AI summarySouthwark's Audit, Governance and Standards Committee noted improved repairs performance against the Regulator for Social Housing improvement plan, ongoing delivery of the £100m 2025/26 capital programme, and plans for a new 5-year investment plan due at Cabinet in autumn 2026.
Written from the decision and the officer reportPDF Pro
OutcomeNotedNoted positive trends, ongoing capital delivery, new 5-year plan timeline
Money£100m capital budget 2025/26Reduces to £77m in 2026/27 and 2027/28
What happens nextNew 5-year plan to CabinetExpected in autumn 2026, based on stock survey
Who it affectsCouncil tenants and leaseholdersAround 37,000 tenanted homes in scope of stock survey
What was decided
The committee noted positive trends in performance against the Improvement Plan agreed with the Regulator for Social Housing, and progress on becoming a Good Landlord, with plans to strengthen the Repairs Service. Report P1
The committee noted ongoing delivery of the current capital investment programme, focused on health, safety and compliance. Report P2
The committee noted the timeline for developing a new 5-year investment plan, based on the stock condition survey findings and resident engagement. Report P3
Why
Southwark's Housing Department has been delivering an improvement plan since the Regulator for Social Housing inspection in August 2024, which resulted in a C3 grading. Report P5
The work supports the council's Good Landlord Plan and the need to bring homes up to safe, modern and decent standards, with significant investment in fire safety, electrical safety, and heating. Report P6, P33, P31
A lack of up-to-date stock condition data was a key failing identified by the Regulator in November 2024, prompting the new survey and asset management work. Report P39, P40
What happens next
Bring a new 5-year investment plan to Cabinet in autumn 2026, using the first six to nine months of stock condition survey data, with input from climate and public health workstreams. Report P50, P51
Achieve full electrical safety compliance by the end of March 2026 across around 25,000 homes, with two new contractors now working alongside existing term contractors and Southwark Repairs. Report P17, P31
Complete procurement of two specialist fire safety contractors by autumn 2026, and roll out the True Compliance IT platform across all workstreams by mid-2026. Report P27, P35
The money
c.£85 million Investment in 2025/26 into maintenance, safety and decent homes Report P6
close to £80m per annum Planned spend across the next two financial years on housing maintenance Report P6
£100m Capital programme budget for 2025/26, forecasts currently in line Report P58
£77m Reduced capital budget for 2026/27 and 2027/28, subject to ongoing review Report P59
around £40m Spend across 2025/26 and 2026/27 on estate-based planned maintenance Report P22
£14m Consort Estate scheme, currently on site Report P23
£10m Taplow House on the Aylesbury Estate to bring over 200 empty properties back into use Report P24
Around £15m Fire safety and building safety work set aside Report P25
£20m External wall systems works funded through central government cladding scheme Report P26
more than £30m Electrical safety and smoke alarm work across c.25,000 homes Report P31
c.£15m Heating and hot water improvements across the next three years at Dighton Court, Gloucester Grove, Setchell and Wyndham Estates Report P33
£25m Repairs Service capital investment in communal and roofing repairs, empty properties and adaptations (£12m in 2025/26) Report P34
more than £7m Lift, water and asbestos safety (c.£3m in 2025/26) Report P35
£1.3m Grant from the Warm Homes: Social Housing Fund for energy efficiency design work Report P36
c.£9.1m Budget for the stock condition and engineering asset survey over a four-year contract Report P40
Options considered
Chosen: Note positive trends and progress against the Regulator for Social Housing improvement plan. Recommended in the officer report Report P1
Chosen: Note ongoing capital programme delivery focused on health, safety and compliance. Recommended in the officer report Report P2
Chosen: Note the timeline for a new 5-year investment plan based on the stock condition survey. Recommended in the officer report Report P3
Implications
Financial: Capital budget falls from £100m in 2025/26 to £77m in each of 2026/27 and 2027/28, with ongoing conversations about whether the programme can be stretched over future years. Report P58, P59
Risk: Staff vacancies across the Repairs and Maintenance Directorate remain an ongoing challenge to delivering large programmes, being addressed through a skills gap and training needs analysis. Report P60, P61
Risk: Procurement governance timeframes at Southwark are lengthy, and aligning internal teams plus securing the right delivery partners, particularly in building and fire safety, are key challenges. Report P53
Equalities: Works have a medium to high impact on tenants, leaseholders and other stakeholders; pre-construction planning gathers information on residents' individual needs to tailor the programme. Report P66, P67
Climate: The council is exploring low carbon and sustainable material options, extending low carbon heat from SELCHP, and securing external funding to meet climate emergency commitments. Report P33, P71, P72, P73
Legal: Compliance work targets fire risk assessments, electrical safety, gas safety and building safety legislation, with most outstanding gas cases progressing through legal routes. Report P19, P31
Staffing: Investment in the Direct Labour Organisation (DLO) through a new workforce strategy is part of the responsive repairs improvement programme. Report P10
Who and where
Council tenants in Southwark's housing stock (c.37,000 tenanted homes in scope of the stock condition survey) Report P43
Leaseholders, including those at schemes such as Consort Estate Report P23, P66
Residents of high-rise buildings (HRBs), engaged through the Building Safety Resident Engagement Strategy Report P28, P29, P30
Vulnerable residents, people with disabilities, the elderly and very young, identified as particularly at risk from poor housing standards Report P12, P69
Households affected by damp and mould, with cases reduced from 1,226 to 485 between March and December 2025 Report P13
Timeline
August 2024: RSH inspection of Southwark's Housing Department, resulting in a C3 grading Report P5
27 November 2024: Regulator publishes Judgement of Southwark's Housing Services Report P39
2025/26: Around £85m invested in maintenance, safety and decent standards; £100m capital programme budget Report P6, P58
March 2025 to December 2025: Damp and mould cases reduced from 1,226 to 485; Category 1 hazards down from 39 to 4; valid electrical certificates rose from 24.74% to 57.03% Report P13, P16
End of September 2025: Full stock condition and engineering asset survey began Report P49
2025/26: Over 1,000 inefficient non-condensing boilers being replaced Report P36
By end of March 2026: Target for full electrical safety compliance, access permitting Report P17
Autumn 2026: Two specialist fire safety contractors expected to be in place; new 5-year investment plan to be brought to Cabinet Report P27, P51
Middle of 2026: True Compliance IT platform to be in place across all workstreams Report P35
Plain English for the jargon
RSH: Regulator for Social Housing, the body that inspected Southwark's housing services and set the C3 grading
C3 grading: A regulatory judgement indicating the landlord is delivering outcomes below the required standard and must improve
DLO: Direct Labour Organisation, the council's in-house repairs workforce
EICR: Electrical Installation Condition Report, the inspection programme covering electrical safety and smoke alarm checks
HRB: High-rise building, subject to specific building safety resident engagement under the Building Safety Resident Engagement Strategy
WH:SHF: Warm Homes: Social Housing Fund, the government grant of £1.3m supporting energy efficiency design work
LCP Framework and DPS: Procurement routes via London Construction Programme, used to call off 13 tenders for engineering services
SELCHP: South East London Combined Heat and Power plant, a source of low carbon heat being extended to some estates
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item16
Resolved
That the committee noted positive trends in relation to performance against the Improvement Plan agreed with the Regulator for Social Housing (RSH), and good progress towards our commitment to become a Good Landlord, including plans to strengthen the Repairs Service. 2. That the committee noted ongoing delivery of the current capital investment programme, and its focus on health, safety and compliance. 3. That the committee noted the timeline for the development of a new 5-year investment plan, based on the findings of the stock condition survey and engagement with our residents and stakeholders.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Audit, Governance and Standards Committee, 8 pages
Recommendations
1. That the committee notes positive trends in relation to performance against the Improvement Plan agreed with the Regulator for Social Housing (RSH), and good progress towards our commitment to become a Good Landlord, including plans to strengthen the Repairs Service.
2. That the committee notes ongoing delivery of the current capital investment programme, and its focus on health, safety and compliance.
3. That the committee notes the timeline for the development of a new 5-year investment plan, based on the findings of the stock condition survey and engagement with our residents and stakeholders.
BACKGROUND INFORMATION
4. Following the August 2024 inspection by the RSH, and subsequent C3 grading, Southwark’s Housing Department, including the Repairs and Maintenance Directorate, has been working to improve services through delivery of the improvement plan agreed with the Regulator. Some progress highlights are set out below.
5. In 2025/26, we are investing c.£85 million into making sure council homes are well maintained, safe and meet modern, green and decent standards. Across the next two financial years, we will spend close to £80m per annum, as well as securing external funding for works to external wall systems, in line with building safety and fire safety legislation. This is a major investment in our residents’ homes, and it plays a vital role in delivering our Good Landlord Plan.
6. We are delivering this work across all teams in Repairs and Maintenance: Planned Maintenance (Major Works), Responsive Repairs, Engineering and Compliance and Building Safety.
KEY ISSUES FOR CONSIDERATION
1 Response to the RSH – the Housing Improvement Plan
7. Regarding Responsive Repairs, we continue to focus on mobilising and delivering our improvement programme, which includes strengthening learning and development, improving customer experience and access to services, tackling damp and mould, embedding a new management structure, investing in the DLO through a new workforce strategy, improving data insight to drive continuous improvement, and strengthening financial management.
8. Specifically on Damp and Mould, significant improvements in case management and interdepartmental working have been made. Escalation arrangements for complex or long-running cases have been strengthened, and weekly meetings between Repairs and the Housing Complaints Team have been introduced to review cases, agree next steps, and drive clear timescales for inspections, surveys, and remedial works, with responsibilities clearly assigned.
9. Relationships with Public Health have been enhanced to redesign tenant vulnerability assessments and triaging processes, including improved information sets and screening tools to better identify at risk households.
10. Current performance is improving, with open cases assessed as Category 1 hazards down from 39 in March 2025 to 4 in December. Total damp and mould cases have been reduced from 1226 to 485 in the same period.
11. Fire risk assessment compliance remains high, with 100% of properties having an up-to-date assessment in July 2025. This has dipped to 99.5% in December, due to technical and resource challenges, but it is expected full compliance will be regained before the end of the financial year.
12. We continue to reduce the number of overdue actions through a coordinated, cross-departmental approach that prioritises high-risk issues. A weekly review meeting is now in place, and a compliance consultant is overseeing delivery. A comprehensive review was undertaken, across all task owners, which has seen the number of overdue high-risk tasks fall from 176 in July to 11 in December. Medium and low-risk tasks have also been reduced.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Audit, Governance and Standards Committee at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.