London Borough of Southwark
Cabinet (decommissioned, for the Executive after, Thursday 28 May 2026 at 4.00pm

Albion Street Project Mandate

Agreed Executive 2 papers

AI summarySouthwark Cabinet agreed the Albion Street regeneration project mandate, covering four themes in two phases [D][P4][P6][P8]. Technical expert appointments are estimated at around £50k, subject to the gateway process [P48][P52].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedAppendix 1 covers four themes and two phases [D][P6][P8]
Moneyaround £50k for experts [P52]Funded from regeneration reserves, subject to the gateway process [P48][P52]
What happens nextTwo phases, funding dependent [P6][P7]Phase one develops approaches; phase two delivers [P6][P7]
Who it affectsAlbion Street and Rotherhithe [P4][P39]School, estate, library site and public realm [P8][P9]

What was decided

London Borough of Southwark Cabinet agreed the project mandate for Albion Street regeneration in Appendix 1. The framework covers four themes, progresses in two phases and is intended to maintain high public involvement. Report P2, P4, P5, P6, P8, P9

Why

The decline of Albion Street as a commercial centre had concerned people in Rotherhithe for some time. The mandate is intended to encourage regeneration and maintain substantial public involvement throughout the project. Report P4, P5

The work brings separate activities together to exploit synergies and maximise the benefit of investment. The key test is whether it meets local aspirations consistently with the Canada Water Area Action Plan. Report P10, P12

Extensive consultation shaped the project and its scope. The four themes also connect directly with adopted policy statements and help deliver important objectives. Report P19, P55, P56

What happens next

Move the four themes through the first phase, developing a general approach for each. Continue involving local people and partner organisations. Transition to delivery will depend on funding. Report P6, P7, P43, P57

Test whether expanding Albion Primary School is feasible using children's services budgets. Establish the Albion Estate's condition and resident issues through normal housing management, then involve residents in any policy response. Report P27, P28, P45, P46

Carry out preliminary design for selected public realm interventions, develop a signage and way finding strategy, improve pedestrian and cycle routes and address barriers to reinstating a market. Appoint specialists through the gateway and procurement process, seeking the most economically advantageous tender, and include public consultation in their work. Support the library developer, who will make a planning application in due course. Report P33, P39, P40, P47, P48, P52, P57

The money

  • around £50k Estimated cost of technical experts for public realm, signage, way finding and access routes, funded from regeneration reserves Report P52

Options considered

  • Chosen: Two phase delivery structure. The first phase develops each theme's general approach and the second delivers it, subject to funding. Report P6, P7, P43
  • Chosen: Albion Primary School expansion exploration. There is anticipated demand for additional pupil places. Expansion could support local places and increase footfall that supports Albion Street's local economy. Report P22, P23, P24
  • Chosen: Developer delivery of the former library. The purchaser will deliver its own commercial scheme. Initial designs show commercial space at ground level and around 30 residential units above; council officers will support and facilitate it. Report P31, P32, P33, P47
  • Chosen: Albion Estate resident investigation. The initial task is to establish the estate's condition and issues faced by residents. A policy response will then be formulated if appropriate. Report P27, P28
  • Chosen: Public realm improvement work. The work covers the neighbourhood's appearance, way finding, links with wider Rotherhithe and practical issues affecting a market. Report P9, P39
  • Chosen: Specialist support for public realm work. Consultants will support selected work and public consultation, with appointments subject to gateway reporting. Report P40, P48
  • Chosen: Separate school expansion decision. Initial school work will test whether expansion is feasible. Any solution will then be subject to a separate report and relevant decisions. Report P45
  • Chosen: Normal housing management for estate investigation. This creates no additional resource requirement at the initial investigation stage. Report P46

Implications

  • Financial: The recommendation has no direct financial implications. Implementation costs will be within existing budgets or subject to specific funding bids. Report P62
  • Financial: Appointing technical experts is estimated at around £50k and funded from regeneration reserves. Report P52
  • Legal: No particular legal issues arise at this stage. Advice and further reports will follow if property, planning or other legal issues emerge. Report P51, P60
  • Risk: Second phase delivery and specific public realm interventions depend on funding. Report P7, P43, P48
  • Staffing: Initial estate investigations will use normal housing management with no additional resource. Project coordination will remain within the Canada Water regeneration team's normal responsibilities. Report P46, P49
  • Other: If a school expansion solution is found, it will require a separate report and relevant decisions. Report P45
  • Legal: The former library planning application will determine the s106 package, including resources for public realm improvements. Report P47
  • Other: The intention is to maintain public involvement throughout the project. New consultation with Albion Estate residents is included. Report P5, P57

Who and where

  • People in Rotherhithe Report P4
  • Albion Primary School governors, staff and future pupils Report P17, P22, P23
  • Albion Estate residents and tenants Report P26, P37
  • Albion Street shoppers, leaseholders and local businesses Report P16, P23
  • Commercial developer of the former library site Report P31, P33
  • Norwegian and Finnish Churches Report P31
  • ASSG and other local volunteers Report P35, P36
  • Local doctors' surgery and possible pharmacy Report P32

Timeline

  • 29 November 2012: The officer report reached final version. Report P67
  • Between 2008 and 2011; 2009; 2010; summer of 2012: Consultation included CWAAP preparation, cafe conversations, community meetings and workshops, and an ideas forum for all local stakeholders. Report P55
  • 2026-05-28: Cabinet decided the Albion Street Project Mandate.
  • First phase and second phase: Develop a general approach for the four themes, then move to delivery when funding is available. Report P6, P7, P8, P43
  • by 2014/15: Council housing priority to make all homes warm, dry and safe. Report P18
  • by 2016: An additional 240 places for pupils in year 7 are required in the planning area. Report P23
  • ahead of 2026: CWAAP sets out initiatives needed to realise the Canada Water vision. Report P15
  • in due course: The library developer will make a planning application. Report P47

Plain English for the jargon

  • Project mandate: The agreed regeneration outline set out in Appendix 1 [D][P2]
  • Albion Street Regeneration Framework: The name given to the Albion Street regeneration project [P4]
  • CWAAP: Canada Water Area Action Plan [P15]
  • ASSG: Albion Street Steering Group [P35]
  • CGS bids: Funding bids for public realm improvements [P7][P36]
  • s106 package: The library site package determined through planning, including public realm resources [P47]
  • Gateway reporting: The report and decision needed before specialist appointments [P48][P52]
  • Public realm: The neighbourhood's appearance, routes and public spaces [P9][P39]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17

Resolved

That the project mandate for the regeneration of Albion Street as set out in Appendix 1 of the report be agreed.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 7 pages

Recommendation

That the cabinet

1. Agrees the project mandate for the regeneration of Albion Street as set out in Appendix 1.

BACKGROUND INFORMATION

2. The decline of Albion Street as a commercial centre has long been a source of concern for people in Rotherhithe. This report sets out details of the mandate for a project to encourage the regeneration of the area. The project will be called the Albion Street Regeneration Framework.

3. The mandate includes information gathered during extensive public consultation and benefits from the positive contributions made by many local people. It is the intention that a high level of public involvement will be maintained throughout the life of the project.

4. The project is structured around four themes that it is envisaged will progress in two distinct phases. The first phase focuses on developing a general approach for the particular theme area; the second on delivery of that theme. Transition to

1 the second phase will depend on the availability of funding and where appropriate will involve local people and partner organisations in fund raising: for example through CGS bids.

5. The four theme areas are:

• Albion Primary School – to explore expanding the school to two forms of entry • Albion estate – to respond to comments from residents and local people about the condition of the estate and whether it can be better integrated into the regeneration of the wider area. • The former Library on Albion Street – to ensure, so far as is possible, that the site is redeveloped in a way that supports the regeneration aspirations of local people. • Public realm – looking at a number of initiatives to improve the general appearance of the neighbourhood, way finding and links with the wider Rotherhithe area.

6. As well as extensive public consultation further work is already underway in a number of the theme areas. There is considered to be advantage in pulling all of this together in order to exploit synergies and to maximise the benefit of any investment.

KEY ISSUES FOR CONSIDERATION

7. The key issue for consideration is whether the project mandate as drafted will deliver the aspirations of local people for the regeneration of the Albion Street area in a way that is consistent with the objectives of the Canada Water area action plan.

Policy implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Albion Street Project MandateAppendix 1 11 pages Download
PDF
Report: Albion Street Project MandateReport 7 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 11 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-FyleCommittee Member, apologies
BH
Councillor Barrie HargroveCommittee Member, present
CH
Councillor Claire HicksonCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

On this subject at Southwark

Search all
  1. Albion Street Project MandateThis decision
  2. Disposal of the Rotherhithe Library, Albion Street, London SE16 7HYAgreed
  3. St. Olav's Public Convenience Site, Albion Street resolution to make Compulsory Purchase Order for Site Assembly PurposesAgreed
  4. Acquisition of Freehold Interest in 71, 73 and 75 Albion Street, SE16 and 18 Brunel Road SE16Approved
  5. Albion Street RegenerationNoted
  6. Rotherhithe Civic Centre, Albion Street, London SE16 7BSDecided

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open