Quarterly Capital Monitoring Report Outturn and Capital Programme Refresh 2012-2022
NotedExecutive5 papers
AI summarySouthwark Cabinet noted the 2011/12 capital outturn, approved reprofiling, variations and new bids, and requested an updated programme report for September 2012. [D][P11][P12][P13][P14][P15] General fund underspend was £49.2m and housing underspend was £52.7m. [P27][P28]
Written from the decision and the officer reportPDF Pro
OutcomeNotedVirements, funded variations, reprofiling and new bids approved [D][P13][P14]
MoneyNot stated
What happens nextUpdated report due September 2012 [D][P15]Remaining refresh items to use updated resources and information [P15]
Who it affectsNot stated
What was decided
The 2011/12 general fund outturn in Appendix A, including the overall programme position, and the housing investment outturn in Appendix B were noted. [D][P11][P12] Report P11, P12
The virements and funded variations to the general fund capital programme were approved. [D][P13] Report P13
Cabinet approved the 2012/13 reprofiling of general fund expenditure and resources and new bids for both programmes, and requested an updated programme report for September 2012. [D][P14][P15] Report P14, P15
Why
The general fund underspend came from procurement, works and contractor management delays, withdrawn support for Rotherhithe school, delays at other school sites, ICT reprofiling and slippage in highways, lighting and riverside public realm. [P8][P23] Report P8, P23
Housing underspends came from delayed leaseholder buybacks and partnering contracts, with the Lands Tribunal judgement received too late to achieve the intended delivery. [P7][P146][P152] Report P7, P146, P152
New bids cover previously agreed cemetery and office accommodation decisions, Revitalise Camberwell and private sector housing renewal. [P9] Report P9
What happens next
The Strategic Director of Finance and Corporate Services will present an updated programme report in September 2012, using updated resources and information. [D][P15] Report P15
Carry out the approved virements and funded variations, and reprofile general fund expenditure and resources into 2012/13. [D][P13][P14][P171] Report P13, P14, P171
The approved new bids form part of the refresh, and the fuller refresh will add a year to maintain a ten year timetable and review continuing annual spending programmes. [D][P14][P172][P175] Report P14, P172, P175
The money
£49.2m General Fund underspend against budget Report P27, P29
£17.3m Housing renewal growth bid required over the programme Report P202
Implications
Financial: Approved reprofiling shifts unspent 2011/12 expenditure into the new financial year. [P171] Report P171
Financial: Housing programme resources have risen overall, but earlier years remain under pressure because resources arrive later. [P169] Report P169
Financial: Further resources may be needed for school places, housing renewal and cemetery projects. [P182][P188][P202] Report P182, P188, P202
Financial: Accumulated balances were committed to existing projects, but could change after finalisation of the 2011/12 accounts. [P161][P163] Report P161, P163
Risk: Large, complex programmes remain exposed to delays that cause substantial variations against planned spend. [P20][P23] Report P20, P23
Legal: The late Lands Tribunal judgement reduced the time available for intended housing works. [P146] Report P146
Staffing: Action is being taken to ensure staff resourcing has no overall impact on the level of approved housing works. [P148] Report P148
Equalities: Demand remains high for disabled facilities grants, and proposed savings may lower assistance per application from 2012/13. [P112][P113] Report P112, P113
Who and where
People who live, learn, visit or do business in the borough Report P19
Council housing residents and leaseholders Report P149, P152
Children, families and schools Report P180, P181, P182
Private homeowners and people using housing grants Report P105, P113
People needing adult care, dementia care or disability support Report P199, P200
Community councils and local communities Report P74
Council staff Report P129, P132, P148
People and businesses affected by major improvement schemes Report P78, P137
Timeline
2011/12: General fund outturn was £84.2m and housing investment outturn was £53.5m. [P27][P28] Report P27, P28
31 March 2012: Accumulated capital cash balances were £91.2m. [P161] Report P161
01 April 2012: Budgets reflected funded and agreed variations. [P173] Report P173
2012/13: Underspends were set to be reprofiled into the new financial year. [P171] Report P171
September 2012: Updated programme report due with remaining refresh items. [P15] Report P15
2021/22: An additional programme year would support a ten year timetable. [P175] Report P175
2012/13 and 2013/14: School carbon reduction work and troubled families adaptations were planned. [P180][P181] Report P180, P181
2015/16: An additional 10 to 14 permanent school class expansions were estimated as required. [P182] Report P182
Plain English for the jargon
Outturn: Actual expenditure recorded for the financial year. [P22][P29]
Reprofiling: Moving planned expenditure and resources into another financial year. [P171][P172]
HIP: Housing Investment Programme. [P18][P141]
Capital programme: Council spending funded through planned capital receipts, government supported borrowing, grants, Section 106 agreements and revenue contributions. [P160]
Warm Dry and Safe: A housing works programme using partnering contracts for delivery. [P145][P146][P148]
S106: A developer funding obligation used for council projects. [P69][P77][P119][P160]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item15
Resolved
That the outturn position for 2011/12 for the general fund capital programme including the overall position of the programme from 2011-21 (Appendix A of the report) be noted. 2. That the outturn position for 2011/12 for the housing investment programme (Appendix B of the report) be noted. 3. That the virements and funded variations to the general fund capital programme (Appendix C of the report) be approved. 4. That the reprofiling of general fund expenditure and resources in the new financial year 2012/13 in light of the outturn position in 2011/12, and new bids for both general fund and housing investment programmes (Appendix D of the report) be approved. 5. That the strategic director of finance and corporate services be requested to present an updated programme report with the remaining items for refresh in September 2012 in light of updated resources and information.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 26 pages
Item No. Classification: Date: Meeting Name: 15. Open 17 July 2012 Cabinet
Report title: Quarterly Capital Monitoring Report Outturn and Capital Programme Refresh 2012-2022
Ward(s) or groups All affected:
Cabinet Member: Councillor Richard Livingstone, Finance, Resources and Community Safety
FOREWORD - COUNCILLOR RICHARD LIVINGSTONE, CABINET MEMBER FOR FINANCE, RESOURCES AND COMMUNITY SAFETY
This report sets out the council's use of its capital expenditure in the 2011/12 financial year, for both the general fund and the housing investment programme, and seeks approval for some new bids to be included in the programme for forthcoming years. Cabinet will be taking further decisions to amend the programme when it considers the capital programme refresh report in the autumn.
In 2011/12, there was a significant variance, of just below 50%, in the expenditure on the housing investment programme. This has been as a result of delays in leaseholder buy- backs in the Aylesbury, Heygate and Abbeyfield projects and the delay in partnering contracts arising from the Lands Tribunal case. As part of the Warm, Dry and Safe programme agreed for 2012 onwards last October, steps have been put in place to pick up the pace on these works in future years.
On the general fund side, there has also been a significant variance. Some of this was anticipated when the programme was agreed last year, and some expectation of slippage was built into the programme. Nevertheless, the outturn represents 78.4% of the resources identified in the programme for the year and work is being undertaken with departments to improve that figure in future years. The report details the reasons for this difference, including the withdrawal of government support for the Rotherhithe school proposal preventing that work proceeding, delays in work on other school sites as part of the Southwark Schools for the Future programme, re-profiling of council ICT projects and slippage in the Highways and Lighting programme and improvements to the public realm near the riverfront.
New bids for approval as part of the programme in this report include funding decisions previously agreed by Cabinet in other reports, including the cemeteries strategy and changes to the office accommodation strategy. In addition, proposals are made here to Revitalise Camberwell and to fund housing renewal in the private sector. RECOMMENDATIONS
That Cabinet:
1. Notes the outturn position for 2011/12 for the general fund capital programme including the overall position of the programme from 2011-21 (Appendix A).
2. Notes the outturn position for 2011/12 for the housing investment programme (Appendix B).
3. Approves the virements and funded variations to the general fund capital programme (Appendix C).
4. Approves the reprofiling of general fund expenditure and resources in the new financial year 2012/13 in light of the outturn position in 2011/12, and new bids for both general fund and housing investment programmes. (Appendix D).
5. Requests the Strategic Director of Finance and Corporate Services to present an updated programme report with the remaining items for refresh in September 2012 in light of updated resources and information.
BACKGROUND INFORMATION
6. On 21 June 2011 the 2010/11 capital outturn report was presented to the Cabinet. This reported the capital outturn position at the end of 2010/11 and approved the continued expenditure and resources to be brought into the existing 2010–19 programme. At that time the total value of the general fund programme stood at approximately £429.4m including the Southwark Schools for the Future programme; the housing investment programme stood at £445.9m.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.