CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Southwark
Cabinet (decommissioned, for the Executive after, Thursday 28 May 2026 at 4.00pm

Gateway 1 Long-term Repairs and Maintenance Contract

Approved Executive 1 paper

AI summaryCabinet approved the procurement strategy for repairs and maintenance in Camberwell, Peckham, Peckham Rye, Nunhead and Dulwich. The contract is due to start 3 October 2013 for five years, with an extension of up to five years subject to performance and an estimated value of £110,000,000. [D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFive years plus an optional extension up to five years [P2]
Money£110,000,000 [D]Estimated contract value; annual value up to £11m [P2]
What happens nextTender and award [P3] [P78]Award report will decide whether services move in house [P3]
Who it affectsHousing residents and leaseholders [P58] [P98]Repairs across five south borough areas [P2]

What was decided

Cabinet approved the procurement strategy for a repairs and maintenance contract covering Camberwell, Peckham, Peckham Rye, Nunhead and Dulwich. It is due to start on 3 October 2013 for five years, with an extension option of three plus two years, subject to performance, at up to £11m a year and an estimated value of £110,000,000. Report P2

All repairs and maintenance services are included in the procurement. Cabinet noted that out of hours service and works to empty properties might be provided in house, with that decision left to the contract award report. Report P3

The approved route uses an EU Restricted Procedure, with at least six contractors chosen through a PQQ. Tenders must show the full service cost and separately price out of hours and voids, and evaluation will use 70% quality and 30% price. Report P30, P34, P35, P95, P96

Why

The service is essential to council residents, and the council must keep it running to meet landlord and legal duties. Report P16, P17

Five years plus an extension of up to five years balances price competitiveness with time to improve and embed delivery. It also allows the council to review delivery after five years. Report P18

The previous contract showed that 50/50 savings were hard to achieve and measure, changing KPIs prevented profit adjustments, and subcontracting of up to 70% caused quality management difficulties. These lessons will shape the new tender. Report P10, P11, P12, P13, P88

What happens next

Develop the specification, preliminaries, pricing documents, evaluation method and weightings with legal and internal support, taking account of the contract lessons. The Project Board must approve all documents before issue. Report P88, P90

Run the restricted procurement, select at least six contractors through the PQQ, and publish the official notice in OJEU and on the council website. Report P34, P35, P92, P93

At the Gateway 2 contract award stage, compare the full service tender and the separately priced out of hours and voids against in house provision before recommending what to award. If the contractor changes, the incoming contractor must carry out TUPE consultation and negotiations with the workforce. Report P30, P31, P32, P86

The money

  • £110,000,000 Estimated value of the repairs and maintenance contract. Report P2
  • £11m Annual contract value of up to this amount and the base budget used for cost sensitivity. Report P2, P114
  • £150k Estimated cost of external legal advisers and additional project management, to be met from HRA reserves. Report P113, P114
  • £550k annually Potential annual cost increase or decrease if costs change by 5% on the base budget of £11m. Report P114
  • £687k Savings anticipated for 2013/14 from reductions to the outgoing contract amount, which the new tender could affect. Report P115
  • £100 per annum Limit on the minor repair service charge for leaseholders when a framework was used for longer than 12 months. Report P29
  • £15 million Threshold above which the procurement is strategic and approval is reserved to Cabinet. Report P119
  • £250 Leaseholder cost threshold above which qualifying repairs would need separate tendering and full consultation if the service moved in house. Report P138

Options considered

  • Rejected: Do nothing. The contract with Morrison Facilities Services Limited ends on 2 October 2012 and the interim contract ends on 2 October 2013. The council needs another way to deliver repairs and meet its legal duties. Report P24
  • Rejected: Shared Services. No neighbouring authority is currently seeking a shared service for this work, and their arrangements are generally ring fenced. Report P25, P26
  • Rejected: Full in house provision through Southwark Building Services. Southwark Building Services had been reorganised and downsized by circa 27%. Its highest cost was 20% above the outgoing contractor, and further expansion was not yet ready. Report P27, P30
  • Chosen: Further incremental in house delivery. Out of hours service and/or voids may suit Southwark Building Services, subject to effective mobilisation, value for money and capacity. Report P28, P31, P32
  • Rejected: Use an existing framework agreement. The only live framework expires in July 2014 and is unsuitable for long term delivery. It also creates potential difficulty recovering costs from leaseholders. Report P29
  • Chosen: Go out to tender. The contract value is above the OJEU threshold. Two tender options will allow comparison with in house provision. Report P30, P34
  • Chosen: Hybrid external and in house delivery. The remaining services would be delivered by an external contractor while possible internalisation of out of hours service and/or voids is explored. The award report will decide which services, if any, are internalised. Report P31, P32

Implications

  • Financial: The contract has an estimated value of £110,000,000 and an annual value of up to £11m. A 5% cost change on the £11m base budget could mean an increase or decrease in cost of £550k annually. Report P2, P114
  • Financial: External legal advisers and additional project management are estimated at £150k and will be met from HRA reserves. The £687k savings planned for 2013/14 could be affected. There is also a low risk that higher tender rates could reduce service charge collection, with a possible reduction to the lowest tender rate and an impact on HRA if challenged. Report P113, P114, P115, P139
  • Legal: TUPE 2006 rules would apply if the long term contractor differs from the interim contractor. Circa 80 directly employed staff and a small number of subcontractor staff may transfer, and the incoming contractor must conduct consultation and negotiations. Report P86
  • Legal: The contract is a strategic procurement above £15 million, so Cabinet approval is required and the full EU tendering rules apply. Section 20 landlord and tenant consultation is also required. Observations closed on 5 July, and 80 observations were received. Report P119, P120, P133
  • Risk: Evaluation will put 70% weight on quality and 30% on price. This may cost more than the council's standard method, but the competitive market is expected to deliver value for money. Report P95, P96
  • Staffing: Southwark Building Services had been reorganised and downsized by circa 27%. Its highest cost was 20% above the outgoing contractor, and it needed more time to expand. Incremental in house work depends on mobilisation, value for money and capacity. Report P27, P28
  • Equalities: Contractors must demonstrate an Equal Opportunity Policy and compliance with the council's policy. They must also show how they will support local employment and provide a comprehensive apprenticeship programme, while the successful contractor is expected to meet London Living Wage requirements. Report P104, P105
  • Climate: The contract must follow the council's Sustainability Policy. Materials should come from sustainable sources where possible, with goals for reuse and recycling, and avoiding environmentally damaging or harmful materials. Report P100, P101, P102

Who and where

  • Council housing tenants in Camberwell, Peckham, Peckham Rye, Nunhead and Dulwich Report P2, P16, P98
  • Leaseholders paying charges for communal repairs Report P58, P69
  • Borough residents using the universal repairs service Report P98
  • Southwark Building Services and its workforce Report P27, P28
  • Interim contractor employees, including circa 80 directly employed staff Report P86
  • Contractors seeking to be shortlisted for the tender Report P30, P35
  • Council repairs, legal, procurement and commercial teams Report P88, P107, P111
  • Residents, resident groups, the Homeowners and Tenants Councils and council members Report P109

Timeline

  • 2 April 2012: Notice served of the intention to terminate the outgoing repairs contract. Report P5
  • 17 July 2012: Gateway 1 procurement strategy approval. Report P70
  • 30 July 2012: Contract advertised. Report P72
  • 7 September 2012: Closing date for expressions of interest. Report P73
  • 7 January 2013: Closing date for return of tenders. Report P74
  • 16th April 2013: Gateway 2 contract award report approval. Report P78
  • 13th May 2013: Contract award, with mobilisation beginning. Report P81, P82
  • 3 Oct 2013; 2 Oct 2018; 2 Oct 2023: Contract start, initial completion date and completion date with extensions. Report P82, P83, P84

Plain English for the jargon

  • SBS: Southwark Building Services, the council's in house repairs and maintenance service [P20] [P27]
  • OJEU: The official procurement notice channel used to advertise the contract [P92]
  • PQQ: The questionnaire used to select contractors for the tender list [P34] [P35]
  • TUPE: Rules that would apply to staff transfers if the long term contractor differs from the interim contractor [P86]
  • KPI: A measure used to assess contractor or service performance [P12] [P111]
  • HRA reserves: The funding source identified for the estimated £150k legal and project management costs [P113] [P114]
  • Voids: Works to empty properties [P28]
  • Schedule of rates: A full list of prices used to measure and charge work, replacing a separate lump sum [P10] [P89]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

That the procurement strategy outlined in the report for the procurement of a repairs and maintenance contract covering Camberwell, Peckham, Peckham Rye, Nunhead and Dulwich for an annual value of up to £11m to commence from 3 October 2013 for five years with the option to extend for a further period up to five years (three plus two years), subject to performance, making an estimated contract value of £110,000,000 be approved. 2. That it be noted whilst all repairs and maintenance services are to be included in the procurement, two elements, namely the out of hours service and works to empty properties, might be suitable to be provided in-house as noted in paragraphs 21, 23-24 of the report. A decision will be made on this in the subsequent contract award report.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 15 pages

Recommendations

That Cabinet is asked to:

1. Approve the procurement strategy outlined in this report for the procurement of a repairs and maintenance contract covering Camberwell, Peckham, Peckham Rye, Nunhead and Dulwich for an annual value of up to £11m to commence from 3 October 2013 for five years with the option to extend for a further period up to five years (three plus two years), subject to performance, making an estimated contract value of £110,000,000.

2. Note that whilst all repairs and maintenance services are to be included in this procurement, two elements, namely the out of hours service and works to empty properties, might be suitable to be provided in-house as noted in paragraphs 21, 23-24 below. A decision will be made on this in the subsequent contract award report.

BACKGROUND INFORMATION

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Report: Gateway 1 Long-term Repairs and Maintenance ContractReport 15 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 10 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
DD
Councillor Dora Dixon-FyleCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
CH
Councillor Claire HicksonCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

On this subject at Southwark

Search all
  1. Gateway 1 Long-term Repairs and Maintenance ContractThis decision
  2. Gateway 2: Contract Award Approval - Long-term Repairs and Maintenance ContractApproved

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies