AI summarySouthwark Cabinet approved contract changes releasing Barratt from its 11KV supply duty and increasing its plaza contribution. [D] [P2] [P11] It also noted the planning overage, payable on or before 4 July 2011. [D] [P3] [P12]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedBarratt released from 11KV duty; plaza contribution increased. [P11]
MoneyBoth payments due on or before 4 July 2011. [P11] [P12]
What happens nextExecute deed of variation [D] [P10]Amend the 21 December 2007 sale contract. [P10]
Who it affectsNot stated

What was decided

Southwark Cabinet approved the changes to the sale contract for site A and most of site B at Canada Water. Report P2

The variation removes Barratt's duty to provide a new 11KV high voltage electricity supply and the council's duty to contribute towards its cost. Report P11, P39

Barratt's contribution towards the new plaza is increased. The council noted the planning overage. Both payments are payable on or before 4 July 2011. Report P3, P11, P12

Why

EDF allocated the Deptford supply to another customer after the land sale, so Barratt arranged a new supply from Neckinger substation. The replacement supply had significantly lower capacity. Report P16

The 11KV supply offered significantly more capacity than Barratt needed, and there was no immediate need for the additional supply. Report P15, P28

Barratt agreed to make an additional contribution towards the new plaza in return for release from the supply duty. Report P28, P44

What happens next

A deed of variation is to amend the sale contract dated 21 December 2007. Report P10

Barratt's increased plaza contribution is payable on or before 4 July 2011. Report P11

The planning overage is payable to the council on or before 4 July 2011. Report P12

Options considered

  • Chosen: Release Barratt from the 11KV supply obligation. Barratt agreed to make an additional plaza contribution, and there was no immediate need for the higher capacity supply. Report P26, P28
  • Rejected: Insist that Barratt provides the 11KV supply. This would expose the LBS / BLCQ development account to a financial contribution. Report P26, P28

Implications

  • Financial: The council is released from its obligation to contribute towards the new electricity supply. Report P11, P45
  • Financial: Barratt's additional plaza contribution and the planning overage are payable on or before 4 July 2011. Report P11, P12
  • Financial: The council's eventual net receipt increases because it is released from the electricity supply contribution. Report P45
  • Legal: The amount paid for the land does not change, but payments for electricity, overage and plaza works do. Report P39
  • Legal: No adverse legal implications were identified for the proposed contract variation. Report P41
  • Risk: Insisting on the 11KV supply would expose the LBS / BLCQ development account to a financial contribution. Report P28
  • Other: The net adjustment exceeded the Head of Property's delegated authority, so Cabinet approval was required. Report P40
  • Other: No particular policy or community impacts were identified. Report P30, P32

Who and where

  • Barratt, purchaser for site A and most of site B Report P9, P11, P12
  • Southwark Council Report P39, P45
  • British Land Canada Quays Ltd, strategic development partner Report P9, P28
  • The public plaza around the new Canada Water library Report P9, P11, P19
  • Future landowners and developers Report P28

Timeline

  • April 2005: The council entered a development agreement with British Land Canada Quays Ltd for phased regeneration of six sites. Report P5
  • 18 December 2007: The Executive agreed in principle to sell site A and most of site B. Report P6
  • 21 December 2007: The contract of sale was signed. Report P7
  • After the sale of the land to Barratt: EDF allocated the Deptford supply to another customer, and Barratt arranged a supply from Neckinger substation with significantly lower capacity. Report P16
  • 9 June 2011: The final report was dated. Report P51
  • on or before 4 July 2011: The increased plaza contribution and planning overage are payable. Report P11, P12
  • 2026-05-28: The decision to approve the contract changes was recorded.

Plain English for the jargon

  • Planning overage: A payment to the council based on residential floor space over the level granted planning consent, less certain costs. [P9] [P12] [P21]
  • Deed of variation: A document used to amend the 21 December 2007 sale contract. [P10]
  • 11KV high voltage electricity supply: The supply originally required for Barratt's site and other Canada Water development sites. [P9]
  • Development account: The account charged with project costs and funded through receipts from land sales. [P5]
  • Public plaza: Public space on part of site B around the new Canada Water library, to be constructed by BLCQ. [P9] [P19]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item19

Resolved

That the changes to the contract for the sale of site A and most of site B at Canada Water (see the plans attached as appendices 1 and 2 to the report) as set out in paragraph 6 of the report be approved. 2. That the level of planning overage to be paid to the council as detailed in the report on the closed agenda be noted.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 5 pages

Recommendations

That Cabinet:

1. Approves the changes to the contract for the sale of site A and most of site B at Canada Water (see the plans attached as appendixes 1 and 2) as set out in paragraph 6.

2. Notes the level of planning overage to be paid to the council as detailed in the report on the closed agenda.

BACKGROUND INFORMATION

3. In April 2005 the council entered into a development agreement with British Land Canada Quays Ltd. (BLCQ) to bring about the comprehensive regeneration of the six sites shown at appendix 3. The development was to be delivered in phases in accordance with a masterplan to be prepared by BLCQ, who was also to deliver planning consent for the scheme. BLCQ are responsible for the day- to-day conduct of the project including the marketing for sale of council land. Costs are charged to a development account and recovered from the receipts from land sales.

4. At is meeting on 18 December 2007 the Executive agreed in principle to the sale of site A and most of site B at Canada Water and delegated to the Head of Property authority to agree the final terms provided they represented best consideration.

5. Those negotiations concluded on 21 December 2007 with the signing of a contract of sale and for the purposes of this report the key terms are as follows:

 The sale is a tri-partite agreement between the council, its strategic

1 development partner BLCQ and the purchaser BDW Trading Ltd (who trade as Barratt Homes).  The sale price includes planning overage that is calculated on the amount of residential floor space over a set level that is granted planning consent less certain costs.  Barratt shall provide a new 11KV high voltage electricity supply to the area to serve their site and other development sites in Canada Water.  The council and BLCQ shall make a contribution towards the cost of the new supply.  Barratt shall make a contribution towards the cost of creating a new public plaza on part of site B around the new Canada Water library.  BLCQ shall construct the new plaza.

6. For the reasons explained below this report recommends that a deed of variation be entered into that will amend the sale contract dated 21 December 2007 as follows:

 To remove the obligation on Barratt to provide a new 11KV high voltage electricity supply and the corresponding obligation on the council to contribute towards the cost of that supply.  That Barratt’s contribution towards creating the new plaza should be increased, which shall be payable on or before 4 July 2011.

7. Cabinet is also asked to note the final agreement with Barratt on the level of planning overage. The overage shall be payable on or before 4 July 2011.

High voltage electricity supply

8. At the time of the marketing of sites A and B it was know that the local electricity network was operating at capacity. EDF had confirmed that they could increase capacity by taking an 11KV supply from the Deptford major substation. Throughout this period the Deptford option was the only solution offered by EDF.

9. An 11KV supply was significantly more capacity than required by Barratt and so as part of the sale negotiations it was agreed the council and BLCQ would make a contribution towards the cost.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Site A Canada WaterAppendix 1 1 pages Download
PDF
Site B Canada WaterAppendix 2 1 pages Download
PDF
Strategic Development Agreement SitesAppendix 3 1 pages Download
PDF
Report: Improved terms for the sale of sites A and B at Canada WaterReport 5 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 11 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-FyleCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, present
AM
Councillor Abdul MohamedCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present
AS
Annie ShepperdOfficer, expected
DC
Deborah CollinsOfficer, expected

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies