Elephant and Castle Supplementary Planning Document / Opportunity Area Planning Framework
ApprovedExecutive6 papers
AI summarySouthwark Cabinet adopts Elephant and Castle Supplementary Planning Document and Opportunity Area Planning Framework, covering 122 hectares and targeting at least 4,000 new homes by 2026.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedReplaces 2004 SPG and two 2008 SPDs
MoneyNo immediate financial implicationsCosts within existing Planning Policy budgets
What happens nextSPD used to assess planning applicationsMaterial consideration in decisions
Who it affectsElephant and Castle opportunity area122 hectares in Southwark
What was decided
Cabinet adopted the Elephant and Castle Supplementary Planning Document and Opportunity Area Planning Framework (Appendix A) together with the table of proposed final amendments. Report P2
Cabinet noted the comments of the planning committee and the recommendations of the regeneration and leisure scrutiny sub-committee. Report P3
Cabinet noted the consultation report, table of representations and council response, updated equalities impact assessment, updated sustainability appraisal and sustainability adoption statement. Report P4
Why
Existing 2004 and 2008 planning documents are out of date and do not reflect the Core Strategy or London Plan, so guidance needs refreshing. Report P7, P8
The London Plan requires boroughs to work with the Mayor on opportunity area planning frameworks, and joint adoption gives certainty for developers, the public and councillors. Report P10, P11
The SPD sets objectives, overarching policies and character-area guidance for nine areas across the 122 hectare opportunity area, with targets of at least 4,000 new homes by 2026 and around 5,000 new jobs. Report P6, P46
What happens next
The adopted SPD/OAPF will be a material consideration in determining planning applications, replacing the 2004 SPG and 2008 SPDs. Report P9, P11
The council will keep school place need under review and work with NHS Southwark on health facilities over the 15 year plan period. Report P73
A draft preliminary community infrastructure levy will be consulted on over the summer, alongside updated community project banks. Report P80
Options considered
Chosen: Adopt the Elephant and Castle SPD/OAPF (Appendix A) with the table of proposed final amendments. Refreshes out-of-date planning guidance and gives certainty to developers, public and councillors Report P2, P7, P11
Chosen: Regeneration option: major new town centre destination (Sustainability Appraisal Option b). Appraisal judged it more positive for sustainability, jobs, community cohesion and public realm than the other options Report P91
Rejected: Regeneration option: business as usual, no SPD (Sustainability Appraisal Option a). Not considered the most sustainable approach Report P91
Rejected: Regeneration option: district centre meeting local needs (Sustainability Appraisal Option c). Appraisal judged it less sustainable than option b in the long term Report P91
Implications
Financial: No immediate financial implications; costs of adoption met from existing Planning Policy budgets and any further specific financial implications will come in later reports. Report P96, P97
Legal: SPDs are local development documents under the Planning and Compulsory Purchase Act 2004; once adopted they are a material consideration in planning decisions but are not subject to independent examination and are not part of the development plan. Report P100, P101, P102
Equalities: Equalities impact assessment considered impacts on age, disability, gender, race, religion and other protected groups, with mitigation through affordable business space for displaced businesses, flexible unit sizes and accessible public realm design. Report P83, P84, P85, P114, P119
Climate: Sustainability appraisal considered options for regeneration; SPD includes policies on energy, water, waste, green infrastructure, open space and public realm to mitigate climate change impacts. Report P63, P90, P91, P93
Risk: If transport mitigation is not put in place through the strategic transport s106 tariff, there is a risk regeneration of the area will stall. Report P77, P78
Other: The SPD addresses the 15 year plan period; consultees raised concerns that school place and health facility detail could not yet be fixed and will be kept under review. Report P73
Who and where
Residents of the Elephant and Castle opportunity area, including the Heygate Estate and Walworth Road communities Report P6, P15
Existing retail and market businesses in the Elephant and Castle shopping centre and surrounding area, including Latin American and minority ethnic businesses Report P33, P48, P84
The Bangladeshi community on the Rockingham Estate and local faith groups Report P15, P39, P85
Developers and landowners in the opportunity area, including the Lend Lease masterplan partners Report P11, P33
London South Bank University and the London College of Communications Report P54
Statutory consultees: GLA, Transport for London, English Heritage, Natural England, Environment Agency, Thames Water and the Coal Authority Report P18, P20, P22, P24, P27, P29
Timeline
2004: Council adopted the Elephant and Castle Development Framework supplementary planning guidance, now to be replaced Report P7
2008: Council adopted the Elephant and Castle Enterprise Quarter SPD and Walworth Road SPD, now to be replaced Report P7
15 November 2011 to 26 December 2011: Six week informal consultation on the draft SPD Report P14
22 November 2011: Draft SPD reported to cabinet for approval to consult Report P12
27 December 2011 to 7 February 2012: Six week formal consultation on the draft SPD Report P14
9 March 2012: Final report dated and sent to Constitutional Team Report P129
2011 to 2026: Plan period over which the SPD targets at least 4,000 new homes and around 5,000 new jobs Report P6, P52
Plain English for the jargon
SPD: Supplementary Planning Document, a local development document providing more detailed guidance on existing policies in the Core Strategy and London Plan
OAPF: Opportunity Area Planning Framework, produced jointly with the Mayor for areas identified in the London Plan
SPG: Supplementary Planning Guidance, the predecessor to SPDs, used for the 2004 Elephant and Castle Development Framework
EQIA: Equalities Impact Assessment, assessing potential impacts on groups with protected characteristics under the Equality Act 2010
s106: Section 106 planning obligations, legal agreements used to secure infrastructure or contributions from developers
CIL: Community Infrastructure Levy, a mandatory charge used to fund infrastructure
SA: Sustainability Appraisal, also covering Strategic Environmental Assessment requirements for the SPD
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13
Resolved
That the Elephant and Castle Supplementary Planning Document/Opportunity Area Planning Framework (Appendix A), together with the table of proposed final amendments to the SPD be adopted. 2. That the comments of the planning committee and the recommendations of the regeneration and leisure scrutiny sub-committee be noted. 3. That the consultation report (Appendix B), the table of representations received on the draft SPD and the council’s response (Appendix C), the updated equalities impact assessment (Appendix D), the updated sustainability appraisal (Appendix E) and the sustainability adoption statement (Appendix F) be noted.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 19 pages
Recommendations
That cabinet
1. Adopts the Elephant and Castle Supplementary Planning Document/Opportunity Area Planning Framework (Appendix A).
2. Notes the comments of the planning committee and the recommendations of the regeneration and leisure scrutiny sub-committee.
3. Notes the consultation report (Appendix B), the table of representations received on the draft SPD and the council’s response (Appendix C), the updated equalities impact assessment (Appendix D), the updated sustainability appraisal (Appendix E) and the sustainability adoption statement (Appendix F).
BACKGROUND INFORMATION
4. The Elephant and Castle opportunity area is identified in the London Plan (2011) and the council’s recently adopted core strategy (2011). It covers an area of 122 hectares. In addition to the shopping centre and Heygate Estate, the opportunity area also incorporates Walworth Road, London South Bank University campus, St George’s Circus, West Square and the Imperial War Museum and Newington Causeway. Both the London Plan and the core strategy recognise its potential for change and growth and set a target of providing at least 4,000 new homes by 2026 and around 5,000 new jobs.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.