AI summarySouthwark Cabinet approved the procurement strategy for communal lighting and lightning protection [D]. The estimated cost is £2,542,293, with an estimated contract value of £4,237,155 if two performance based extensions are used [D].
Written from the decision and the officer reportPDF Pro
OutcomeApprovedCompetitive tender for a 3 year contract [D][P21]
MoneyInitial cost £2,542,293 [D]Potential value £4,237,155 [D]
What happens nextIssue notice of intention [P45]Planned for 28 May 2012 [P45]
Who it affectsAll borough communities [P61]Housing estate communal areas and buildings [P3][P15]
What was decided
Cabinet approved the procurement strategy for a 3 year contract from 1 October 2013 to 30 September 2016, with two 12 month extensions possible to 30 September 2018, subject to performance.
The estimated cost is £2,542,293 for the initial term. The estimated value is £4,237,155 with extensions.
The strategy provides for one contractor, an EU Restricted Procedure with at least five contractors invited to tender, and a price and quality evaluation at 70:30. Report P1, P11, P21, P22, P58
Why
The service is a statutory duty as landlord and employer. It supports safer access, health, safety and quality of life in all wards. Report P14, P15, P25, P41
Competitive tendering was expected to attract interest, secure competitive costs and best value, and support stable service delivery. Report P5, P16, P19, P31
Combining the services gives one point of responsibility. The report identifies potential technical, operational and cost benefits, while the current lightning service has no annual maintenance planning. Report P6, P7
What happens next
Complete TUPE due diligence for Spokemead Maintenance Ltd and Central High Rise Ltd before tendering starts and before definitive advice can be given. Include the results in the tender pack. Report P49
Engineering and Compliance will prepare the specification and contract documentation with the council's legal department, using JCT Measured Term Contract 2011 subject to legal amendment. The team will manage the contract and monitor value and quality. Report P51, P52, P74
Carry out the required Schedule 2 consultation. Issue the Notice of Intention before tenders are sought and the Notice of Proposal before contract placement. Advertise through OJEU and on the council website. Report P45, P54, P55, P100
The money
£2,542,293 Estimated cost for the 3 year term Report P1
£4,237,155 Estimated contract value with two 12 month extensions, subject to performance Report P1
£1,694,862 Total cost for the additional 2 year term Report P10
£731,540 Current estimated annual cost of communal lighting Report P4
£115,891 Annual lightning protection cost based on 2011/12 actual spend Report P8
£2,194,620 Planned communal lighting budget for the three years Report P80
£1,463,080 Planned communal lighting budget for the following two years Report P80
£165,000 Projected annual lightning protection allowance for the next 3 years Report P81
Options considered
Rejected: Do nothing. Provision is a statutory obligation, so the council cannot stop the service. Report P25
Rejected: Use an existing framework agreement. The council has no existing framework for this work and no external arrangement meets its requirements. Report P26
Rejected: Shared Services. No neighbouring local authority was seeking a shared arrangement, and existing contracts were generally ring fenced. Report P27
Rejected: Provide the services through PRAM. It was not taken further because of Leaseholder Valuation Tribunal implications and no current market cost or rates evidence to show best value. PRAM has confirmed that it will tender for the service. Report P28, P29
Chosen: Go out to tender. It was expected to attract considerable interest and achieve best value. The council must use an EU compliant process. Report P30, P31
Implications
Financial: Costs and officer time can be contained within existing budgeted revenue resources. Costs must be attributed to the relevant block and estate cost centres. Lightning protection has no separate budget provision, and future metal theft costs may need another budget or reduce the £165,000 allowance. Report P8, P81, P95, P101
Legal: All reasonable steps must be taken to obtain at least 5 tenders through a publicly advertised competitive process. The service is Part A under the Public Contracts Regulations 2006 and must follow those Regulations and contract standing orders. Report P90, P91, P92
Legal: A new contractor appointment will be a Service Provision Change, so TUPE may apply. Due diligence on both current providers is needed before tendering starts and definitive advice can be given. The contract will also be treated as a qualifying long term agreement, requiring Schedule 2 consultation and the specified notices. Report P49, P100
Equalities: The service affects all communities and groups in the borough. Contractors must demonstrate an Equal Opportunity Policy and comply with the council's own policy. Report P61, P70
Climate: The contract must follow the council's Sustainability Policy, use sustainable materials where possible, require recommendations for new low energy technologies, and encourage low emission vehicles. Report P63, P64, P66, P72
Risk: Procurement delays will be reviewed and escalated. Contractors must provide performance bonds or parent guarantees. If the main contractor fails or performs inadequately, the council can instruct an approved alternative after a Default Notice, with service costs borne by the main contractor. Report P11, P34, P35, P36
Staffing: Retendering will have no impact on council staff. Consultants have been appointed to support specific parts of the procurement where required. Report P77
Other: Proper communal lighting supports safer access and helps deter crime and vandalism. The service is intended to limit defective lighting and lightning protection equipment. Report P15, P41, P61
Who and where
All communities and groups in the borough Report P61
Council residents in all wards Report P14
Tenants Report P61
People using communal areas on council estates Report P3, P15
Spokemead Maintenance Ltd and Central High Rise Ltd Report P4, P7, P49
EU and local electrical contractors Report P68
PRAM Report P29
Timeline
15 May 2012: Gateway 1 procurement strategy approval Report P44
25 May 2012: Scrutiny call in period and notification of Gateway 1 implementation Report P44
28 May 2012: Issue Notice of Intention Report P45
23 Jul 2012: Advertise the contract Report P46
11 Sept 2012: Closing date for expressions of interest Report P46
22 Nov 2012: Closing date for return of tenders Report P47
13 May 2013: Contract award Report P47
1 Oct 2013 to 30 Sept 2018: Contract start and maximum completion date Report P47
Plain English for the jargon
EU Restricted Procedure: Interested contractors express interest and complete a PQQ [P21]. At least five shortlisted contractors are invited to tender [P22].
OJEU: Official Journal of the European Union, where the contract notice will be published [P54].
PQQ: Pre Qualification Questionnaire used to select contractors for tendering [P21][P57].
MEAT: Most Economical Advantageous Tender, assessed using a price and quality ratio of 70:30 [P58].
TUPE: A possible requirement following the Service Provision Change [P49]. Due diligence is needed before definitive advice can be given [P49].
PRAM: The council's own contractor [P28]. It has confirmed that it will tender for the service [P29].
JCT Measured Term Contract 2011: The proposed contract form, subject to amendment by the council's legal department [P52].
BS EN 62305 2006: The lightning protection standard used to set appropriate protection levels on buildings [P15].
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
That the procurement strategy outlined in the report for the communal lighting and lightning protection contract at an estimated cost of £2,542,293 for a period of 3 years from 1 October 2013 to 30 September 2016 with the potential for two 12 month extensions to 30 September 2018, subject to performance, making an estimated contract value of £4,237,155 be approved.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 12 pages
Recommendation
1. That the Cabinet approves the procurement strategy outlined in this report for the Communal Lighting and Lightning Protection Contract at an estimated cost of £2,542,293 for a period of 3 years from 1 October 2013 to 30 September 2016 with the potential for two 12 month extensions to 30 September 2018, subject to performance, making an estimated contract value of £4,237,155.
BACKGROUND INFORMATION
2. The Communal Lighting Contract is a borough wide service to provide external communal lighting on council estates. The lighting includes all essential lighting in all communal areas on estates including (but not limited to) lamp posts, bulk head lighting, emergency lighting, security lighting, electrical power supply systems and wiring associated with these appliances.
1 3. The service is currently being provided to the council by Spokemead Maintenance Ltd (Spokemead) at an estimated annual cost of £731,540. This contract will expire on 30th September 2013.
4. The intention is to competitively tender the communal lighting service, as set out in this report for a period of 3 years (with the potential for two 12 month extensions) to ensure competitive costing of the contract, and long term stability of the service delivery.
5. In considering the tender process to be followed, the Engineering & Compliance team consider it prudent to package the council’s lightning protection service with the communal lighting service, providing a single point of responsibility for both. This strategy is consistent with the recommendations set out in the Engineering Contracts Strategy which identified that such an arrangement would benefit from technical and operational synergies. It is envisaged that there will also be potential cost benefits by combining the engineering disciplines.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.