Elephant and Castle – Provision of a new leisure facility

Noted Executive 3 papers

AI summarySouthwark Cabinet agreed the core design for an Elephant and Castle leisure centre with a swimming pool and four court sports hall, with capital costs in the region of £20m. [D] [P5] [P35] It delegated planning approval and the first Gateway decision on appointing the Local Education Partnership. [D] [P9] [P10]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedConsultation supported Option B, with pool and sports hall. [P32]
Money£20m capital estimate [P35]Option B could fit this envelope, subject to design. [P35]
What happens nextCosting and Gateway reviews [D]Officers will report on sale terms and construction award. [D]
Who it affectsResidents and leisure users [P73]Pool and sports hall could increase leisure choice. [P73]

What was decided

Cabinet noted the consultation carried out throughout September and October, and the proposed provisional budget. Further work will assess project costs before a capital programme funding bid. [D] [P2] [P3] Report P2, P3

Cabinet agreed the project mandate for redevelopment of the leisure centre site. Core provision is a 6 lane 25m swimming pool, a learner pool, a 4 court sports hall, a gym, an exercise studio, a crèche and a cafe. [D] [P4] [P5] Report P4, P5

Officers must report back on terms for selling the adjoining residential plot and, after all design and technical work, recommend the construction contract award through the second Gateway. The Leader delegated planning approval before submission to the Cabinet Member for Regeneration and Corporate Strategy. The Leader also delegated the first Gateway appointment of the Local Education Partnership to the Cabinet Member for Finance and Resources, subject to existing protocols and value for money. [D] [P6] [P7] [P9] [P10] Report P6, P7, P9, P10

Why

The consultation drew 1,316 replies from 8,190 letters and reply cards, a 16% response compared with the 5% originally hoped for. Respondents ranked a swimming pool first, and the findings supported Option B. [P26] [P27] [P30] [P32] Report P26, P27, P30, P32

An 8 court sports hall would reduce the residential plot to a non viable size. Retaining a viable residential plot was crucial to generating the capital receipt for the leisure centre. [P33] [P55] Report P33, P55

The current offer was restricted to a sports hall and gym, and the swimming pool had been closed for over twelve years. A new facility including a swimming pool could increase leisure choice and activity and support improved health outcomes. [P73] Report P73

What happens next

Complete detailed design and technical work and assess project costs before a capital programme funding bid. Further budget testing runs until the end of the financial year 2010 / 11, with the Project Board keeping the budget under review. Through the first Gateway, test the Local Education Partnership proposal for value for money, with independent cost, technical and commercial advice. [P3] [P36] [P37] [P38] [P46] Report P3, P36, P37, P38, P46

Submit a hybrid planning application, with outline planning for housing and detailed planning for leisure. Officers will report back on the adjoining residential plot sale terms at the appropriate time. [D] [P6] [P61] [P82] Report P6, P61, P82

Through the second Gateway, recommend the construction contract award once design and technical work is complete. Officers will manage the interim closure and relocation arrangements with Fusion. [D] [P7] [P50] [P51] Report P7, P50, P51

The money

  • £20m Estimated capital cost for developing a new leisure facility. Option B could fit this budget envelope, subject to full detailed design and technical surveys. Report P35

Options considered

  • Chosen: Option B leisure centre. Includes all of Option A plus a four court sports hall. The consultation supported Option B and it was taken forward. Report P21, P32, P33
  • Rejected: Option A leisure centre. It excludes the four court sports hall. The consultation supported Option B instead. Report P20, P32
  • Rejected: 8 court sports hall. Spatial requirements would reduce the residential plot to a non viable size, making funding for the project difficult. Report P33, P55
  • Chosen: Local Education Partnership procurement route. Delegated for appointment through the first Gateway, subject to existing protocols and value for money. It offers programme advantages, risk transfer and added cost certainty. Report P10, P45, P46, P47
  • Rejected: Full EU tendering exercise. This was not the route selected now. Another procurement route would be needed if the Local Education Partnership could not offer acceptable value for money. Report P42, P48
  • Rejected: Further competitive tender after Local Education Partnership appointment. Any Local Education Partnership appointment would preclude a further competitive tender. Report P46
  • Rejected: Squash courts and other leisure uses. The most frequent other request was squash courts, from 52 individuals. This was 4% of replies and not significant enough to amend the strategic design brief. Report P31

Implications

  • Financial: The scheme must be funded from the council's capital programme, which largely relies on land sale receipts. Retaining a viable residential plot is crucial to generating the capital receipt for the leisure centre. Report P55
  • Risk: Option B could be delivered within the £20m budget envelope, subject to full detailed design and technical surveys. A fixed contract sum will only be known after planning. Report P35, P38
  • Risk: The Local Education Partnership route offers programme advantages, risk transfer and added cost certainty, but appointment requires value for money. If the proposal is unacceptable, another route will be needed and the timetable could extend. Report P45, P46, P48
  • Legal: The intended hybrid application has an outline element for housing and a detailed application for leisure. The report says the housing is proposed as enabling development and that the social housing requirement is not viable in this case because it funds the leisure centre. Report P61
  • Risk: Residential planning must address the busy highway intersection, the listed Metropolitan Tabernacle, height constraints, air quality and noise. The case for development without affordable housing must be justified because policy requires 35%, and an outline proposal needs a detailed heritage statement. Report P60, P90
  • Legal: The Fusion lease expires on 29 October 2016. It has no provision for early termination except through termination of the management agreement, so early ending would require agreement with Fusion. Report P81
  • Other: During demolition and construction, officers will negotiate closure variations with Fusion to minimise disruption and cost. Displaced users will be relocated where possible, but not everyone can be accommodated. Report P50, P51
  • Equalities: The present offer is limited to a sports hall and gym, and the pool has been closed for over twelve years, reducing access to leisure facilities. A new pool could increase leisure choice and activity and support better health outcomes. Report P73

Who and where

  • Local residents and the wider community Report P73
  • Existing leisure centre customers Report P28, P50
  • Non users of the leisure centre Report P29
  • People displaced by the centre's closure Report P51
  • Schools, clubs and other organisations Report P51
  • Fusion membership holders Report P51
  • Sports hall organisations, including Comunidad Cristiana de Londres Report P52
  • The Local Education Partnership, branded 4 Futures Report P42, P43, P45

Timeline

  • 7 July: Cabinet agreed the current leisure centre site as the preferred location and the broad arrangement of housing and leisure uses. Report P12, P13
  • September and October: The resident, customer and stakeholder consultation took place. Report P2
  • September 14th: A public exhibition displayed the two proposed leisure centre options. Report P19
  • November: Officers were due to report back with the consultation results and a full project mandate. Report P16
  • end of the financial year 2010 / 11: Further testing was to establish an appropriate project budget. Report P36
  • 2011: The capital bid was to be considered by Cabinet under the Capital refresh programme. Report P85
  • post planning: The fixed contract sum would be known after design, technical work and the final specification. Report P38
  • 29 October 2016: The existing Fusion lease expires. Report P81

Plain English for the jargon

  • Local Education Partnership (LEP): A public private partnership established to deliver the Building School's for the Future programme, since branded 4 Futures. [P42]
  • Gateway process: The first Gateway handles procurement appointment; the second handles recommendation of the construction contract. [P7] [P10]
  • 4 Futures: The Local Education Partnership's name, with design, construction, project management and facilities management expertise. [P42] [P43]
  • Option B: Option A plus a four court sports hall. [P20] [P21]
  • Enabling development: Residential development intended to generate capital for the leisure centre. The report says the social housing requirement is not viable in this case. [P61]
  • Capital bid: A request for capital programme funding, to be considered by Cabinet in 2011. [P3] [P85]
  • Fixed contract sum: A known contract price, available only after planning, detailed design, technical work and final specification. [P38]
  • Section 106 contributions: Possible contributions towards the leisure facility from the Elephant and Castle Opportunity Area. [P54]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

Decisions of the Cabinet 1. That the outcome of the consultation exercise summarised in paragraphs 23 to 30 and attached at Appendix 1 of the report that had been carried out throughout September and October be noted. 2. That the proposed provisional budget for the Elephant and Castle Leisure Centre as detailed in the closed report and the further work which will be undertaken to assess project costs prior to the submission of a bid for capital programme funding be noted. 3. That the project mandate for the redevelopment of the leisure centre site (attached in Appendix 2 of the report) and in particular the following key principles be agreed: · That the new leisure facility include the following core provision: a 6 lane 25m swimming pool, a learner pool, a 4 court sports hall, a gym, an exercise studio, a crèche and a cafe. 4. That officers report back the terms on which the adjoining residential plot will be sold at an appropriate time. 5. That officers report back, through the second gateway process, at the appropriate time once all design and technical has been completed to recommend the award of the construction contract. Decisions of the Leader of the Council 6. That approval of the planning application prior to submission be delegated to the cabinet member for regeneration and corporate strategy. 7. That the appointment of the Local Education Partnership (LEP) to construct and deliver the Elephant and Castle Leisure Centre, through the first gateway process, subject to existing protocols for LEP engagement and demonstrating value for money be delegated to the cabinet member for finance and resources.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 11 pages

Recommendations

Recommendations for the Cabinet

1 5. Cabinet note the outcome of the consultation exercise summarised in paragraphs 23 to 30 (and attached at Appendix 1) that has been carried out throughout September and October.

6. Cabinet note the proposed provisional budget for the Elephant and Castle Leisure Centre as detailed in the closed report and the further work which will be undertaken to assess project costs prior to the submission of a bid for capital programme funding.

7. Cabinet agree the Project Mandate for the redevelopment of the leisure centre site (attached in Appendix 2) and in particular the following key principles:

 That the new leisure facility include the following core provision: a 6 lane 25m swimming pool, a learner pool, a 4 court sports hall, a gym, an exercise studio, a crèche and a cafe.

8. Cabinet instructs officers to report back the terms on which the adjoining residential plot will be sold at an appropriate time.

9. Cabinet instructs officers to report back, through the second Gateway process, at the appropriate time once all design and technical has been completed to recommend the award of the construction contract.

Recommendations for the Leader of the Council

10. The Leader delegates to the Cabinet Member for Regeneration and Corporate Strategy approval of the planning application prior to submission.

11. The Leader delegates to the Cabinet Member for Finance and Resources the appointment of the Local Education Partnership (LEP) to construct and deliver the Elephant and Castle Leisure Centre, through the first Gateway process, subject to existing protocols for LEP engagement and demonstrating value for money.

BACKGROUND INFORMATION

12. At the meeting on the 7 July the Council’s Cabinet agreed a report concerning the provision of a new leisure facility at the Elephant and Castle and agreed the following:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Elephant and Castle: Provision of a New Leisure FacilityReport 11 pages DownloadRead as text
PDF
Elephant and Castle: Provision of a New Leisure Facility: Appendix 1Appendix 14 pages Download
PDF
Elephant and Castle: Provision of a New Leisure Facility: Appendix 2Appendix 5 pages Download

At this meeting

Whole meeting

Who was there

9 of 10 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-FyleCommittee Member, present
JF
Councillor John FriaryCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, apologies
AM
Councillor Abdul MohamedCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present

On this subject at Southwark

Search all
  1. Elephant and Castle – Provision of a new leisure facilityThis decision
  2. Elephant and Castle - Provision of a New Leisure FacilityApproved
  3. Elephant and Castle - Regeneration Agreement and Disposal of Associated LandAgreed
  4. Elephant and Castle Regeneration - Shopping CentreAgreed
  5. Disposal of Site 19 Elephant and CastleAgreed
  6. Elephant and Castle Supplementary Planning Document/Opportunity Area Planning FrameworkApproved

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open