Cabinet approved a £35.63 million parking and traffic enforcement contract over seven years, adopted the Elephant and Castle planning framework targeting at least 4,000 new homes by 2026, and backed enhanced refurbishments of the Four Squares and Abbeyfield estates, funded partly by selling up to 71 empty flats.
What the committee will consider, in order, with every paper attached to its item. Elephant and Castle Supplementary Planning Document / Opportunity Area Planning Framework is the main business; one item may be taken in private.
To receive any apologies for absence.
In special circumstances, an item of business may be added to an agenda within five clear working days of the meeting.
Members to declare any personal interests and dispensation in respect of any item of business to be considered at this meeting.
To receive any questions from members of the public which have been submitted in advance of the meeting in accordance with the cabinet procedure rules.
To approve as a correct record the minutes of the open section of the meeting held on 7 February 2012.
Decision: That the minutes of the meeting held on 7 February 2012 be approved as a correct record and signed by the chair. Decision page
To consider any deputation requests.
Decision: That the deputation requests as set out be heard. Elephant Amenity Network Group The deputation spokesperson addressed the meeting to speak on the Elephant and Castle Supplementary Planning Document on behalf of the Elephant Amenity Network, a community group of residents and traders. The spokesperson proposed amendments to the final version of the SPD which related to the town centre and small traders; improvements to the Walworth Road, pedestrian, cycle routes and the use of S106... Decision page
To consider the findings of the Four Squares options appraisal.
Decision: That the findings of the Four Squares options appraisal be noted. 2. That approval be given for work to continue to implement a scheme of enhanced refurbishment to all blocks described as option 3 within the report, to run concurrently with the security works already committed for Marden Square and Layard Square. 3. That officers be instructed to programme future resources from the sources identified in paragraphs 79-82 of the report. 4. That the substantial financial resources required for the... Decision page
To consider the findings of the Abbeyfield Estate options appraisal, considering Maydew House, Thaxted Court and Damory House.
Decision: That the findings of the Abbeyfield Estate options appraisal, considering Maydew House, Thaxted Court and Damory House be noted. 2. That approval be given for the adoption of enhanced refurbishment of all 3 blocks as the preferred option with the retention of the freehold of Maydew House and disposal of sufficient void properties in the block to bridge the funding gap between the warm, dry, safe works and enhanced refurbishment works on the estate and that these works are programmed into the... Decision page
To note and agree the responses to the recommendations of the housing and community safety scrutiny sub-committee’s investigation into the fire safety works at Canada Estate.
Decision: That the responses to the recommendations of the housing and community safety scrutiny sub-committee’s investigation into the fire safety works at Canada Estate be noted. 2. That officers report back to cabinet in October 2012 to review progress. Decision page
To agree the secondary and primary coordinated admissions schemes for 2013 admissions.
Decision: That the secondary and primary coordinated admissions schemes for 2013 admissions attached as Appendices 1 and 2 of the report respectively be agreed. Decision page
To agree the community primary schools, nursery schools and nursery classes admissions criteria for 2013.
Decision: That the community primary schools, nursery schools and nursery classes admissions criteria for 2013 attached as Appendix 1 of the report be agreed. Decision page
To approve the procurement strategy for the parking and traffic enforcement services contract.
Decision: That the procurement strategy outlined in the report for the parking and traffic enforcement services contract be approved. Decision page
To adopt the Elephant and Castle Supplementary planning document / opportunity area planning framework.
Decision: That the Elephant and Castle Supplementary Planning Document/Opportunity Area Planning Framework (Appendix A), together with the table of proposed final amendments to the SPD be adopted. 2. That the comments of the planning committee and the recommendations of the regeneration and leisure scrutiny sub-committee be noted. 3. That the consultation report (Appendix B), the table of representations received on the draft SPD and the council’s response (Appendix C), the updated equalities impact... Decision page
To authorise the head of property to dispose of the council’s freehold interest in 143 Barry Road, SE22 and 19 Oakhurst Grove, SE22 for a sum that in each case equates to the market value of the property.
Decision: That the head of property be authorised to dispose of the council’s freehold interest in 143 Barry Road, SE22 and 19 Oakhurst Grove, SE22 (the “Properties”), for a sum that in each case equates to the market value of the property. Decision page
To approve the acquisition of the freehold interest in a small residential care home complex at Bowley Close, London, SE19 1SZ from Southwark Primary Care Trust.
Decision: That the acquisition of the freehold interest in a small residential care home complex at Bowley Close, London, SE19 1SZ (see the plans at Appendix 1 of the report) from Southwark Primary Care Trust (PCT) be approved. 2. That the agreement of the detailed terms of the transaction be delegated to the head of property. Decision page
To approve the acquisition of the freehold in (block J) Queens Road, London SE15 2HP.
Decision: That the acquisition of the freehold in (block J) Queens Road, London SE15 2HP (identified edged red on the attached plan to the report) on the terms specified in the closed version of the report be approved. 2. That the reallocation of existing capital budget in the revised office accommodation strategy capital programme for the acquisition and fit out including all fees as detailed in the report be approved. 3. That it be noted that a capital out-turn refresh report will be presented to... Decision page
To consider motions referred from council assembly on 25 January 2012 on the following: Motion on themed debate – Environment Changes to NHS Southwark Save Chambers Wharf
Decision: Motion on Themed Debate: Environment That the motion referred from council assembly as a recommendation to cabinet, set out below be noted and agreed. 1. That council assembly believes that even in times of austerity protecting our natural environment is one of the most important issues for the borough and must remain a key priority for the council. 2. That council assembly believes this is recognised by all political parties and so calls on councillors to work together to suggest innovative... Decision page
That the press and public be excluded from the meeting for the following items of business on the grounds that they involve the likely disclosure of exempt information as defined in category 3 of paragraph 10.4 of the Access to Information Procedure Rules of the Southwark Constitution.
To approve as a correct record the closed minutes of the meeting held on 7 February 2012.
Item 13 is where most of this meeting's papers sit: 6 papers, about 42 MB.
To adopt the Elephant and Castle Supplementary planning document / opportunity area planning framework.
This is the first time this subject appears in the meetings we have read.
Get the decision the day it is recorded, and anything that comes back to the committee on this subject.
All 48 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
Every Cabinet (decommissioned, for the Executive after meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
Southwark, Cabinet (decommissioned, for the Executive after
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the Cabinet (decommissioned, for the Executive after, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.