Cherry Garden School Increase in Size - Report Back on Statutory Notice Consultation

Agreed Executive 5 papers

AI summarySouthwark Cabinet agreed to enlarge Cherry Garden Primary Special School permanently from 46 to 66 places from 1 September 2015. [D] The estimated capital cost was £13 million. [P18]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreed46 to 66 places from 1 September 2015. [D]
Money£13 million capital cost [P18]Included in the 2012/13 Capital Refresh. [P18]
What happens nextDeliver permanent expansion [P5] [P29]Combined contract for works, with expansion from 1 September 2015. [P5] [P29]
Who it affectsPupils with special educational needs [P14]More pupils can benefit from improved and expanded buildings. [P14]

What was decided

The permanent enlargement of Cherry Garden Primary Special School from 46 to 66 places was agreed to take effect from 1 September 2015.

Why

The current school building had serious condition and suitability issues and was a priority in the Primary Capital Programme. [P7] The proposed new school on the Gloucester primary school site could allow services to be located together. Its location between Gloucester and Tuke would enable the two special schools to work together. [P7] [P8] Report P7, P8

The SEN Improvement Test showed expected improvements from better facilities and a more central location. A shorter travel time for most pupils would benefit health and education. [P15] Report P15

The increase is a prescribed alteration because it was over 10% of the original Planned Admission Number. Appropriate consultation was completed, the statutory notice was published, and no representations were received. [P12] [P24] Report P12, P24

What happens next

Deliver the works through a combined contract that also covers works to Gloucester Primary School. Cherry Garden was to expand formally from 1 September 2015. [P5] [P29] Report P5, P29

Develop an outreach programme into the local community. [P14] Report P14

Record Cabinet’s consideration of Stage 4 guidance, the SEN Improvement Test and the Equality Impact Assessment. [P25] [P26] [P27] Report P25, P26, P27

The money

  • £13 million Estimated capital cost of the works, included in the 2012/13 Capital Refresh. Report P18
  • £13m Total value of the combined contract for Cherry Garden School and works to Gloucester Primary School. Report P29
  • £9m Approximate value for Cherry Garden School within the combined contract. Report P29

Options considered

  • Chosen: Increase Cherry Garden Primary Special School permanently from 46 to 66 places from 1 September 2015.. The current building had serious condition and suitability issues. The SEN Improvement Test anticipated better facilities, a more central location and shorter travel for most pupils, with health and educational benefits. Report P7, P15

Implications

  • Financial: The works had an estimated capital cost of £13 million, included in the 2012/13 Capital Refresh. Report P18
  • Financial: The combined Cherry Garden and Gloucester Primary School contract had a total value of £13m, with an approximate Cherry Garden value of £9m. Report P29
  • Legal: Cabinet is enabled to agree the recommendation under Part 3C of the Council’s Constitution. The Director of Legal Services advised approval. Report P21
  • Legal: The recommendation rests on school reorganisation duties under the Education Act 1996 and the Education and Inspections Act 2006. The Council has a statutory duty under s.14(2) Education Act 1996 to ensure suitable special educational needs provision is available in Southwark. Report P22, P23
  • Legal: The increase is a prescribed alteration because it was over 10% of the original Planned Admission Number. Appropriate consultation and statutory notice requirements were met. No statutory notice was required for Gloucester Primary School because the proposed relocation was not a prescribed alteration. Report P24
  • Equalities: The Equality Impact Assessment assesses relevant considerations for the enlarged school and improved facilities for severely disabled children. Report P16
  • Other: The SEN Improvement Test showed expected benefits from improved facilities, a more central location and shorter travel for most pupils, with health and educational benefits. Report P15
  • Risk: The current school building has serious condition and suitability issues. Report P7

Who and where

  • Pupils with special educational needs in Southwark Report P14, P15
  • Pupils with severe, profound and multiple learning difficulties and complex needs Report P7, P8
  • Severely disabled children Report P16
  • Cherry Garden School pupils Report P7, P15
  • Parents and carers of pupils Report P9
  • Cherry Garden School governors and staff Report P9
  • The local community Report P14
  • Gloucester Primary School and Tuke secondary special school Report P7, P8, P29

Timeline

  • 1 February 2010: Stage 4 of the decision makers statutory guidance was dated. Report P25
  • May 2010: Ofsted judged Cherry Garden School outstanding. Report P7
  • 15 March to 20 April 2012: The initial consultation took place. Report P9
  • 27 July 2012: The Cabinet Member for Children’s Services agreed publication of the statutory notice. Report P3
  • Thursday 13 September: The statutory notice was displayed at the school gates, in the local library and in the local press. A 6 week period for representations followed, with no representations received. Report P12
  • 29 November 2012: The final report was dated. Report P34
  • 2012/13: The estimated works cost was included in the Capital Refresh. Report P18
  • 1 September 2015: Cherry Garden was to expand permanently from 46 to 66 places. Report P5

Plain English for the jargon

  • SEN: Special educational needs. [P15]
  • SEN Improvement Test: An assessment showing expected improvements in special educational needs provision. [P15] [P26]
  • Prescribed alteration: A school change covered by the 2007 maintained schools regulations. [P24] The increase qualified because it was over 10% of the original Planned Admission Number. [P24]
  • Statutory notice: The public notice required for the proposal, with a 6 week period for representations. [P12]
  • Primary Capital Programme: The programme in which the school building was identified as a priority. [P7]
  • Co location: Potential for services to share one site. [P7]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

That the permanent enlargement of Cherry Garden Primary Special School from 46 to 66 places from 1 September 2015 be agreed.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 4 pages

Recommendation

1. That the Cabinet agrees the permanent enlargement of Cherry Garden Primary Special School from 46 to 66 places from 1 September 2015.

BACKGROUND INFORMATION

2. The Cabinet Member for Children’s Services agreed on 27 July 2012 to the publication of the statutory notice on the proposal to increase Cherry Garden School in size from 46 to 66 places from 1 September 2015 following a consultation process.

3. The statutory notice has been published as required. This report also summarises the outcomes of the earlier consultation process on this proposal.

4. It is now proposed that Cherry Garden formally expands from 1 September 2015.

KEY ISSUES FOR CONSIDERATION

5. Cherry Garden is a very effective special school, judged to be outstanding by Ofsted in May 2010. However, the current school building has serious condition and suitability issues and was therefore identified as a priority in the Primary Capital Programme. It is proposed to enlarge the school to take 66 pupils and to develop the new Cherry Garden School on the Gloucester primary school site. There would be many advantages in this, such as the potential for co-location of services. In addition the new proposed location is between Gloucester and the new Tuke secondary special school. This proposal would therefore enable the

1 two special schools to work together in supporting pupils with severe, profound and multiple learning difficulties and complex needs, particularly at the age of transfer.

Consultation

6. There was an initial consultation process on the proposed enlargement of Cherry Garden School from 15 March to 20 April 2012. Letters were sent to the following stakeholders: parents and carers of pupils, governors and staff at Cherry Garden School, Headteachers and Chairs of governors of all Southwark schools, Councillors, the NHS Trust, local MPs, trade unions and a neighbouring authority.

7. The outcome of the initial consultation is summarised in Appendix 1.

Statutory notice

8. The attached statutory notice was published to the community as required by displaying it on the school’s gates, in the local library and in the local press on Thursday 13 September, allowing a 6 week period for representations on the proposals. No representations have been received.

Community impact statement

9. Permanently enlarging Cherry Garden School will enable more pupils in Southwark with special educational needs to benefit from improved and expanded buildings and to enable the school to develop an outreach programme into the local community.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
The outcome of the initial consultation processAppendix 1 3 pages Download
PDF
Statutory noticeAppendix 2 1 pages Download
PDF
SEN Improvement TestAppendix 3 2 pages Download
PDF
Equality Impact AsessmentAppendix 4 4 pages Download
PDF
Report: Cherry Garden School increase in size: Report back on statutory notice consultationReport 4 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 11 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-FyleCommittee Member, apologies
BH
Councillor Barrie HargroveCommittee Member, present
CH
Councillor Claire HicksonCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

On this subject at Southwark

Search all
  1. Cherry Garden School Increase in Size - Report Back on Statutory Notice ConsultationThis decision
  2. Determination of Primary School Expansions - Permanent Enlargement of Cherry Garden School, and Phoenix, Bellenden, Ivydale, Robert Browning, and Keyworth Primary SchoolsNoted

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies