Revised Office Accommodation Strategy

Agreed Executive 2 papers

AI summaryCabinet approved a revised office accommodation strategy that moves the three town halls out of operational use and requires plans for a shared operational centre, avoiding the £7million capital allocation for 19 Spa Road. [D] [P3] [P4] [P6] [P135]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedThree town halls released and functions reallocated [D] [P5]
Money£7million [P135]19 Spa Road capital allocation saved [P135]
What happens nextProperty disposals to begin [D]Sale and lease work starts immediately [D] [P11]
Who it affectsNot stated

What was decided

The principles in appendix 1 were agreed and the strategy components were approved. The three town halls will not remain operational, and their remaining functions will be reallocated. [D] [P2] [P3] [P4] [P5]

17 Spa Road was confirmed as surplus from 30 September 2011. Officers must plan a large shared operational office in the centre or south of the borough, provide alternative customer services, and investigate moving the 17 Spa Road pavilion to Camberwell. [D] [P6] [P7] [P8] [P9]

The Finance Director must include resource and capital implications in the relevant council plans and identify required funding. Officers must begin preparing property sales, lease sales and lease terminations on best terms. [D] [P10] [P11]

Why

The three town halls were not affordable to retain. Occupation beyond the very short term required significant capital investment, and the halls cost £1.5 million a year to maintain, with costs increasing as they aged. [P4] [P35] [P38]

The dispersed estate had poor condition, weak public transport access and high maintenance costs. Ageing buildings required capital investment that reduced funds available for other council priorities. [P27] [P30] [P31]

A modern shared workspace could reduce property liabilities, facilities management costs and emissions. Consolidation could improve customer service and provide an alternate headquarters if Tooley Street suffered a major disruption. [P132] [P133] [P144] [P146]

What happens next

Officers must bring forward plans for a large shared operational office facility in the centre or south of the borough. A preferred building was identified, and negotiations with its developers were continuing. [D] [P6] [P68] [P74]

Officers must provide alternative customer services for Bermondsey One Stop Shop users. They must also investigate relocating the pavilion to Camberwell, including D'Eynsford Road, with wider regeneration plans, needs analysis, consultation, feasibility work, a business case and planning consent. [D] [P8] [P9] [P130]

The Finance Director must include resource effects in the medium term Policy and Resources Strategy and capital effects in the revised capital programme. Officers must begin preparing property sales, lease sales and lease terminations on best terms. [D] [P10] [P11]

The money

  • £7million Saved capital allocation for 19 Spa Road Report P135
  • £14 million Proposed, but not agreed, for Walworth Town Hall and Newington Library Report P136
  • £9 million Proposed, but not agreed, for Southwark Town Hall Report P136
  • £1.5 million a year Current maintenance cost for the three town halls Report P38
  • £20 million Investment needed for occupation beyond the very short term Report P35
  • £30 million Cost of agreed or proposed town hall development Report P48
  • £5m Proposed allowance for area based service delivery Report P54
  • £35,000 per annum Saving from moving the post room to Tooley Street Report P84

Options considered

  • Rejected: Retain the three town halls as operational buildings. Retention was not affordable and would require substantial capital investment and continuing maintenance. [P4] [P35] [P38] Report P4, P35, P38
  • Chosen: Provide a shared operational centre in the centre or south. It provides low cost flexible space for 400 to 600 staff, with customer access and good transport links. [P6] [P68] [P71] [P193] Report P6, P68, P71, P193
  • Rejected: Area based service delivery in multiple local locations. It had high capital and revenue costs, limited estate improvement and faced pressure from staff reductions. [P54] [P57] [P60] Report P54, P57, P60
  • Chosen: Keep specialist services in specialist sites, but rationalised. Specialist provision would remain at suitable sites while making better use of the available facilities. [P67] Report P67
  • Chosen: Use One Stop Shops or co-located facilities for customer access. This forms part of the revised customer contact approach and supports accessible customer access points. [P67] Report P67
  • Rejected: Develop 19 Spa Road for continuing council use. 19 Spa Road has poor transport access, and equivalent accommodation in a modern building would cost less and offer better sustainability and accessibility. [P42] [P72] Report P42, P72
  • Chosen: Relocate the 17 Spa Road pavilion to Camberwell. D'Eynsford Road has potential, but the proposal needs full investigation and consultation. [P9] [P127] [P130] Report P9, P127, P130
  • Chosen: Grant a long lease of Southwark Town Hall while retaining council chamber access. This is the preferred present route, subject to further negotiation and approval. It could reduce revenue costs and capital investment but would lower the capital receipt and take longer. [P82] [P83] Report P82, P83

Implications

  • Financial: The £7million capital allocation for 19 Spa Road will be saved. The report identifies proposed, but unagreed, investments of £14 million and £9 million, and says overall facilities management costs will be reduced. Property disposals and leases will generate capital receipts. [P83] [P102] [P133] [P135] [P136] Report P83, P102, P133, P135, P136
  • Legal: Planning consent is needed for the 17 Spa Road sale and Camberwell pavilion proposals. Listed status adds constraints for 19 Spa Road and Walworth Town Hall. [P72] [P119] [P130] Report P72, P119, P130
  • Equalities: A full equality impact assessment will run alongside development and implementation. Better access may help disabled staff and residents, while consultation must identify staff impacts. [P159] [P170] [P176] [P181] Report P159, P170, P176, P181
  • Climate: The model could make a significant contribution to the council wide reduction target of 60% by 2016/17. Meeting it requires total savings of 25,000t CO2. [P147] Report P147
  • Risk: Consolidation should reduce long term repair liabilities and improve health and safety compliance. It would also provide an alternate temporary headquarters if Tooley Street suffered a major disruption. [P141] [P146] Report P141, P146
  • Staffing: Relocation would affect up to 1,000 staff, about 20% of the workforce. Staff with caring responsibilities may find relocation difficult, so consultation and mitigation are required. [P162] [P178] [P179] Report P162, P178, P179
  • Other: Alternative customer services must replace the 17 Spa Road offer. Vulnerable client groups must be told about changes in service locations. [P171] [P172] Report P171, P172
  • Other: Council Assembly meetings and civic functions may move to more accessible venues. Alternative venues and their costs must be assessed. [D] [P5] [P81] [P170] Report P5, P81, P170

Who and where

  • Up to 1,000 council staff Report P162
  • Current users of Bermondsey One Stop Shop Report P8
  • Disabled residents and meeting participants Report P170
  • Vulnerable client groups Report P172
  • Staff with disabilities Report P176
  • Staff with caring responsibilities or older staff Report P177
  • Recruitment target groups including the BME community, women and disabled people Report P175
  • Local residents and businesses near disposal sites Report P189

Timeline

  • January 2007: The initial Office Accommodation Strategy was agreed Report P14
  • May 2007: The Office Accommodation Strategy was revised Report P14
  • 21 October 2008: The Three Town Halls and Residual Estate Strategy was agreed Report P4, P33
  • 16 October 2010: A planning application was submitted for 17 Spa Road and adjoining Site C5 Report P119
  • early 2011: Detailed customer service proposals were due Report P122
  • March/April 2011: The council may complete the sale of both sites Report P120
  • 30 September 2011: 17 Spa Road was to become surplus to requirements Report P7, P122
  • 2026-05-28: Cabinet approved the revised office accommodation strategy

Plain English for the jargon

  • One Stop Shop: A customer service access point for residents and service users. [P67] [P115]
  • Shared operational centre: A shared office facility for 400 to 600 staff in the borough centre or south. [P68] [P71]
  • Tooley Street: The council's administrative and management centre at 160 Tooley Street. [P68] [P98]
  • Council Assembly: The council's democratic meeting body, currently held at Southwark Town Hall. [P81]
  • Capital receipt: Income received by the council from property disposal or leasing. [P83] [P132]
  • Residual estate: The council's dispersed offices outside 160 Tooley Street. [P27] [P50]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

That the principles to be applied when planning for the council’s office accommodation needs as set out in appendix 1 of the report be agreed. 2. That the components of the strategy developed by officers in accordance to these principles be approved: · Concludes that the retention of Southwark’s three town halls as operational buildings as agreed on 21 October 2008 by the then executive is not affordable; · That the future use of Southwark Town Hall, Walworth Town Hall and 19 Spa Road (known as Bermondsey Town Hall) and the functions remaining within the town halls are reallocated in accordance with the detail as described from paragraph 47 of the report; · That officers bring forward plans to provide for a large shared operational office facility in the centre or south of the borough; · That it be confirmed that 17 Spa Road will be surplus to requirements from 30 September 2011; · That officers provide alternative means of providing customer services to the current users of the Bermondsey One Stop Shop; · That officers develop proposals for the relocation of the pavilion building currently at 17 Spa Road to Camberwell through a full investigation of potential sites, including D'Eynsford Road, integration with wider plans for regeneration in Camberwell, following a complete needs analysis and consultation. 3. That the finance director incorporate all resource implications arising from the agreed programme within the policy and resources strategy for 2011/12-2013/14 and to incorporate capital implications within the revised capital programme for agreement by council assembly. The finance director to identify required funding in consultation with the cabinet member for finance and resources. 4. That officers commence preparation immediately on best terms for the sale of freehold, sale of leases and termination of leases, of property held by the council and released through this strategy.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 22 pages

Recommendations

That the Cabinet:

7. Agrees the principles to be applied when planning for the council’s office accommodation needs as set out in appendix 1;

8. Approve the components of the strategy developed by officers in accordance to these principles:

 Concludes that the retention of Southwark’s three town halls as operational buildings as agreed on 21 October 2008 by the then Executive is not affordable;

 The future use of Southwark Town Hall, Walworth Town Hall and 19 Spa Road (known as Bermondsey Town Hall) and the functions remaining within the town halls are reallocated in accordance with the detail as described from paragraph 47.

 Instructs officers to bring forward plans to provide for a large shared operational office facility in the centre or south of the borough;

 Confirms that 17 Spa Road will be surplus to requirements from 30 September 2011;

 Instructs officers to provide alternative means of providing customer services to the current users of the Bermondsey One Stop Shop;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Revised Office Accommodation Strategy: Appendix 1Appendix 1 pages Download
PDF
Revised Office Accommodation Strategy: ReportReport 22 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-FyleCommittee Member, present
JF
Councillor John FriaryCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, apologies
AM
Councillor Abdul MohamedCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open