AI summarySouthwark Cabinet approved completing a 250 year lease of phase B2 retail units at Canada Water, using existing budgets. The chief executive will negotiate price and terms, with the leader deciding if the final price is more than 5% above the closed report estimate.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedCouncil approved completing the 250 year lease
MoneyRevenue contribution to capitalA regeneration and development reserve release will also fund it
What happens nextNegotiate price and final leaseFinal price more than 5% above estimate goes to leader
Who it affectsCanada Water town centreLibrary, plaza and retail letting are affected
What was decided
Southwark Cabinet approved completion of a 250 year lease of the phase B2 retail units at Canada Water, as shown on plan 1.
The chief executive may negotiate the option price and final lease, provided they represent best consideration. If the final option price is more than 5% higher than the closed report estimate, the leader will decide whether to proceed.
Cabinet noted that further feasibility would assess the option to purchase the long lease of phase A3 retail units. An appropriate allowance will be put into the capital programme for financial year 2012/2013. Report P3
Why
Taking the lease would give the council control of the letting policy. The council could manage the units to support the new library and plaza, the night time economy and regeneration. Report P20, P35
The purchase price would be discounted and property values were expected to rise. The council could later sell the improved asset to support the capital programme. Disposal could carry minimum risk to regeneration objectives. Report P5, P21
The closed report business case concluded that the phase B2 option should be exercised. The phase A3 option should be considered in detail once it has been constructed. Report P23, P16
What happens next
The chief executive will negotiate the option price and final lease, provided they represent best consideration. If the final option price is more than 5% higher than the closed report estimate, the leader will decide whether to proceed.
Further feasibility will be prepared in due course for the phase A3 long lease purchase option. An appropriate allowance will be put into the capital programme for financial year 2012/2013. Report P3
Property Services will lead further lease negotiations with Barratt Homes and its legal advisers. The priority is permission to let the units to others or transfer the lease without restriction. Taking the lease is expected to use a tri-partite agreement involving the council, BDW Trading and Peverel. Report P17, P49, P54
The money
5% Final option price increase above the closed report estimate that requires the leader to decide whether to proceed
Options considered
Chosen: Complete the 250 year lease of phase B2 retail units. The business case concluded that the option should be exercised. Ownership would support regeneration and an appropriate setting for the library and plaza. Report P20, P23, P35
Chosen: Prepare further feasibility for the phase A3 long lease purchase option. Phase A3 had planning consent but no work on site and no option notice. The council chose to assess its benefit and provide an allowance in the capital programme for financial year 2012/2013. Report P3, P16
Implications
Financial: The option price is fixed at a rate per square foot of gross external area. The project will use a revenue contribution to capital and a release from the regeneration and development reserve. Report P14, P51
Financial: The longer term business model is scheduled to produce sustained income from the retail units. Income can support regeneration across the borough and replenish the capital reserve, while a later disposal could generate a capital receipt for the corporate resource pool. Ground floor units will be let at open market value to prospective occupiers. Report P51, P53
Legal: The Strategic Director advises that sections 120(1) and 120(2) of the Local Government Act 1972 provide adequate powers to acquire the lease. Acquisition is for the benefit, improvement and development of Canada Water. Report P44, P46, P47, P48
Legal: The final lease form is not agreed. The decision delegates negotiation to the chief executive, while the officer recommendation names the Head of Property; Eversheds LLP is providing legal advice. Report P2, P49
Legal: The council should secure permission to let the units to other businesses or transfer the lease without restriction. The 21 December 2007 sale contract says there should be no restrictions on assignments or under lettings on the open market. Report P54
Risk: Failure to find a suitable tenant would remove expected rental income and mean the payback period is not met. The report sees suitable occupants as likely because Canada Water is attracting investors and CBRE supports this view. Tenants may seek rent free periods for shop fitting work, while building work may delay lettings, although the report assesses the delay risk as not highly likely. Report P25, P27, P28, P29, P30, P32
Staffing: The units will be held in the managed property holding account and managed within the commercial property portfolio. Day to day management will pass to the investment portfolio team within Property Services. Report P39, P53
Other: Exercising the option creates an opportunity to enhance the new civic plaza and benefit all of the local community. Report P37
Who and where
Retail tenants and prospective occupants Report P25, P53
Local community around the library and plaza Report P35, P37
Council commercial property portfolio Report P39, P53
Regeneration programme across the borough Report P51
Barratt Homes, BDW Trading and Peverel Report P17, P53
Timeline
5th April 2005: The council and British Land Canada Quays Ltd signed a strategic development agreement for regenerating Canada Water. Report P6
11th October 2005: Executive approved the masterplan. Report P6
18 December 2007: Executive authorised the sites A and B agreement, which was dated 21 December 2007. Report P13, P14
28 February 2010: The phase B1 option notice expired without being taken up. Report P16
29 June 2010: The officer report was dated in its final version. Report P60
middle of 2011: The library and plaza were due to complete construction. Report P12
financial year 2012/2013: An appropriate allowance will be put into the capital programme for phase A3. Report P3
15 July 2010: The phase B2 retail option notice period was due to expire. Report P16
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
1 That approval be given to the completion of a 250 year lease of the retail units in phase B2 of the Canada Water development, located as shown on the plan attached to the report (plan 1) and authority be delegated to the chief executive to negotiate the option price and final form of lease provided that they represent best consideration. If the final option price is more than 5% higher than the estimated price stated in the closed report then the decision on whether to proceed be delegated to the leader of the council. 2 That it be noted that a further feasibility will be prepared in due course to consider the option to purchase the long lease of the retail units in phase A3 of the Canada Water Development and that an appropriate allowance will be put into the capital programme for financial year 2012/2013.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 6 pages
Recommendations
The cabinet is asked to:
6. Give approval to the completion of a 250 year lease of the retail units in phase B2 of the Canada Water development, located as shown on the plan attached as plan 1, and to delegate to the Head of Property authority to negotiate the option price and final form of lease provided that they represent best consideration.
7. Note that in due course a further feasibility will be prepared to consider the option to purchase the long lease of the retail units in phase A3 of the Canada Water Development and that an appropriate allowance will be put into capital programme for financial year 2012/13.
BACKGROUND INFORMATION
8. The council has the opportunity to underpin its investment in the new Canada Water library and plaza by exercising an option to buy from Barratt Homes a long lease in the retail space being built at sites A and B. Ownership of these assets will allow the council, through its letting policy, to enhance the setting for the new library, take advantage of the discounted purchase price for the shops and benefit from the anticipated rise in property values. Subsequently the council will have the option of selling the improved asset at any time to support the capital programme.
9. On 5th April 2005 a strategic development agreement was signed between the council and British Land Canada Quays Ltd (BLCQ) for the regeneration of the Canada Water area. The agreement required BLCQ to create a masterplan, which was approved by Executive on 11th October 2005.
10. After an initial period of public consultation and masterplanning the project is now in its delivery phase. This will see the area take full advantage of its central location and impressive public transport infrastructure (which is being further improved) to emerge as a renewed, vibrant and exciting residential quarter within inner London.
11. The philosophy behind the regeneration has been to follow a multifaceted approach in order to produce a sustainable community. One key element of this is the council’s investment in the iconic Canada Water library, which along with the adjoining plaza will create a new civic heart for Rotherhithe.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.