Approval to take a lease on the ground floor offices, 1 Lugard Road, SE15 2HG and of the principle heads of terms
AgreedExecutive2 papers
AI summarySouthwark Cabinet agreed to lease Block C, 1 Lugard Road, subject to acceptable terms [D]. The Chief Executive will finalise the lease [D]; capital requirements will go into the July 2012 capital outturn report [P4]; programme disposals are estimated at £50m, with £30m delivered [P38].
Written from the decision and the officer reportPDF Pro
OutcomeAgreedTerms must be acceptable and agreed with the landlord [D].
MoneyNot stated
What happens nextLease completion delegated [D]Chief Executive negotiates detailed terms and completes the lease [P3].
Who it affectsCouncil staff [P24]Up to 120 desk spaces are possible [P24].
What was decided
Cabinet agreed to take a lease of Block C, 1 Lugard Road, SE15 2HG. The lease is subject to acceptable terms being agreed with the landlord [D] [P2]. Report P2
Authority was delegated to the Chief Executive, following the Head of Property's recommendation, to agree detailed lease terms and complete the lease. The authority covers the closed report terms or better terms [D] [P3]. Report P3
Cabinet noted the capital requirements for taking the lease and fitting out the premises, as detailed in the closed report. Those requirements will be included in the capital outturn report presented to Cabinet in July 2012 [D] [P4]. Report P4
Why
Block C adds an operational office site in the centre or south of the borough and places it with Blocks F and J in one campus [P8] [P14] [P15]. Report P8, P14, P15
The premises can accommodate up to 120 desks and support call handling facilities for a new service operated in house, while shared facilities are expected to improve efficiency [P16] [P24] [P34]. Report P16, P24, P34
The office accommodation programme is fully funded through surplus property disposals, and the revised capital allocation will fund Block C's acquisition and fit out [P38] [P40]. Report P38, P40
What happens next
Complete landlord negotiations and technical due diligence, then agree detailed terms and complete the lease [D] [P3] [P22] [P25]. Report P3, P22, P25
Include the lease acquisition and fit out capital requirements in the capital outturn report presented to Cabinet in July 2012 [D] [P4]. Report P4
Procure fit out works under the iESE contractors framework. Practical completion is anticipated by 1 April 2013, subject to lease and procurement approvals [P26]. Report P26
The money
£50m Current estimate for disposals resulting from the office accommodation programme [P38]. Report P38
£30m Disposal receipts delivered so far under the programme [P38]. Report P38
£2.5 m Properties identified as candidates to enter the programme's scope [P38] [P39]. Report P38, P39
£100,000 Constitutional threshold for Cabinet decisions on land and property acquisitions [P48]. Report P48
Options considered
Chosen: Take a lease of Block C at 1 Lugard Road, subject to acceptable terms. It supports an operational hub in the centre or south of the borough, brings staff together and allows facilities to be shared across the Queens Road campus [P14] [P16]. Report P14, P16
Implications
Financial: The lease acquisition and fit out costs will be funded through the revised capital allocation, subject to approval of the capital outturn report in July 2012. The wider programme is fully funded through surplus property disposals [P38] [P40] [P53]. Report P38, P40, P53
Financial: A facilities management revenue budget will use funds from candidate teams' current accommodation. Overall council spending on facilities management is expected to reduce [P42]. Report P42
Legal: Section 120 of the Local Government Act 1972 permits the council to acquire land by agreement for its statutory functions or for the benefit, improvement or development of its area. The constitution reserves land and property acquisitions to Cabinet where market value exceeds £100,000 [P45] [P48]. Report P45, P48
Risk: Landlord negotiations remain ongoing. The due diligence survey is not expected to reveal significant issues, but its conclusions and recommendations must inform the report seeking approval of final heads of terms [P22] [P25]. Report P22, P25
Risk: The existing temporary fit out will need to be removed and replaced with a standard consistent with Blocks F and J [P21]. Report P21
Staffing: Up to 120 desks can be accommodated, with the final number based on service needs. Initial use is proposed for call handling facilities for a new service operated in house [P24] [P34]. Report P24, P34
Climate: Consolidating offices is intended to improve environmental sustainability, reduce the number of office sites and release strategic sites for regeneration [P29] [P30] [P31]. Report P29, P30, P31
Other: The council expects the Queens Road campus to bring economic benefits to the local area [P17]. Report P17
Who and where
Council staff using Block C Report P21, P24
New service using call handling facilities Report P34
Customer services function moving in house from the Cottons Centre Report P35
Community Housing Service, a possible occupant Report P36
Specialist Children's services, possible occupants Report P36
Corporate training and meeting facilities, possible users Report P36
Wandle Housing Association, landlord and former occupier Report P21
People in the local area around Queens Road Report P17
Timeline
23 November 2010: Cabinet approved the Revised Office Accommodation Strategy [P6]. Report P6
1 June 2011: The Block F lease was completed for a term of 20 years [P10]. Report P10
20 March 2012: Cabinet approved acquisition of the freehold of Block J [P11]. Report P11
April 2012: The opportunity to lease Block C was presented to officers [P13]. Report P13
28 May 2012: Acquisition of the freehold of Block J was completed [P12]. Report P12
July 2012: The capital outturn report with Block C requirements was due before Cabinet [P4] [P38]. Report P4, P38
December 2012: The Overground link to the London Underground network was expected to open [P17]. Report P17
1 April 2013: Practical completion of Block C fit out was anticipated, subject to lease and procurement approvals [P26]. Report P26
Plain English for the jargon
Revised Office Accommodation Strategy: The council strategy approved on 23 November 2010 to maximise use of 160 Tooley Street and provide a further operational office site in the centre or south of the borough [P6] [P8].
Operational hub: An office location in the centre or south of the borough where staff and facilities are brought together [P8] [P16].
Principle heads of terms: The proposed lease terms contained in the closed version of the report [P23].
Shell/core condition: The condition of the Block C space that lacks the existing cellular meeting and office fit out [P21].
iESE contractors framework: The proposed procurement arrangement for Block C fit out works, similar to that for Blocks F and J [P26].
Technical due diligence survey: A commissioned survey expected not to reveal significant issues, with its conclusions considered in the final heads of terms report [P25].
Localism Act general power of competence: A power allowing councils generally to do what individuals can do, subject to legal limitations [P47].
Practical completion: The expected finish of Block C fit out, anticipated by 1 April 2013 [P26].
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item19
Resolved
That it be agreed to take a lease of Block C, 1 Lugard Road, SE15 2HG (identified on the plan attached to the report), subject to acceptable terms being agreed with the landlord. 2. That authority be delegated to the chief executive to agree detailed lease terms, as recommended by the head of property, and to complete a lease of the premises on the terms (or better) set out in the closed version of the report. 3. That the capital requirements for the acquisition of the lease and fit out costs, as detailed in the closed version of the report be noted and that it will be incorporated into the capital outturn report that is being presented to cabinet in July 2012.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 6 pages
Recommendations
That cabinet:
1. Agrees to take a lease of block C 1 Lugard Road, SE15 2HG (identified on the attached plan), subject to acceptable terms being agreed with the landlord.
2. Delegates authority to the Chief Executive to agree detailed lease terms, as recommended by the Head of Property, and to complete a lease of the premises on the terms (or better) set out in the closed version of this report.
3. Notes that the capital requirements for the acquisition of the lease and fit out costs, as detailed in the closed version of this report, will be incorporated into the capital outturn report that is being presented to cabinet in July 2012.
BACKGROUND INFORMATION
4. Cabinet approved the Revised Office Accommodation Strategy at its meeting on 23 November 2010.
5. The Revised Office Accommodation Strategy committed the council to maximise the use of 160 Tooley Street. Overall 350 additional staff have been moved in to Tooley Street, including for example the new housing central operations team and the new in-house revenues and benefits service.
1 6. In addition to maximising the use of Tooley Street, the accommodation strategy agreed the council’s requirement for a further operational office site in the centre or south of the borough for specialist services that do not fit efficiently into the Tooley Street model or which are geographically more appropriately located in that area.
7. A previously unoccupied office development comprising of two adjacent blocks (F and J) was identified at Queens Road, SE15, and cabinet delegated authority to the chief executive to acquire leases on these properties.
8. A lease of Block F Queens Road was completed on 1 June 2011 for a term of 20 years. Subsequently, procurement for fit-out of the property was completed and the build project is currently underway with practical completion expected on 30 July 2012. The office block will provide modern, flexible and sustainable accommodation for 350 staff with occupation commencing during August and September 2012. Major staff groups will include health and community services, housing management and community safety.
9. Cabinet approved a subsequent decision to acquire the freehold of Block J Queens Road, on 20 March 2012. This acquisition will allow the council to continue consolidating its remaining estate and to further fulfil anticipated accommodation requirements in terms of space, quality and flexibility.
10. The acquisition of the freehold of Block J was completed on 28 May 2012.
11. Since that decision, the opportunity to acquire a lease on additional ground floor office accommodation within a third adjacent unit, Block C, was presented to officers in April 2012.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.