Adoption of refreshed Southwark Economic Development Strategy 2010-16
ApprovedExecutive5 papers
AI summarySouthwark Cabinet approved the revised Economic Development Strategy 2010-2016, adopted it as the borough's local economic assessment and approved the council's role in the 2010/11 delivery plans. No additional council resources were requested. [D] [P62]
Written from the decision and the officer reportPDF Pro
OutcomeApprovedCouncil role in 2010/11 delivery plans approved [D]
MoneyNot stated
What happens nextLocal Economy Group oversight [P41]Delivery plans will be reviewed for 2011-12 and annually thereafter [P61]
Who it affectsResidents, businesses and partners [P42] [P46]Priorities include workless residents and deprived town centres [P46] [P54]
What was decided
Cabinet approved and adopted the revised Southwark Economic Development Strategy 2010-2016. Report P2
The strategy was also adopted as the borough's local economic assessment to meet the council's assessment duty. Report P3, P43, P44
Cabinet noted and approved the council's role in the associated 2010/11 strategic delivery plans. Report P4
Why
The first three year review found that existing objectives remained valid, but the strategy needed to reflect recession, uncertain recovery, spending reviews and reforms to welfare to work and skills policy. Report P8, P19
The refreshed approach emphasises the skills gap, business and employer engagement, enterprise activity in outlying areas and town centres, new businesses, self employment and stronger partnership working. Report P21, P22
The Local Democracy, Economic Development and Construction Act 2009 requires the council to prepare an assessment of local economic conditions. Report P43, P76
What happens next
The Local Economy Group will use the delivery plans to show partner resources, mainstream provision and contributions to the strategy's objectives. Report P61
There are no partner resource commitments beyond March 2011, and the delivery plans will be reviewed for 2011-12 and annually thereafter. Report P61
The council's Economic Development Team will support implementation using existing staffing, while officers keep future assessment guidance under review. Report P44, P66
The money
£10-£50 million The total contracting value for DWP's new Single Work Programme across London, with 3 to 8 providers. Report P40
Options considered
Chosen: Adopt the revised Southwark Economic Development Strategy 2010-2016. The Southwark Alliance endorsed it following the first three year review. Report P8, P9
Chosen: Adopt the strategy as the borough's local economic assessment. The evidence base fulfilled the requirement to prepare a local economic assessment. Report P15, P43, P44
Chosen: Note and approve the council's role in the strategic delivery plans. The council has significant lead and supporting roles in delivering the strategy. Report P4, P42, P61
Implications
Financial: No additional council resource commitment is sought. Any specific strategy proposal must confirm funding and receive formal approval under procurement protocols. Report P81
Financial: Reduced council funding and the Working Neighbourhoods Fund cut will limit the level of service the Economic Development team can deliver. Report P64, P80
Legal: Adoption meets the local economic assessment duty. The assessment has no statutory content guidance or monitoring and may be revised at any time. Report P43, P76
Equalities: The strategy sets out to steer employment and skills services towards priority groups, including young people, BME residents, women, disabled people and people with mental health needs. Report P52
Risk: London wide contracting leaves little scope for specialist delivery tailored to the needs of individual boroughs and wards. Report P40
Other: The strategy provides a partnership framework for regeneration. The Local Economy Group oversees implementation and partner accountability. Report P38, P41, P61
Staffing: Existing Economic Development Team resources will support implementation, with no additional staffing proposed. Report P66
Risk: Partners cannot commit resources beyond March 2011 because spending reviews and policy changes make future commitments uncertain. Report P61
Who and where
The whole community in every ward, including the borough's business community Report P46
Workless residents facing barriers involving skills, childcare, employer access, health, disability, information, housing and personal circumstances Report P47, P48
Ex offenders, young offenders, BME residents, women, young people, people with alcohol or drug dependency, homeless people, refugees, disabled people, people over 50, people with mental health needs and families with young children, particularly lone parents Report P52
Businesses and employers, particularly private sector organisations Report P21
Residents in Livesey, East Walworth, Nunhead, Peckham, Riverside, South Bermondsey, Camberwell Green, Grange, Newington, Rotherhithe, The Lane, Cathedrals, College, Faraday, Peckham Rye and Surrey Docks Report P53
Businesses and communities around Peckham, Camberwell, Bermondsey and Elephant and Castle Report P54
Young people aged 18 to 24, who were disproportionately affected by the recession Report P51
Delivery partners in the Local Economy Group, including Jobcentre Plus, Southwark College and the London Development Agency Report P41, P66
2009: The two phase consultation began. Report P67
11 November 2010: The final officer report was dated. Report P86
2010-11: Year 1 delivery plans covered this period, using existing council budgets for identified actions. Report P62, P84
March 2011: Partner resource commitments stop at this point. Report P61
2011-12: Council resources and delivery plans were due for review. Report P59, P61
annually thereafter: The delivery plans were to be reviewed each year. Report P61
Plain English for the jargon
Local economic assessment: A council assessment of local economic conditions, required by section 69 of the 2009 Act. [P43] [P76]
Local Economy Group: The forum that oversees and governs strategy implementation on behalf of Southwark Alliance. [P41]
Southwark Alliance: The partnership body whose thematic groups and partners contributed to the refreshed strategy. [P39] [P67] [P72]
Jobcentre Plus: The mainstream service provider for economically inactive people seeking jobs and training. [P40]
Single Work Programme: A DWP programme with contracts for services across London delivered by 3 to 8 providers. [P40]
Working Neighbourhoods Fund: A funding source used with council project funding and other sources for employment and enterprise work. [P60] [P64]
Section 106 Supplementary Planning Document: A planning document used to clarify negotiations for economic benefits from planning obligations. [P39]
Strategic delivery plans: Plans showing partner resources, mainstream provision and contributions to strategy objectives. [P61]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
That the revised Southwark economic development strategy 2010-2016 (attached as appendix 1 of the report) be approved and adopted. 2. That the revised Southwark economic development strategy 2010-2016 be approved and adopted as the borough’s local economic assessment, in response to the local authority economic assessment duty. 3. That the council’s role in the associated 2010/11 strategic delivery plans (attached as appendices 2 & 3 of the report) be noted and approved.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 11 pages
Recommendations
That the Cabinet
3. Approve and adopt the revised Southwark Economic Development Strategy 2010 – 2016 (attached as appendix 1)
4. Approve and adopt the revised Southwark Economic Development Strategy 2010-2016 as the borough’s local economic assessment, in response to the local authority economic assessment duty.
5. Note and approve the council’s role in the associated 2010 - 11 strategic delivery plans (attached as appendices 2 & 3) 1 BACKGROUND INFORMATION
Southwark’s Economic Development Strategy
6. The Southwark Alliance employment and enterprise strategies were first developed in 2002 to address the high levels of unemployment and deprivation in Southwark with the aim to create employment opportunities for Southwark residents who were most disadvantaged in the labour market, to encourage small firms to thrive, and to promote enterprise activity in deprived areas and amongst disadvantaged groups.
7. The strategies were comprehensively revised and developed in 2005 following wide stakeholder and public consultation. The subsequent Southwark Alliance employment and enterprise strategies 2006 – 2016 were endorsed by the Southwark Alliance and adopted by the Council Executive in 2005 with a commitment to review them every three years to reflect changing economic and policy contexts.
8. As partnership documents the strategies were owned by the Southwark Alliance Employment and Enterprise Partnerships; following the merger of the latter into the new Local Economy Group, ownership has transferred accordingly. Over the last year, the strategies have undergone their first three year review to assess whether they are still fit for purpose to deliver the strategic objectives set out in Southwark 2016 and the corporate plan’s aims to improve life chances and build a vibrant economy.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.