London Borough of Southwark
Executive, Tuesday 13 October 2026 at 11.00am

Gateway 1 - Highway works contract

Approved Executive 2 papers

AI summarySouthwark Council approved a two lot competitive procurement for highway works from 01 April 2028, with potential values of £39.25 million for maintenance and £127.55 million for projects over seven years plus up to three years. [D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedTwo lots; suppliers may bid for either or both. [D]
Money£39.25m; £127.55m [P139]Potential ten year values for Lots A and B. [P139]
What happens nextGateway 2 follows tender [P6]Tender in early 2027; approval in Summer 2027. [P37][P6]
Who it affectsHighway users and contractors [P94]Maintenance, projects, footways, roads and cycleways. [P94][P96]

What was decided

The procurement strategy for highway works was approved. It covers routine maintenance, winter services, reactive repairs, planned renewal and improvement projects.

The Competitive Flexible Procedure was approved using two lots. Suppliers may bid for one lot or both lots. Report P32, P33

The anticipated contract starts on 01 April 2028. The initial term is seven years, with an option to extend for up to three further years.

Why

The council has a statutory duty to keep most public roads and pavements safe. This includes pothole repairs, winter gritting and other maintenance. Report P16

Separate lots bring specialist expertise, increase competition, reduce delivery risk and improve value for money. The design also increases the chance of SME interest. Report P20, P34

A competitive tender allows market testing, revised specifications, innovation and new performance monitoring. It also supports environmental, climate and social value objectives. Report P31, P71, P108

What happens next

A Gateway 3 report is due in November 2026 on taking up the further 12 month extension. This would extend the current contracts to 31 March 2028. Report P13, P39

The contract is planned to be tendered in early 2027. A Gateway 2 contract award report is planned for Summer 2027, with approval listed for 19/07/2027. Report P37, P6, P50

Formal consultation will take place with the incumbent contractor and potential suppliers under the current contract and procurement rules. Report P135

The money

  • £3.925 million Estimated annual value for Lot A, maintenance.
  • £39.25 million Potential total value for Lot A over the initial term and extension option.
  • £12.755million Estimated annual value for Lot B, projects.
  • £127.55 million Potential total value for Lot B over the initial term and extension option.
  • £4.5m per year Average Lot A revenue budget over the past three financial years. Report P14
  • £15m per year Average Lot B capital budget, including external funding. Report P14
  • £39,250 Total shown for Lot A in the indicative budget table. Report P131
  • £127,550 Total shown for Lot B in the indicative budget table. Report P131

Options considered

  • Rejected: Do nothing. The current contracts cannot continue beyond 31 March 2028. Doing nothing would leave the council unable to discharge its highway maintenance duty and exposed to insurance claims and possible litigation. Report P26
  • Rejected: Bring the services in house. Insourcing would require significant capital for machinery and depots, with high operating costs for services that are not always required. Report P27
  • Rejected: Use the London Highway Maintenance and Project Framework. The framework would limit the council's ability to tailor contractual arrangements to its operational, performance and sustainability objectives. Report P29
  • Chosen: Run a new competitive tender using the Competitive Flexible Procedure. This route permits market testing, revised specifications, innovation, stronger performance monitoring and the use of two lots with specialist supplier expertise. Report P31, P32, P34

Implications

  • Financial: There is no guaranteed minimum volume or contract value. The values are indicative and depend on revenue budgets, capital budgets and external funding. Report P127, P139, P140
  • Financial: Schedule of Rates will be fixed but adjusted annually for inflation. Contractors and subcontractors must meet the London Living Wage requirement, and expenditure and demand will be monitored. Report P17, P44, P45, P110
  • Risk: The current contracts can be extended only to 31 March 2028. A transition plan and current contractor delivery to expiry are intended to protect service continuity. Report P39, P44
  • Legal: The procurement must comply with the Procurement Act 2023. A change of provider may trigger TUPE, with approximately three full time Lot A employees and 21 full time Lot B employees potentially eligible for transfer. Report P52, P53, P156
  • Equalities: The Public Sector Equality Duty was considered and the impact has not changed since the current contract was awarded. Very young, disabled and elderly people are expected to benefit from safer footways. Report P95, P99
  • Climate: The new contract can embed carbon reduction, low carbon design and emissions monitoring. It supports the council's carbon neutrality ambition for 2030. Report P102, P104, P119
  • Staffing: Highways officers will lead the procurement with support from Legal, Finance and Procurement. Mobilisation and transition arrangements will support any employee transfer. Report P53, P125
  • Other: Tender scoring is 55% price, 35% quality and 10% social value. Monthly contract meetings and quarterly performance reviews will monitor the contractor. Report P69, P70, P123

Who and where

  • All borough communities and highway users Report P94, P97
  • Very young, disabled and elderly people Report P95
  • Pedestrians and cyclists Report P96, P101
  • Workers, businesses, visitors and people passing through the borough Report P97, P101
  • The incumbent contractor, FM Conway Ltd Report P12
  • Employees potentially transferring under TUPE Report P52, P53
  • Prospective bidders, including SMEs and larger contractors Report P20, P22
  • Local apprentices and supply chain businesses Report P88, P89

Timeline

  • 11 March 2026: The Gateway 0 strategic procurement options assessment was approved. Report P8
  • 13/10/2026: Executive approval of the Gateway 1 procurement strategy. Report P50
  • November 2026: A Gateway 3 report will consider the further 12 month extension. Report P13, P39
  • 31 March 2027: Current contract expiry date following the approved 12 month extension. Report P12
  • early 2027: The new contracts are planned to be tendered. Report P37
  • Summer 2027: A Gateway 2 report will go to Executive after the procurement process. Report P6
  • 01 April 2028: The anticipated new contract start date. Report P50
  • 31/03/2035 and 31/03/2038: Initial completion, followed by completion if extension options are exercised. Report P50

Plain English for the jargon

  • Competitive Flexible Procedure: A Procurement Act 2023 route under which suppliers may bid for either or both lots. [P32][P33]
  • Lot A: Maintenance services, including routine work, winter services and small scale reactive repairs. [P11][P33]
  • Lot B: Projects services, including planned renewal and improvement projects. [P11][P33]
  • Gateway 1, 2 and 3: Approval stages for the procurement strategy, contract award and any current contract extension. [P6][P13][P47]
  • Schedule of Rates: Contract rates that stay fixed but are adjusted each year for inflation. [P17]
  • TUPE: The Transfer of Undertakings (Protection of Employment) Regulations 2006, which may apply when the service provider changes. [P52]
  • SME: A small or medium sized enterprise considered in the procurement design. [P20][P31]
  • KPI: A performance measure used to monitor and incentivise the contractor. [P119][P123]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

That the procurement strategy outlined in the report for the provision of Highways Works be approved, comprising: · Lot A (Maintenance), covering routine maintenance, winter services and reactive repairs, with an estimated annual value of £3.925 million. The contract is anticipated to commence on 01 April 2028 for an initial term of seven years, with the option to extend for up to a further three years, giving a total potential contract value of £39.25 million. · Lot B (Projects), covering planned renewal and improvement projects, with an estimated annual value of £12.755million. The contract is anticipated to commence on 01 April 2028 for the initial term of seven years, with the option to extend for up to three further years, giving a total potential contract value of £127.55 million. 2. That use of a Competitive Flexible Procedure for the procurement (as detailed in the report), comprising two lots, with suppliers permitted to bid for one or both lots be approved.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Executive

Reasons for recommendations

6. The reasons for the recommended procurement approach are detailed in paragraphs [16-19] of this report.

ALTERNATIVE OPTIONS CONSIDERED AND NOT RECOMMENDED

7. The alternative options considered for this procurement are set out in paragraphs [23-26] of this report.

POST DECISION IMPLEMENTATION

8. Once the recommendation(s) within this report have been approved:

i. A Gateway 2 report will be presented to Executive for consideration in Summer 2027 following the conclusion of the procurement process. ii. Details of the planned contract management and monitoring regime are set out in paragraphs [85-86] of this report. iii. The implementation timeline is set out in paragraph [37] of this report.

BACKGROUND INFORMATION

9. This Gateway 1 procurement strategy follows the Gateway 0 strategic procurement strategy options assessment approved by the Cabinet Member for Climate Emergency, Jobs & Transport on 11 March 2026.

10. The Gateway 0 decision approved that the following services currently delivered externally will continue to be delivered externally;  Reactive maintenance (2 & 24 hr response services)  Planned maintenance (7 & 28 day response services)  Winter maintenance and carriageway gritting  Major maintenance (Non-Principal Road and Principal Road)  Capital Project delivery

11. The Gateway 0 required officers to prepare a Gateway 1 report for further consideration of the procurement strategy for the outsourced works.

12. These works are currently being provided by FM Conway Ltd under the Southwark Highways Works Contracts (SHWC). The provision of services are divided into the following lots:  Lot A – Maintenance (routine maintenance, winter services and small scale reactive repairs)  Lot B – Projects (planned renewal and improvement projects)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gateway 1 Highway Works Contract Equality Impact and Needs AnalysisAppendix 1 340 KB Download
PDF
Report: Gateway 1: Highway Works ContractReport 528 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 10 attended
JM
Councillor James McAsh Leader of the CouncilChair, expected
VC
Councillor Victor Chamberlain Deputy Leader and Executive Member for Neighbourhoods, Strategic Planning, and WellbeingVice-Chair, expected
AA
Councillor Alexandra Austin Executive Member for Public Works and New HomesCommittee Member, expected
RB
Councillor Rachel Bentley Executive Member for Inclusive Economy, Equalities and DemocracyCommittee Member, expected
RC
Councillor Rebecca Corn Executive Member for Education and CareCommittee Member, expected
SF
Councillor Sam Foster Executive Member for Finance and General PurposesCommittee Member, expected
RP
Councillor Reginald Popoola Executive Member for Council HomesCommittee Member, expected
VT
Councillor Vanessa Threadgold Executive Member for Parks and RecreationCommittee Member, expected
EW
Councillor Eloise Waldon-Day Executive Member for Council Co-ordination and ClimateCommittee Member, expected
DW
Councillor David Watson Executive Member for Community Safety and EngagementCommittee Member, expected

On this subject at Southwark

Search all
  1. Gateway 1 - Highway works contractThis decision
  2. Gateway 1 - Procurement Strategy Approval: Integrated Highways Maintenance, Project Delivery and Professional Services ContractApproved
  3. Combined Gateway 1 Procurement Strategy Approval and Gateway 2 Contract Award for Integrated Highways Term ContractApproved
  4. Gateway 2 - Contract Award Approval - Integrated Highways Maintenance, Project Delivery and Professional Services ContractApproved

More from Southwark Executive

All decisions
MeetingDecisionOutcome
13 Oct 2026 MinutesThat the minutes of the meeting held on 15 September 2026 be approved as a correct record and signed by the chair. Approved Open
13 Oct 2026 Deputation requestsRESOLVED - That the written statement from Andrew Eke be heard. Deputation to Southwark Council Executive – Tustin Es... Decided Open
13 Oct 2026 Beormund School Expansion and RelocationThat the proposals to relocate and expand the Beormund Special Primary School be agreed. Agreed Open
13 Oct 2026 Climate Change Strategy & Action Plan Update and Annual ReportThat the contribution of communities, schools, businesses and council services in tackling the climate crisis over th... Noted Open
13 Oct 2026 Ledbury Estate Phase 2 - Appropriation for Planning PurposesThat the land shown outlined on the plan at Appendix 1 of the report known as Phase 2 of the Ledbury Estate that is c... Approved Open