Report on retrospective contract-related decision: Communal Lighting and Electrical Testing Contracts - Contract A: North of the Borough and Contract B: South of the Borough
NotedFinance1 paper
AI summarySouthwark audit committee noted two retrospective extensions of communal lighting and electrical testing contracts, with revised total values of £39.12m for BCS and £43.67m for Spokemead, and accepted actions to reduce future retrospective decisions.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted retrospective decisions and director's actions
Money£39.12m and £43.67m revised totalsBCS and Spokemead contracts to 31 January 2026
What happens nextEIRM procurement being progressedNew contract to consolidate electrical compliance workstreams
Who it affectsTenants, homeowners, two contractorsAround 37,600 council homes subject to EICR programme
What was decided
The committee noted the two retrospective contract extension decisions covering 1 April 2023 to 31 August 2025 and 1 September 2025 to 31 January 2026. Report P1, P7
The committee noted the actions set out by the Director of Repairs and Maintenance to minimise the risk of future retrospective contract decisions. Report P2, P66
The committee made no further recommendations to improve future decision-making. Report P3
Why
The council self-referred to the social housing Regulator in June 2024 and set a target of completing EICRs across all council homes by 31 March 2026, creating urgent delivery pressure. Report P12, P26, P49
Operational resources were diverted to front-line inspections and safety-critical remedial work, so the re-procurement could not be progressed at the required pace. Report P9, P14
Existing contractors BCS and Spokemead were already mobilised across the borough and could increase capacity immediately, making them the only viable delivery route. Report P13, P16, P50
What happens next
Engineering is progressing the new Electrical Inspection and Remedial Works (EIRM) procurement, with pre-market engagement completed and tender documentation being finalised. Report P73, P74
Quarterly review meetings with electrical contractors will assess performance against KPIs and forecast capacity needs. Report P67
A structured training programme is being rolled out to embed the True Compliance centralised certification database across engineering, repairs, voids and major works teams. Report P71, P72
The money
£39.12m Revised total estimated value of Contract A (North) with BCS to 31 January 2026 Report P37, P55
£43.67m Revised total estimated value of Contract B (South) with Spokemead to 31 January 2026 Report P46, P56
£11.1m Original total estimated value of Contract A (North) when awarded in 2018 Report P20
£9.18m Original total estimated value of Contract B (South) when awarded in 2018 Report P21
£1.85m Original estimated annual value of Contract A (North) Report P20
£1.53m Original estimated annual value of Contract B (South) Report P21
Options considered
Chosen: Extend existing BCS and Spokemead contracts retrospectively to maintain service continuity. Only viable route to meet 31 March 2026 EICR deadline given self-referral to Regulator and lack of time to procure new contractors Report P8, P13, P16, P50
Implications
Legal: Extensions enable the council to meet statutory duties as a social landlord under the Landlord and Tenant Act 1985, Building Regulations Part P, the Building Safety Act 2022 and the Social Housing (Regulation) Act 2023. Report P78
Financial: Revised contract values reflect much higher activity than originally forecast, driven by new electrical safety legislation and emergency lighting and fire-related remedial work. Report P47, P55, P56
Governance: The retrospective approvals were required because procedural steps for procurement and contract extension were missed while resources were focused on safety-critical delivery. Report P9, P12, P14
Risk: Actions to reduce future retrospective decisions include quarterly contract reviews, earlier procurement initiation, a central compliance risk register, and joint working between procurement and engineering. Report P67, P69, P70
Staffing: A training and onboarding programme is being rolled out across Engineering, Repairs/Voids and Major Works teams to embed the True Compliance database. Report P72
Equalities: Contracts are assessed as medium impact on tenants, homeowners and other stakeholders, with majority of works external and some electrical testing in tenanted properties. Report P80
Who and where
Around 37,600 council homes subject to the EICR testing programme Report P49
Council tenants and homeowners across the north and south of the borough Report P80
BCS (Electrical and Building) Ltd, contractor for the north of the borough Report P20, P28
Spokemead Maintenance Ltd, contractor for the south of the borough Report P21, P38
The council's electrical engineering, repairs, voids and major works teams Report P72
Timeline
13 March 2018: Gateway 2 approval to award the two contracts Report P19
1 October 2018: Contracts start, initial four-year term with two-year extension option Report P20, P21
22 June 2022 and 10 August 2022: Gateway 3 extensions approved to 31 March 2023 Report P22
June 2024: Council self-referred to the social housing Regulator Report P12
25 July 2025: First retrospective Gateway 3 approval, extending contracts to 31 August 2025 Report P8
18 December 2025: Second retrospective Gateway 3 approval, extending contracts to 31 January 2026 Report P8
31 January 2026: End date of current extension period Report P7
3 February 2026: Audit, Governance and Standards Committee meeting noted the retrospective decisions
31 March 2026: Target deadline for completing EICRs across all council homes Report P12
Plain English for the jargon
EICR: Electrical Installation Condition Report, a periodic safety test of electrical installations
EIRM: Electrical Inspection and Remedial Works, the new consolidated procurement being developed
Gateway 1/2/3: Approval stages for procurement strategy, contract award and contract variation/extension
CSO 6.7: Contract Standing Order requiring retrospective decisions over £100,000 to be reported to the audit committee
CCRB: Corporate Contracts Review Board
True Compliance: Centralised certification database replacing the previous Apex system
AOV: Automatic Opening Vent, used in fire safety systems
UPS: Uninterruptible Power Supply, backup power equipment in newbuild sites
BMI: Building Maintenance Indices, the annual price adjustment applied to the contracts
C1/C2: Electrical safety codes for dangerous and potentially dangerous defects
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
That the audit, governance and standards committee noted the retrospective contract decisions detailed in the report. 2. That the audit, governance and standards committee noted the actions taken by the Director of Repairs and Maintenance as set out in paragraphs 37 to 45 of the report to ensure that the risk of future retrospective contract decisions is minimised for the future. 3. That the audit, governance and standards committee made no further recommendations to help improve future decision-making.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Audit, Governance and Standards Committee, 10 pages
Recommendations
1. That the audit, governance and standards committee note the retrospective contract decisions detailed in the report.
2. That the audit, governance and standards committee note the actions taken by the Director of Repairs and Maintenance as set out in paragraphs 37 to 45 below to ensure that the risk of future retrospective contract decisions is minimised for the future.
3. That the audit, governance and standards committee consider whether it would wish to make recommendations to help improve future decision-making.
BACKGROUND INFORMATION
4. Where approval for a contract decision has been sought retrospectively and has an estimated value of more than £100,000, there is a requirement under contract standing order 6.7 to submit a report to the audit, governance and standards committee. The report should set out the circumstances and manner in which the decision was taken, for the purpose of obtaining guidance to inform future decision making.
5. This requirement applies to decisions relating to the approval of a procurement strategy (Gateway 1 or GW1), decisions relating to the approval of a contract award (Gateway 2 or GW2) and decisions relating to the approval of a variation or extension to a contract (Gateway 3 or GW3) decisions.
6. By way of two Gateway 3 reports, retrospective approval of the procurement process was sought to the two Communal Lighting and Electrical Testing contracts: the first report requested an extension for the period 1 April 2023 to 31 August 2025, and the second requested an extension for the period 1 September 2025 to 31 January 2026.
7. The Cabinet Member for Council Homes approved variations/extensions to the two existing term contracts via two Gateway 3 reports—first, on 25 July 2025 for the period 1 April 2023 to 31 August 2025, and second on 18 December 2025 for the period 1 September 2025 to 31 January 2026. Both approvals were retrospective decisions 8. The extension of the contracts for the electrical testing programme and fire-detection installations was critical in enabling the engineering team to focus on meeting the council’s statutory and regulatory obligations as a social landlord. Ensuring the safe delivery of electrical testing across the housing stock necessarily became the team’s priority.
9. Although additional resource was allocated to help manage the significant volume of work, this capacity had to be directed towards front-line delivery, completing validated EICRs, installing fire-detection systems, and addressing safety risks, rather than progressing the re-procurement activity. As a result, some of the procedural steps required for the procurement and contract extension process were missed.
KEY ISSUES FOR CONSIDERATION
Why was approval not sought earlier
10. The electrical compliance programme expanded significantly following the council’s self-referral to the Regulator in June 2024. The council set a target for EICRs to be completed across all council homes by 31 March 2026, creating an urgent delivery requirement.
11. To meet this deadline, the council had to begin large-scale testing immediately. This meant that existing contractors, already mobilised and operating across the borough, was the only viable route to deliver the required volume of work within the available timeframe. There was insufficient time to complete a new procurement process without risking non-compliance and potential safety issues.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
8Report on retrospective contract-related decision: Communal Lighting and Electrical Testing Contracts - Contract A: North of the Borough and Contract B: South of the BoroughThis decision
Report on retrospective contract-related decision: Communal Lighting and Electrical Testing Contracts - Contract A: North of the Borough and Contract B: South of the BoroughThis decision
Follow Audit, Governance and Standards Committee at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.