Gateway 2: Contract Award Approval Consolidated Facilities Management Contract for 160 Tooley Street, London SE1 2QH
ApprovedExecutive3 papers
AI summaryCabinet approved Interserve Plc's facilities management contract for 160 Tooley Street for 5 years from 1 February 2013, retaining council elements and allowing up to 2 further years [D]. The year one total is 1.429, with figures in £m [P6] [P7].
£1,000 Contractor risk threshold for each work item Report P3
£20k Current annual value of small pass through items Report P4
Options considered
Chosen: Standard bid with elements retained by the council. The council selected this bid after neither totally outsourced proposal met the additional criteria. The recommended provider scored highest in quality and price [D] [P21] [P22]. Report P21, P22
Rejected: Totally outsourced solution. Neither bidder's proposal met the additional criteria, so evaluation focused on the partially outsourced solution [P21]. Report P21
Chosen: Continue the procurement with two bids. The steering group considered the implications of only two bids and decided to continue [P20]. Report P20
Implications
Financial: The contract is funded from existing Tooley Street budget CH222, and its base cost can be contained within current provision [P1]. Report P1
Financial: The fixed lump sum is expected to be 90% of contract cost, with two variable streams making up 10% [P2]. Report P2
Financial: The fixed lump sum and variable rates rise each year in line with the agreed RPIX index [P5]. Report P5
Risk: The contractor bears each work item's cost up to £1,000, while the council meets the balance above £1,000 [P3]. Report P3
Risk: Only two of eight bidders submitted proposals, although the steering group decided to continue after considering the implications [P20]. Report P20
Legal: The award is reserved to cabinet as a Strategic Procurement, and the GPS route met EU and council tendering requirements [P25] [P26]. Report P25, P26
Staffing: The award retains elements of the council's Tooley Street facilities management service [D].
Other: The contract could support service provision at other identified key buildings if extended [P15]. Report P15
Who and where
Interserve Plc
Facilities management service at 160 Tooley Street
Council's retained Tooley Street service elements
Staff, suppliers and trade unions consulted during procurement Report P13
Other identified key buildings if the contract is extended Report P15
Timeline
February 2011: Budget report to Council set out business plan savings Report P1
11 October 2012: The final report was dated Report P37, P38
2013/14: CFM savings target included fixed lump sum efficiency Report P8
1 February 2013: The contract was to commence
Each contract year anniversary: Fixed lump sum and variable rates rise with RPIX Report P5
5 years from 1 February 2013: This was the initial contract period
Up to a further 2 years: The council could extend at its discretion
Plain English for the jargon
Fixed lump sum: Contractor's inclusive price for works and services within the threshold [P3].
Pass through items: Small costs passed to the council without overhead or profit [P4].
Variable cost stream: Costs outside the fixed price that vary with need [P9].
RPIX index: Index used for the contract's annual price review [P5].
GPS framework: Facilities Management Framework used for the procurement [P19] [P26].
CFM: Consolidated facilities management contract and savings target [D] [P8].
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14
Resolved
That the award of the consolidated facilities management contract for 160 Tooley Street to Interserve Plc for a period of 5 years commencing 1 February 2013 with the provision to extend at the council’s discretion for up to a further 2 years be approved. 2. That it be noted that the award is for the standard bid retaining the in-house elements of the council’s Tooley Street facilities management service for the reasons set out in paragraphs 46 to 48 of the report.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 17 pages
Item No. Classification: Date: Meeting Name: 14. Open 23 October 2012 Cabinet
Report title: Gateway 2 – Contract Award Approval Consolidated Facilities Management contract for 160 Tooley Street, SE1 2QH.
Ward(s) or groups affected: All
Cabinet Member: Councillor Richard Livingstone, Finance, Resources and Community Safety
FOREWORD – COUNCILLOR RICHARD LIVINGSTONE, CABINET MEMBER FOR FINANCE, RESOURCES AND COMMUNITY SAFETY
This report recommends the award of the consolidated facilities management contract for the council's offices at 160 Tooley Street to Interserve PLC for a period of 5 years, commencing on 1 February 2013. This contract will bring together eleven services that are currently managed through different contracts.
This contract will save £312,000 per year in the lump sum value of the contract, a 20% saving on current arrangements. Furthermore, it will ensure that all staff employed by our contractors to deliver these services will receive the London Living Wage as a minimum.
This has been a long procurement process, given the need to assess bids against both a standard specification and a variant specification. The variant specification considered the benefits of transferring a number of council employees working on facilities management functions to the new contractor. Market-testing of that variant specification has identified that it would not generate significant further savings and so the recommendation is based on the standard specification: only for those facilities management services currently delivered through contract arrangements. . RECOMMENDATIONS
That cabinet
1. Approve the award of the Consolidated Facilities Management contract for 160 Tooley Street to Interserve Plc for a period of 5 years commencing 1 February 2013 with the provision to extend at the council’s discretion for up to a further 2 years.
2. Note that this award is for the standard bid retaining the in-house elements of the council’s Tooley Street Facilities Management service for the reasons set out in paragraphs 46 to 48.
BACKGROUND INFORMATION
3. 160 Tooley Street is the council’s main administrative centre accommodating 2,200 people in a modern and flexible working environment. The building has been fully occupied since mid 2009 and has been maintained to a good standard. 4. Facilities Management (FM) services to 160 Tooley Street are currently provided through a number of outsourced contractual arrangements and an in-house operational FM service.
5. Facilities Management is a fundamental business support service that is vital to service delivery and business continuity. It enables the council’s adopted modern ways of working and supports the council’s agility in the delivery of the wider office accommodation strategy.
6. In line with the agreed procurement strategy this contract has been developed to have the flexibility to incorporate further sites within the scope of the contracted services where best value and cost effectiveness can be demonstrated utilising economies of scale and minimising client management resource.
7. Additional sites will not be considered for incorporation until the council is in contract and has undertaken an early assessment of contractor performance through transition and TUPE transfer. If the level of performance and the value for money mechanisms demonstrate clear benefits to the council this process will be accelerated to maximise the efficiencies of both innovation and economies of scale.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.