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedAnnual report on corporate risk noted
MoneyNot stated
What happens nextFinalisation of registerBy Strategic Director of Resources after committee comments
Who it affectsCouncil-wideRisks identified across all departments

What was decided

The committee noted the annual report on corporate risk, which sets out 163 risks across all departments and identifies the top corporate risks. Report P1, P28

The committee reviewed the current assurance framework, which has minor updates since November 2025 and aligns with the Southwark 2030 strategy. Report P2, P13

The committee will provide comments to officers before the Strategic Director of Resources finalises the register. Report P2

Why

The report fulfils the annual requirement to update the committee on key corporate risks, following prior reports in February 2025 and November 2025. Report P4, P5

The corporate risk process sets out the most significant risks, consolidates common issues, ensures single cross-cutting risks like cyber security are recorded, and alerts the council to new or increasing risks. Report P9, P10

The top risks are those assessed as amber or red that appear in more than one departmental register or significantly affect the Southwark 2030 goals. Report P32

What happens next

Committee members will provide comments to officers for consideration before the register is finalised by the Strategic Director of Resources. Report P2, P46

The top corporate risks, attached in appendix 1, will be actively managed with mitigations implemented as far as possible. Report P31, P32, P44

Options considered

  • Chosen: Note the annual report on corporate risk. Recommended by officers to fulfil annual reporting requirement Report P1
  • Chosen: Review the assurance framework and provide comments to officers. To inform finalisation of the register by the Strategic Director of Resources Report P2

Implications

  • Risk: The council's assurance framework identifies and consolidates the most significant risks, including cyber threats, funding pressures and demand pressures, with mitigations in place. Report P9, P11, P25
  • Other: The report is not considered to have direct policy implications, direct community impact, or direct resource implications. Report P34, P36, P38
  • Staffing: Departmental risk champions and the corporate risk and insurance manager validate departmental risk registers and carry out aggregation exercises. Report P24

Who and where

  • All council departments, which maintain departmental risk registers Report P20, P21
  • The Strategic Director of Resources, who finalises the corporate risk register Report P2, P46
  • Residents and the wider community, as risk management supports the council's ability to serve them Report P10, P36

Timeline

  • Jan 2025 to Jan 2026: Total number of risks rose from 156 to 163 Report P28
  • February 2025: Key corporate risks last reported to the committee in original format Report P4
  • November 2025: Key corporate risks reported to the committee with revised format Report P4, P13
  • 22 January 2026: Final report sent to Constitutional Team Report P46
  • 3 February 2026: Annual report on corporate risk considered by the committee Report P4, P46

Plain English for the jargon

  • Assurance framework: A document that consolidates the most significant corporate risks, their controls, and the sources of assurance across three lines of defence.
  • Three lines of defence: A model for managing risk: operational management, oversight functions like risk and compliance, and independent assurance through internal audit.
  • CMT: Corporate Management Team, which reviewed and updated the risks on the assurance framework.
  • Southwark 2030: The council's strategy with six goals, used to align corporate risks where possible.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

That the audit, governance and standards committee noted the annual report on corporate risk. 2. That the audit, governance and standards committee reviewed the current assurance framework and provided comments to officers for their consideration prior to the finalisation of the register by the Strategic Director of Resources.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Audit, Governance and Standards Committee, 5 pages

Recommendation

1. That the audit, governance and standards committee note the annual report on corporate risk.

2. That the audit, governance and standards committee reviews the current assurance framework and provide comments to officers for their consideration prior to the finalisation of the register by the Strategic Director of Resources.

BACKGROUND INFORMATION

3. This report provides an annual report on the council’s key risks. The key corporate risks were last reported to the committee in February 2025 and again in November 2025 with a revised format. This report provides an annual update.

4. This report also summarises the corporate risk management arrangements and reports on details of the council’s risk profile and risk categories.

KEY ISSUES FOR CONSIDERATION

Overview

5. The main purposes of the council’s corporate risk management process are:

 To set out the most significant risks to the council in the context of multiple risks identified and managed within each department.  Where appropriate, to consolidate common risks issues especially where cumulatively they may amount to a higher risk rating  To ensure that single risks that may act to impact across all council services are recorded (e.g. cyber security).  To enable risks to be effectively managed to ensure that the council meets its corporate and business objectives; and

1  To alert the council to new or increasing risks that may impact on the council’s ability to serve its residents and wider community

6. The council’s assurance framework is prepared following assessment by officers of all departmental risks. Given the range of services provided by the council, these lists are long and detailed and will be rated from low to high. Many risks are of a very specific nature and are unlikely to be translated directly on to the assurance framework. However, they may be consolidated into corporate risks in so far that cumulatively they create a higher risk to the council (e.g. loss of or reduction in funding sources; additional demand pressures; etc.).

7. In the process of preparing the assurance framework, concentration is placed upon moderation of risk ratings to ensure some consistency across the council and to confirm that appropriate mitigations are in place to manage the risk, as far as that is possible.

8. The refreshed assurance framework has some minor updates since it was last reported to committee in November 2025, and incorporates risks associated with the council’s normal operations, plus the Southwark 2030 strategy, and attempts to align the corporate risks with the six goals where possible. It details the different sources of assurance across the three lines of defence and provides a commentary on the level of assurance provided plus a risk score in line with the risk management procedures.

Risk Categories

9. The council uses the following risk categories to capture risk:

 Economic (e.g. credit crunch impacting on service delivery)  Financial (e.g. budgetary constraints)  Reputational (e.g. failures of service delivery which hit the press)  Staffing & Culture (e.g. recruitment & retention)  Operational (e.g. services not being delivered)  Legal & Regulatory (e.g. not complying with a statutory duty)

10. The 2026 split of number of risks by risk category is displayed in the table below. The categories remain at a consistent level compared with the percentages last reported.

Risk Category Percentage (%) Percentage (%) Jan 2025 Jan 2026 Economic 5 5 Financial 26 25 Reputational 13 13 Staffing & Culture 7 7 Operational 30 31 Legal & 19 18 Regulatory

2 Corporate Risk Register

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Assurance FrameworkAppendix 1 18 pages Download
PDF
Report: Risk AssuranceReport 5 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 13 attended
BH
Councillor Barrie HargroveChair, present
AH
Councillor Adam HoodVice-Chair, apologies
EC
Councillor Ellie CumboCommittee Member, absent
DD
Councillor Dora Dixon-Fyle MBECommittee Member, absent
GN
Councillor Graham NealeCommittee Member, present
AS
Councillor Andy SimmonsCommittee Member, present
KW
Councillor Kieron WilliamsCommittee Member, absent
AM
Amrit MangraIndependent Person, expected
GC
Geraldine ChadwickOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected
TJ
Timothy JonesCouncil Staff, expected
CP
Clive PalfreymanCouncil Staff, expected

All 13 on the meeting page

On this subject at Southwark

Search all
  1. Annual report on corporate riskThis decision
  2. Annual report on corporate risk and insuranceNoted
  3. Annual report on the work of the corporate risk and insurance team 2016-17Noted
  4. Annual report on the work of the corporate risk and insurance team 2015-16Noted

More from Southwark Audit, Governance and Standards Committee

All decisions
MeetingDecisionOutcome
13 Jul 2026 Corporate Anti-Fraud Team and Special Investigations Team Year End Report 2025-26That the audit, governance and standards committee noted the Corporate Anti-Fraud Team (CAFT) and the Special Investi... Noted Open
13 Jul 2026 Southwark360: Six-month progress update on the Enterprise Resource Planning (ERP) Replacement programmeThat the Audit, Governance and Standards Committee noted the six-month progress update on delivery of the Southwark36... Noted Open
13 Jul 2026 External Audit Plan - Southwark Council & Pension FundThat the Audit, Governance and Standards committee: a. Noted the Southwark Council External Audit plan attached at Ap... Noted Open
13 Jul 2026 Internal audit progress report for 2025-26That the audit, governance and standards committee noted the update reports, as attached at Appendix A, including app... Noted Open
13 Jul 2026 Internal Audit - Annual Report & Opinion 2025-26That the audit, governance and standards committee note the update reports, as attached at Appendix A. Noted Open