Home Care Contract Monitoring Report

Noted Executive 2 papers

AI summaryCabinet noted that Southwark's home care contracts met all quality and performance standards in their first six months, while recording transition challenges and savings of £633k and £663k. [D] [P1] [P3] [P82] [P92]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedQuality and performance standards were met over six months [P1] [P8]
MoneySavings: £633k and £663kThe report gives savings as £633k and £663k [P82] [P92]
What happens nextCentralised ordering teamDue from April 2012 to maximise main contract use [P44]
Who it affectsHome care service usersOver 1,000 adults received home care in Southwark [P4]

What was decided

Cabinet noted that contract delivery met all quality and performance standards over the first six months of operation. [D] [P1] Report P1

Cabinet noted the transition approach and the dedicated transition team's support for service users. [D] [P2] Service users could remain with their current providers on personal budgets, and far more than anticipated took them up. [D] [P2] Report P2

Cabinet noted that transfer challenges affected the quality and consistency of service delivery. [D] [P3] Good practice had also supported care with dignity and sensitivity for the borough's most vulnerable residents. [D] [P3] Report P3

Why

More users than expected chose to remain with their existing providers on personal budgets. [P25] This meant fewer care staff transferred under TUPE than anticipated, making the increase in care hours harder. [P7] [P27] [P30] Report P7, P25, P27, P30

Transfer pressures led to more service delivery alerts, mainly about care worker attendance, from August 2011 to October 2011. [P61] Report P61

CQC inspections identified concerns and led to agreed action plans. [P78] [P79] Alerts fell in November and December, and all quality and performance indicators were met over the period covered. [P79] [P80] Report P78, P79, P80

What happens next

Launch a centralised team from April 2012 to maximise use of the main contracts. [P44] The team was to gatekeep the setting up of home care packages. [P44] Report P44

Review separately bought care packages, transfer eligible packages to the two main providers and prioritise council managed referrals. [P42] [P43] This was intended to help meet minimum hours guarantees. [P43] Report P42, P43

Complete a full business case for electronic home care monitoring. [P45] Decide whether pursuing it would be cost effective. [P45] Report P45

The money

  • £633k Efficiency savings from the new home care arrangements. Report P82
  • £663k Savings through reduced hourly care rates, with personal budget transfers also contributing. Report P92
  • around £12 per hour to £19 per hour Hourly rates set by the tender to address variable costs and align costs with quality. Report P15

Options considered

  • Chosen: Remain with the existing provider under a MAP personal budget. Over 400 users chose this, far more than anticipated. Report P20, P25
  • Chosen: Take a direct payment and arrange your own care and support. This was one of the choices offered to service users, their families and carers. Report P20, P21, P22
  • Chosen: Transfer to a new provider on a council managed personal budget. Used where users did not choose a direct payment or MAP personal budget. Report P21, P22, P23

Implications

  • Financial: The report gives savings of £633k and £663k in different places. Report P82, P92
  • Financial: Year 1 minimum hours were not achieved. Financial penalties were avoided, and minimum hours were expected in Year 2. Report P93
  • Financial: The report states that there are no specific resource implications from the report. It separately records budget provision for higher Year 2 hourly rates in 2012/13. Report P86, P94
  • Staffing: Far fewer staff transferred under TUPE than expected, placing pressure on the new contractors to scale up. Report P27, P30
  • Risk: Service delivery alerts rose during transfers, especially from August to October 2011, before falling in November and December. Report P61, P79
  • Legal: Contract monitoring supported the Council's legal duty to secure continuous improvement in economy, efficiency and effectiveness. [P90] TUPE rules allowed staff to remain with their existing employer when continuing work was offered. [P30] Report P30, P90
  • Equalities: Services are provided according to need and cover all six strands of the Council's equality agenda. Report P84
  • Risk: The Council had not decided whether electronic home care monitoring was cost effective because a full business case was still needed. Report P45

Who and where

  • Home care service users in Southwark Report P4
  • People using the specialist continuing drinkers and acquired brain injury service Report P12
  • Families and carers consulted about transfer preferences Report P21
  • Users of the two main contracts, around 60% of all users Report P41
  • MAP personal budget users, around 40% of all users Report P41
  • Enara and London Care Report P8
  • Existing providers using MAP arrangements Report P25
  • Care staff eligible to transfer under TUPE Report P28

Timeline

  • January 2011: Home care tendering concluded and contracts were awarded [P5] [P12] Report P5, P12
  • 16th May 2011: Contracts had a start date, with an initial three year period [P12] Report P12
  • June 2011: Transition began, and the six month operating review covered June to December 2011 [P8] [P19] Report P8, P19
  • end of August 2011: Transition from the previous arrangements concluded [P16] Report P16
  • August 2011 to October 2011: Service delivery concerns were at their most noticeable [P61] Report P61
  • December 2011: The six month review ended, and Enara's CQC inspection noted minor safeguarding concerns [P8] [P77] Report P8, P77
  • April 2012: A new centralised ordering team was planned for launch [P44] Report P44
  • 3 May 2012: The final officer report was dated [P99] Report P99

Plain English for the jargon

  • Personal budget: A budget used to arrange and control adult social care support [P10] [P20]
  • Direct payment: A payment that lets a service user arrange their own care and support [P20]
  • MAP: Managed Account Provider arrangement, where the Council manages a personal budget and the user remains with the existing provider [P20]
  • TUPE: Rules under which staff can be consulted about transfer and may remain with their current organisation [P28] [P30]
  • Service Delivery Alert: A logged day to day care concern, ranging from preferences and communication to missed visits and dignity [P54] [P55] [P56] [P57]
  • Safeguarding alert: A concern covering physical or mental abuse, financial abuse or neglect [P50]
  • CQC: The Care Quality Commission, which inspects registered services against outcome domains [P72] [P75]
  • Minimum guaranteed hours: The minimum care hours guaranteed for universal home care, falling each contract year [P13] [P43]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

That it be noted that the delivery of the contracts has met all the quality and performance standards under the contract over the first six months of operation 2. That the summary of how the transition from previous to new contracting arrangements was approached be noted; that through the support of the dedicated transition team service users were given the choice to remain with their current providers on a personal budget and that far greater numbers than anticipated chose to take up a personal budget. 3. That it be noted that while there were challenges that arose during the transfer process that had some impact on the quality and consistency of service delivery, there have also been examples of good practice over the past six months that has ensured the most vulnerable residents in the borough received care with real dignity and sensitivity.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 12 pages

Recommendations

1. That Cabinet Members note the delivery of the contracts has met all the quality and performance standards under the contract over the first six months of operation.

2. That Cabinet Members note the summary of how the transition from previous to new contracting arrangements was approached; that through the support of the dedicated transition team service users were given the choice to remain with their current providers on a personal budget and that far greater numbers than anticipated chose to take up a personal budget.

3. That Cabinet Members note that while there were challenges that arose during the transfer process that had some impact on the quality and consistency of service delivery, there have also been examples of good practice over the past six months that has ensured the most vulnerable residents in the borough received care with real dignity and sensitivity.

Executive summary

4. Ensuring the delivery of good quality and cost effective Home Care services is an important part of adult social care provision in Southwark. With over 1,000 adults receiving some form of home care service in Southwark these services can support the delivery of the Adult Social Care Vision, allowing residents of Southwark to remain as independent as possible, in their own homes for as long as possible.

5. The re-tendering of Home Care services in Southwark, which concluded in January 2011, introduced new contracting arrangements that created two, borough wide, cost and volume contracts for universal home care and one contract for specialist home care. The new arrangements commenced incrementally from June 2011 to allow as smooth a transition as possible from the existing arrangements, which involved 18 different cost and volume contracts with 18 different providers, to the new contracting arrangements.

6. In line with councils commitment to support greater choice and control and increase the use of personal budgets, users were given the choice to remain with their existing provider by taking up a personal budget and over 400 users out of just over 1000 users chose to remain with their existing provider.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Home care contracts dataAppendix 1 8 pages Download
PDF
Report: Home Care Contract Monitoring ReportReport 12 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 10 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
DD
Councillor Dora Dixon-FyleCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, present
AM
Councillor Abdul MohamedCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present
DC
Deborah CollinsOfficer, expected
EK
Eleanor KellyOfficer, expected

On this subject at Southwark

Search all
  1. Home Care Contract Monitoring ReportThis decision
  2. Gateway 2 - Contract Award Approval - Home Care Services in SouthwarkApproved
  3. Overview and Scrutiny Committee Call-in: Gateway 2 - Contract Award Approval - Home Care Services In SouthwarkAgreed
  4. Report into the collapse of Southern Cross Care Homes (Report of the 2011/12 Southwark Health and Adult Social Care Scrutiny Sub-Committee)Noted
  5. Response to the Scrutiny Report into the Collapse of Southern Cross Care HomesNoted
  6. Home Care Annual Contract Performance ReportNoted

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open