Gateway 2: Contract Award Approval - Southwark Heat Network from South East London Combined Heat and Power Plan (SELCHP) - Additional Services Contract

Approved Executive 2 papers

AI summarySouthwark Cabinet approved in principle the Veolia Environmental Services Southwark Ltd heat network contract, with no additional or capital cost to the council [D]. The heat purchase replaces gas and boiler maintenance spending, with supply due in late 2013 [D].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedApproval in principle, with final contract agreement delegated [D] [P6] [P7]
MoneyNo additional or capital cost [D]A long term heat purchase replaces gas and boiler maintenance [D]
What happens nextFinalise terms and agree contract [D]Price, indexation and Leasehold Valuation Tribunal permission remain outstanding [P27] [P48] [P111]
Who it affectsAlmost three thousand council properties [P18]Seven Southwark estates are included [P18]

What was decided

Cabinet approved in principle the award of the Southwark Heat Network Contract to Veolia Environmental Services Southwark Ltd (VESS), using the agreed heads of terms. Report P2

The approval set the contract start for September 2012 and expiry in 2033, with heat supply due in late 2013. Report P3, P4

Authority was delegated to the cabinet member for transport, environment and recycling to finalise outstanding terms and agree the contract, with advice from the Finance Director and Strategic Director for Environment and Leisure. Report P6, P7

Why

The heat purchase would replace the cost of buying gas and maintaining boilers. The decision states that there is no additional cost to the council. Report P2

The network was designed to reduce carbon dioxide emissions and local pollution. It was expected to reduce carbon emissions from the council housing stock by 3.9%. Report P15, P54

Heat was intended to cost less than gas boiler heating, and a cap was agreed on contractor profitability. VESS was the sole potential supplier, so the council developed its own pricing model and used external advisers. Report P24, P36, P74

What happens next

The delegated cabinet member must finalise outstanding heads of terms and agree the contract, with advice from the Finance Director and Strategic Director for Environment and Leisure. Report P6, P7

The council must obtain Leasehold Valuation Tribunal permission to avoid section 20 consultation before signing. Officers estimate this may take three months, and later dates could move back if it takes longer. Report P27, P48

Officers must settle the final price and indexation, resolve the accounting treatment of the assets and complete final contract drafting before final agreement. Report P49, P104, P111

The money

  • £0.5m Budgeted cost of advice for the full procurement. Report P86
  • £500k Required green fund payment if the heat network is not delivered. Report P73
  • £100 per annum Threshold above which section 20 consultation is required for a leaseholder. Report P122

Options considered

  • Chosen: Use an additional services contract with VESS. Regulation 14 permits additional services to the waste contract without advertising, and external legal advice supports the negotiated procedure. Report P47, P100, P109, P110
  • Rejected: Run a competitive procurement process with advertising. The service was linked to the waste contract, so the council was unable to run a competitive procurement process. Report P48, P75
  • Chosen: Seek tribunal permission to avoid section 20 consultation. Statutory consultation was not possible for the proposed agreement, so the council is applying to the Leasehold Valuation Tribunal and undertaking alternative consultation. Report P48, P122
  • Rejected: Require council capital investment. The council requires no capital investment, and VESS will fund the network then recover it through the heat charge. Report P15, P83, P111
  • Rejected: Continue using gas boilers for connected homes. The heat price was intended to be lower than gas boiler heating, and the project also targeted lower emissions and pollution. Report P45, P57, P111

Implications

  • Financial: VESS would fund all network capital costs. The council would reimburse VESS through the heat charge, which also covers scheme lifecycle and repairs. Report P83
  • Financial: The contract value and estimated annual cost are in the closed report. The final charge carries demand risk, partly mitigated by substitute heat and advance notice of stock changes. Report P2, P22, P84
  • Financial: Savings are anticipated. Direct leaseholders' savings are passed to individual units at year end, and those directly supplied are likely to see lower charges over time. Tenants' savings are pooled and redistributed borough wide, while other borough leaseholders will not see these benefits. Report P85, P90
  • Legal: The additional services route did not require advertising. The council must obtain tribunal permission before signing, while final price, indexation, accounting treatment and drafting remain to be settled. Report P47, P48, P49, P104, P110, P111
  • Climate: The network would use renewable heat from waste and reduce carbon emissions from the council housing stock by 3.9%. The report identified approximately 10,000 tonnes of carbon dioxide emissions per annum as a possible saving. Report P53, P54, P73
  • Risk: Sole supplier value for money risk was managed through transparent pricing, the council's model, external advisers and a profitability cap. Gas boilers would provide backup if the network failed. Report P24, P35, P36, P74
  • Equalities: The project aimed to reduce fuel poverty, improve energy security and provide warmer homes, including in an area experiencing deprivation. Report P51, P59
  • Staffing: Housing Engineering would take over contract management after commissioning, using regular meetings and measures of performance. No staff or activity transfer was expected. Report P66, P68, P69, P80

Who and where

  • Almost three thousand Southwark Council properties Report P18
  • Council housing estates at Rouel Road, Keetons, Four Squares, Pedworth, Abbeyfield, Silverlock and Tissington Report P18
  • Leaseholders in areas directly supplied by SELCHP Report P90
  • Tenants connected to the scheme Report P85
  • Residents of estates not scheduled for connection Report P93
  • Southwark Council as heat purchaser Report P2, P18
  • Veolia Environmental Services Southwark Ltd as contractor Report P2
  • Housing Engineering team as future contract manager Report P66, P68

Timeline

  • February 2008: The council signed the waste facility and integrated waste management contract with VESS. Report P9
  • 25 January 2011: Cabinet approved authority to open heat network contract negotiations. Report P11, P26
  • May 2012: Contract award approval was planned, with agreement to key principles and the tribunal application delegated. Report P26
  • 08 May 2012: A public meeting for leaseholders and tenants was scheduled to discuss the project. Report P96
  • Aug 2012: Tribunal dispensation and the contract award approval were planned. Report P26
  • September 2012: The contract was due to commence. Report P3
  • late 2013: Heat supply was due to commence, with the service operational planned for Autumn 2013. Report P4, P26
  • 2033: The contract was due to expire at the same time as the waste contract. Report P33

Plain English for the jargon

  • VESS: Veolia Environmental Services Southwark Ltd [P9].
  • SELCHP: South East London Combined Heat and Power plant [P10].
  • CHP: Combined heat and power, an efficient way of generating and using energy [P30] [P43].
  • District heating network: A pair of highly insulated underground pipes that carry hot water to estates and return cooler water [P13].
  • Heads of Terms: A framework for contract negotiations that creates no legally binding obligations [P30].
  • LVT: Leasehold Valuation Tribunal [P15].
  • Section 20: The statutory consultation requirement under the Landlord and Tenant Act 1985 [P122].
  • IRR: The project's level of profitability for VESS [P36].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

Decisions of the Cabinet 1. That approval be given in principal to the award of the Southwark Heat Network Contract to Veolia Environmental Services Southwark Ltd (VESS) on the basis of the heads of terms set out in paragraph 11 of the report and paragraph 9 of the closed report. There is no additional cost to the Council but the contract is for the long-term purchase of heat from VESS (replacing the cost of purchase of gas and boiler maintenance). There is no capital cost to the Council. The financial value of the contract is contained in the closed version of the report. 2. That the contract commence in September 2012 and expire in 2033. 3. That the supply of heat commence in late 2013. Decision of the Leader of the Council 4. That authority be delegated to the cabinet member for transport, environment and recycling to finalise the outstanding points on the heads of terms, on the advice of the finance director and the strategic director for environment and leisure. 5. That authority be delegated to the cabinet member for transport, environment and recycling to agree the contract, on the advice of the finance director and the strategic director for environment and leisure.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 16 pages

Recommendations

Recommendations for the Cabinet

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Map of proposed routeAppendix 1 1 pages Download
PDF
Report: Gateway 2 Contract Award Approval: Southwark Heat Network from South East London Combined Heat and Power Plan (SELCHP): Additional Services ContractReport 16 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 10 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
DD
Councillor Dora Dixon-FyleCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, present
AM
Councillor Abdul MohamedCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present
DC
Deborah CollinsOfficer, expected
EK
Eleanor KellyOfficer, expected

On this subject at Southwark

Search all
  1. Gateway 2: Contract Award Approval - Southwark Heat Network from South East London Combined Heat and Power Plan (SELCHP) - Additional Services ContractThis decision
  2. Gateway 1 - Highway works contractApproved
  3. Gateway 3 - Variation Decision - Parking and Traffic enforcement and associated services contractApproved
  4. Gateway 1 - Procurement Strategy Approval - Framework contracts to provide bailiff services to the Revenues & Benefits and Parking ServicesApproved
  5. Gateway 2: Contract Award Approval - Corporate Insurance Procurement (excluding Property Insurance)Approved
  6. Gateway 1 - Initial Procurement Strategy, Parking and Traffic Enforcement Services ContractAgreed

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies