Gateway 1 - Procurement strategy approval for IT Managed Services
ApprovedExecutive1 paper
AI summarySouthwark Cabinet approved managed IT procurement through Buying Solutions, planned for four to a maximum of seven years with an estimated maximum value of £42m. [D] [P31] Officers must immediately assess Serco information, and the finance cabinet member may amend the strategy if appropriate. [D]
Written from the decision and the officer reportPDF Pro
OutcomeApprovedApproved via Buying Solutions for up to seven years. [D]
Money£42mMaximum estimated value; £6m per annum indicated. [P31] [P110]
What happens nextAssess Serco informationOfficers will analyse it; authority may amend the strategy. [D]
Who it affectsIT users and contractor staffIT supports council users; TUPE affects contractor staff. [P33] [P51]
What was decided
The Cabinet approved the procurement strategy to use the Buying Solutions framework for an IT managed service under Contract Standing Order 3.3.2. The anticipated duration is four to a maximum of seven years.
The Cabinet noted additional information received from Serco and directed officers to begin analysing it immediately.
Authority was delegated to the cabinet member for finance, resources and community safety to assess the information and, if appropriate, agree an amendment to the procurement strategy.
Why
Officers did not prefer extending the existing contract because the Council's requirements for outsourced IT services had changed significantly since the contract was let in July 2007. Report P7, P8
A full tender would have been resource intensive and offered little inherent benefit beyond the proposed method. There was insufficient time to complete it before July 2012. Bringing services in house also lacked preparation time and the required technical infrastructure. Report P11
Buying Solutions was the only realistic route apart from extending Serco. The report cites competitive rates, EU compliance, and time and cost savings compared with a full tender. Report P12, P16, P23
What happens next
Officers are to undertake an immediate analysis of the additional information received from Serco.
The cabinet member for finance, resources and community safety is to assess that information and may agree a strategy amendment if appropriate.
A further competition will invite all framework contractors that have not deselected themselves to bid. Report P60
The money
£42m Total estimated maximum contract value. Report P31
£6m per annum Estimated annual cost before tenders are received and evaluated. Report P110
£1,000,000 Target of one apprentice per £1,000,000 annual contract expenditure. Report P80
Options considered
Chosen: Use the Buying Solutions IT managed services framework. It was the only realistic route apart from extending Serco, and offered competitive rates, EU compliance and an achievable timetable. Serco had not applied to join the framework. Report P12, P15, P16, P22
Rejected: Extend the existing Serco contract. The review did not prefer extension because requirements had changed. The risk plan retained notice to extend if the market failed to respond. Report P7, P8, P37
Rejected: Run a full comprehensive tender. A full OJEU procurement exercise was resource intensive. There was insufficient time to complete it before July 2012, with little inherent benefit beyond the proposed method. Report P11
Rejected: Bring services in house. Preparation time was insufficient, and extensive external support would be needed. The Council lacked the technical infrastructure for the arrangement in the short term, although it could remain an option after the proposed procurement. Report P11
Rejected: Use other established frameworks. No other mature or developed arrangement was in place. The frameworks considered had legal impediments or unacceptable conditions or scope. Report P11
Implications
Financial: The proposed contract will be funded from existing IT budgets. Savings will contribute to IT targets for 2012/13 and 2013/14. Report P94
Financial: Cost savings are a key evaluation criterion, with an expectation of a net reduction over the contract. The contract will be linked to a price index, may include a gain share mechanism, and will require benchmarking. Report P63, P95, P96
Legal: Because the contract value will significantly exceed the EU threshold, EU procurement regulations apply. The route must use the framework rules and OGC Model Call Off Contract, with legal officers drafting special terms for Council requirements. Report P18, P106, P114
Equalities: Bidders will be assessed against local requirements and the Council's standards for equalities and health and safety. Report P113
Climate: The new provider must set targets to minimise energy consumption and pollutant emissions. It must show that its procedures are effective in Council premises and other managed locations. Report P78
Risk: The timetable is challenging, depends on the correct resources being assigned, and permits very little slippage. Key risks cover technical expertise, project resources, market response, service degradation, TUPE and service information. Report P22, P35, P36, P37, P38, P39, P115
Staffing: External specialists will support procurement and transition from Serco, subject to normal approvals and appropriate budgets. TUPE applies on a secondary basis to existing contractor staff, with advice on consultation, pension and pay issues. Report P20, P51, P52, P53
Other: IDSD will manage the contract using KPIs, SLAs and monitoring for compliance, contractor performance, cost, customer relationships, user satisfaction and risk. The procurement will also assess apprenticeship engagement and local supply chain opportunities. Report P80, P82, P84, P85
Who and where
Southwark Council users of managed IT services Report P33, P75
Staff of existing contractors affected by TUPE Report P51
Serco as incumbent supplier, and the twelve Buying Solutions framework contractors as potential bidders Report P4, P24, P25, P60
Apprenticeship schemes Report P80
Local companies and small to medium enterprises in supplier supply chains Report P80
Black and minority ethnic, women and disabled owned businesses, and voluntary and community sector organisations Report P80
The Information & Data Services Division and Finance & Resources Department Report P82, P84
Service departments providing user input and procurement support Report P58, P71
Timeline
19/07/2011: Approval of the Gateway 1 procurement strategy report. Report P49
08/08/2011: Invitation to further competition. Report P49
19/09/2011: Closing date for responses. Report P49
31/10/2011: Completion of tender evaluation. Report P49
13/12/2011: Approval of the Gateway 2 contract award report. Report P49
06/01/2012: Contract award. Report P49
31/07/2012: Contract start. The listed completion date was 30/07/2016. Report P49
30/07/2019: Possible extensions of up to 3 years. Report P49
Plain English for the jargon
ITMS: IT Managed Services covering basic hardware, IT infrastructure management, the Helpdesk and related services. [P5] [P27]
Buying Solutions: A national procurement partner for public services within the Efficiency and Reform Group in the Cabinet Office. [P12] [P23]
Further competition: A competition among eligible framework suppliers to meet the Council's requirements and secure best value. [P60] [P106]
OJEU: The full EU procurement exercise considered for a comprehensive tender. [P11]
TUPE: Rules affecting staff of existing contractors where they transfer to a new contractor. [P51]
ITIL: Industry standard practices covering incident, release, change and problem management. [P29]
KPIs and SLAs: Key performance indicators and service levels used to manage delivery, contractor performance and compliance. [P67] [P82] [P85]
OGC Model Call Off Contract: The Buying Solutions contract model for ICT services, based on the OGC Model Contract for ICT Services. [P86]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17
Resolved
Decisions of the Cabinet 1. That the procurement strategy outlined in the report which utilises the buying solution framework, to procure an IT managed service (ITMS) in line with contract standing order 3.3.2, with an anticipated duration of four to a maximum of seven years be approved. 2. That it be noted that additional information has been received from the current contractor (Serco) and officers immediately undertake an analysis of this information. Decisions of the Leader of the Council 3. That decision 2 above be noted and authority be delegated to the cabinet member for finance, resources and community safety to assess the additional information and, if appropriate, to agree an amendment to the procurement strategy.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 15 pages
Recommendation
1. That the Cabinet approve of the procurement strategy outlined in this report which utilises the Buying Solution framework, to procure an IT Managed Service (ITMS) in line with Contract Standing Order 3.3.2 , with an anticipated duration of four to a maximum of seven years
BACKGROUND INFORMATION
2. IT is a fundamental business function in Southwark that exists at the centre of service delivery, enabling flexible working within the workforce and provides a solid foundation to generate future service improvements. The Council is currently in the process of formulating a new IT vision which any new contract will be configured to deliver
3. The existing contract for IT Managed Services (ITMS) is with Serco and was awarded in 2007. Serco, originally as ITNET, were the incumbent suppliers at the time in a contract dating back to 2001. The duration of the current contract is 5 years with a provision for LBS to extend for a further 2 years to July 2014. In order to extend the Council is required to notify Serco by January 2012.
1 4. The ITMS contract currently provides for the basic hardware and the management of the IT infrastructure (e.g. desktops; server management; Helpdesk; Disaster Recovery etc.
5. During the past eighteen months the Council has identified the key areas where improvements to service delivery and performance are required. The Council has worked closely with Serco in these areas and as a result there has been some improvements which included the generation of revised performance indicators (to make them more relevant and intelligible), and an improvement in governance and working arrangements. It is noteworthy that a number of key projects have been successfully implemented in that period which required some level of input from Serco. These included projects such as the completion of the Citrix rollout, transition of revenue and benefit services, and upgrade to the Council’s web site. Although those improvements were welcomed it is acknowledged that there is a need to continually improve performance, while addressing the overall ICT cost base. In view of this a range of options have been considered.
6. To determine a recommended procurement strategy a review was undertaken by officers taking into account current performance together, with the benefits and risks of extending the current contract. The outcome of these deliberations, for the reasons described in paragraph 8 below, was that an extension of the existing contract was not the preferred approach.
7. The Council’s requirements of an IT outsourcer have significantly changed since this contract was let in July 2007. Any new contract will specifically accommodate the significant changes that the organisation expects to go through in the coming years, together with the new vision that the Council is keen to implement
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.