Cabinet (decommissioned, for the Executive after, Thursday 28 May 2026 at 4.00pm

Determination of Primary School Expansions - Permanent Enlargement of Cherry Garden School, and Phoenix, Bellenden, Ivydale, Robert Browning, and Keyworth Primary Schools

Noted Executive 1 paper

AI summaryCabinet approved permanent enlargements of Phoenix, Bellenden, Ivydale, Robert Browning and Keyworth primary schools from 1 September 2016 onwards, and Cherry Garden School's enlargement and relocation from September 2017 onwards, within a £106.5m primary expansion programme budget [D] [P75] [P76].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedFive from 1 September 2016; Cherry Garden from September 2017. [D] [P2]
Money£106.5m primary expansion budget [P75]Approved work fits allocated departmental capital budgets. [P76]
What happens nextImplement enlargements and relocation [D]Five from 1 September 2016; Cherry Garden from September 2017. [D] [P2]
Who it affectsNot stated

What was decided

Cabinet noted the consultation result. Two objections were received, both concerning Keyworth Primary School. Report P1, P13, P15

Cabinet agreed permanent enlargements of Phoenix, Bellenden, Ivydale, Robert Browning and Keyworth Primary Schools from 1 September 2016 onwards. Report P2

Cabinet agreed to enlarge Cherry Garden School and relocate it to a new site from September 2017 onwards. Report P2

Why

Forecasts showed a continuing increase in demand and a shortfall in reception places. The schools had physical expansion capacity, governors had agreed, and the council had budget available. Report P23, P25, P50

The council has a legal duty to secure enough primary and secondary places, promote diversity and consider parental preference. Not expanding could leave it vulnerable to legal action. Report P49, P68

The two Keyworth objections were considered. Officers said the rise matched local demand and the school's popularity, and found no evidence of a cumulative negative impact. Planning issues were for the Planning Committee. Report P42, P43, P44

What happens next

Deliver the five permanent enlargements from 1 September 2016 onwards. Report P2

Deliver Cherry Garden School's enlargement and relocation to a new site from September 2017 onwards. Report P2

Allocate the first wave budget at the gateway 2 construction contract award. Schools will be responsible for ongoing expansion revenue. Report P64, P65

The money

  • £106.5m Total budget for the primary expansion programme, incorporating expansions currently planned. Report P75
  • £106.4m Revised programme funding at Quarter 3 2014-15, stated to be sufficient for all proposed enlargements. Report P62
  • £44.4m Budget variation agreed for the Children’s and Adults’ Services capital programme. Report P75
  • £35.9m Proposed variations and transfers included in the revised funding. Report P62
  • £15.8m Council resources within the budget variation, for the expected programme shortfall. Report P75
  • £70.5m Overall programme budget identified in the July 2014 cabinet report. Report P62

Options considered

  • Chosen: Approve the enlargement and relocation proposals. The statutory process was completed, demand was forecast, and capacity and funding were available. Report P17, P18, P19, P23, P50
  • Rejected: Approve the proposals with modifications Report P21
  • Rejected: Approve the proposals conditionally Report P21
  • Rejected: Reject the proposals Report P21

Implications

  • Financial: The approved enlargements fit within departmental capital budgets. Schools will meet ongoing revenue costs, with the Dedicated Schools Grant covering the first financial year through the growth fund and later through the schools funding formula. Report P65, P76
  • Staffing: Staffing and other connected costs can be contained within existing departmental revenue budgets. Report P77
  • Legal: The council must secure enough primary and secondary places, promote diversity and consider parental preference. Not expanding could leave it vulnerable to legal action for failing to provide sufficient primary school places. Report P49, P68
  • Equalities: The equality analysis found no potential for discrimination and says the expansions will provide more choice for parents. Report P60
  • Other: The five enlargements add 210 permanent reception places from 1 September 2016. Report P9
  • Other: Cherry Garden's larger, more central site is expected to benefit more children with special educational needs. Report P35
  • Risk: More reception pupils could increase car journeys, which School Travel Plans are intended to address. Report P30
  • Risk: Keyworth objections raised overlooking, light, traffic, noise, odour and wider community impacts. Officers placed these planning matters with the Planning Committee and found no evidence of a cumulative negative impact. Report P39, P44

Who and where

  • Pupils at Phoenix, Bellenden, Ivydale, Robert Browning and Keyworth primary schools Report P2, P10
  • Cherry Garden School pupils and families Report P11, P35
  • Children with special educational needs Report P35
  • Disabled pupils and staff Report P55
  • Parents seeking primary school places Report P60
  • Parents, staff and governors at all six schools Report P32
  • Keyworth residents Report P39, P44
  • Local communities Report P29, P59

Timeline

  • 1 July 2013: Forecast primary place demand and the need for extra capacity were noted. Report P5
  • 22 July 2014: Cabinet agreed the School Places Strategy Update and planned the statutory process. Report P7
  • 19 January 2015 to 16 February 2015: The four week formal consultation allowed objections and comments. Report P14, P15
  • 10 February 2015: Cabinet agreed a £44.4m capital programme budget variation. Report P75
  • 5 March 2015: The final report was dated. Report P95
  • 16 April 2015: This was the deadline for a council decision, after which proposals would go to the Schools’ Adjudicator. Report P80
  • 1 September 2016 onwards: The five permanent school enlargements take effect. Report P2
  • September 2017 onwards: Cherry Garden School's enlargement and relocation to a new site begins. Report P2

Plain English for the jargon

  • Forms of entry (FE): Reception capacity measured as forms of entry. [P6] [P10]
  • Special educational needs (SEN): Provision for children with special educational needs. [P35]
  • Public Sector Equality Duty: The duty to eliminate discrimination, advance equality of opportunity and foster good relations. [P52]
  • Dedicated Schools Grant: Grant funding for additional expansion pupils, first via the growth fund and later the schools funding formula. [P65]
  • Gateway 2 award: The construction contract award at which the programme budget is allocated. [P64]
  • School Travel Plans: Plans seeking to address increased car journeys from enlargement. [P30]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14

Resolved

That the outcome of the consultation on the proposed enlargements of Cherry Garden School, and Phoenix, Bellenden, Ivydale, Robert Browning, and Keyworth Primary Schools be noted. 2. That the enlargement of Phoenix, Bellenden, Ivydale, Robert Browning, and Keyworth Primary Schools, from 1 September 2016 onwards be agreed, and to the enlargement and relocation of Cherry Garden School relocation, on a new site in September 2017 onwards.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 20 pages

Recommendations

1. That the cabinet notes the outcome of the consultation on the proposed enlargements of Cherry Garden School, and Phoenix, Bellenden, Ivydale, Robert Browning, and Keyworth Primary Schools.

2. That the cabinet agrees to the enlargement of Phoenix, Bellenden, Ivydale, Robert Browning, and Keyworth Primary Schools, from the 1st September 2016 onwards, and to the enlargement and relocation of Cherry Garden School relocation, on a new site in September 2017 onwards.

BACKGROUND INFORMATION

3. The Primary Investment Strategy was agreed by cabinet in July 2013 and this was updated by the cabinet member for children’s services in January 2014. In

1 July 2013, members noted notes the forecast demand for primary places and associated need for the creation of additional capacity within Southwark’s primary estate.

4. As part of the Primary Investment Strategy and expansions to meet anticipated need, the permanent enlargements of Albion, Bessemer Grange, Charles Dickens, Crawford, Grange and Keyworth Primary schools were agreed by cabinet on 18 March 2014, providing an additional 4.5 forms of entry (“FE”) at reception. At the same meeting, Members agreed that cabinet would be updated in July 2014 with new pupil place planning data, any proposals arising and the outcome of discussions with funding bodies in regard to the approach to delivery and the availability of funding.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Report: Primary school expansionReport 20 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 12 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldCommittee Member, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-Fyle MBECommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
DM
Councillor Darren MerrillCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
MS
Councillor Michael SituCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, present
EK
Eleanor KellyOfficer, present
DF
Doreen Forrester-BrownOfficer, expected

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies