London Borough of Southwark
Executive, Monday 20 July 2026 at 3.00pm

Governance arrangements for the monitoring of Community Infrastructure Levy (CIL) and Section 106 Projects

Approved Executive 2 papers

AI summarySouthwark Executive approves a unified governance framework bringing Community Infrastructure Levy and Section 106 capital projects within the council's existing capital bid process and monitoring arrangements.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedAligns with existing capital governance, flowchart adopted
MoneyNo new spending approved; £100k monitoring threshold noted
What happens nextOfficers to implement the frameworkUpdate guidance, decision pathways and monitoring
Who it affectsCIL and Section 106 funded capital projectsAll projects above £100k enter capital monitoring

What was decided

Approved a unified governance framework for capital projects funded through Strategic CIL and Neighbourhood CIL, aligning these with the council's existing capital governance framework while retaining current approval arrangements.

Noted that capital Section 106 funded projects will be reported through the same process as other capital programmes, where expenditure complies with the relevant Section 106 agreement, retaining current approvals.

Noted adoption of the capital project flowchart as the standard route for project identification, assessment, reporting, approval and monitoring of CIL and Section 106 funded projects. Report P19

Why

Current CIL and Section 106 governance arrangements sit largely outside the capital bid process, limiting strategic oversight and consistency. Report P1, P16

A single overarching process is intended to strengthen assurance and transparency, improve prioritisation, and support effective delivery within constrained resources. Report P1, P16

The proposal builds on the council's strengthened capital governance arrangements introduced in 2024-25, including the capital bid process and Capital Board assurance. Report P7, P13, P14

What happens next

Officers will implement the unified governance framework, update associated guidance and decision pathways, and align monitoring and reporting of CIL and Section 106 schemes with existing capital monitoring arrangements. Report P5

All CIL, NCIL and Section 106 projects above £100k will be included in the council's existing capital monitoring framework, including Capital Board review and reporting to CMT and Executive. Report P21

Neighbourhood CIL proposals will be developed through ward members and officers working with community councils, with a consolidated NCIL programme summary presented to Capital Board. Report P19, P21, P22

Options considered

  • Rejected: Retain separate governance and monitoring arrangements for CIL and Section 106. Would continue current inconsistencies in prioritisation, decision-making routes and reporting. Report P3

Implications

  • Legal: CIL policy and decisions are executive matters; planning permission and Section 106 requirements are non-executive and fall within Planning Committee's remit. Report P33
  • Equalities: Report is about governance only and does not change service provision; equalities and community impacts will be assessed within individual project business cases. Report P25
  • Climate: No direct climate change implications, but stronger strategic decision-making should help ensure climate impacts are considered consistently across the programme. Report P27
  • Financial: Implementation will be managed within existing officer capacity, with any additional administrative activity kept proportionate to scheme value and complexity. Report P29
  • Risk: Improved visibility of project progress and funding commitments should help reduce the risk of avoidable slippage, duplication or underspend over time. Report P29
  • Governance: Decision thresholds will apply consistently: officer and Executive Member delegations below £100k, Executive-level consideration for larger, multi-ward or complex schemes. Report P23

Who and where

  • Projects funded through Strategic CIL and Neighbourhood CIL (NCIL) Report P8, P9, P20
  • Capital projects funded through Section 106 planning obligations Report P10, P20
  • Capital Board and Corporate Management Team Report P14, P21
  • Ward members and community councils involved in shaping NCIL proposals Report P21

Timeline

  • 2024-25: Council strengthened capital governance, introducing the capital bid process and Capital Board assurance. Report P7, P13
  • September 2024: Cabinet agreed an interim framework for allocating NCIL, delegating authority to the Executive Member for New Homes and Sustainable Development for one year. Report P18
  • 31 March 2026: Interim NCIL framework extended for a further 6 months. Report P18
  • 9 July 2026: Final report dated and sent to Constitutional Team. Report P38, P39
  • 20 July 2026: Executive considered the unified governance framework.
  • Each year, usually June, September and December: Capital programme reports to Executive scheduled at Outturn, Month 4 and Month 7 monitoring. Report P15

Plain English for the jargon

  • Community Infrastructure Levy (CIL): A statutory planning charge introduced under Part 11 of the Planning Act 2008, given detailed effect through the Community Infrastructure Levy Regulations 2010 (as amended).
  • Strategic CIL: The element of CIL retained by the council as charging authority for strategic infrastructure, which must be spent on infrastructure in accordance with Regulation 59 of the CIL Regulations.
  • Neighbourhood CIL (NCIL): The neighbourhood portion of CIL, used either for infrastructure or to address the demands that development places on an area, in line with Regulation 59C. Southwark allocates 25% of CIL to NCIL.
  • Section 106: Planning obligations under section 106 of the Town and Country Planning Act 1990: legal agreements between a local planning authority and a developer, or unilateral undertakings, used to make development acceptable in planning terms.
  • Capital Board: A Corporate Management Team-led body that reviews capital proposals, providing assurance on affordability and prioritisation.
  • Infrastructure Delivery Plan (IDP): A plan being developed as part of the Southwark Plan review, setting out infrastructure required to support planned growth and new development across the borough.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13

Resolved

That the following recommendation be approved: 1. The unified governance framework for capital projects funded through community infrastructure levy (CIL), both strategic CIL and neighbourhood CIL (NCIL), aligning these with the council’s existing capital governance framework while retaining current approval arrangements. That the following recommendations be noted: 2. The reporting of capital Section 106 funded projects, where expenditure is in accordance with the terms of the relevant section 106 agreement, through the same process as all other capital programmes, whilst retaining current approvals. 3. The adoption of the capital project flowchart as the standard route for project identification, assessment, reporting, approval and monitoring for CIL and Section 106 funded projects.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Executive, 7 pages

Reasons for recommendations

4. The council’s current governance arrangements for Community Infrastructure Levy (CIL) and Section 106 funded programmes sit largely outside the capital bid process, limiting strategic oversight and consistency. A single overarching process will strengthen assurance and transparency, improve prioritisation, and support effective delivery of infrastructure schemes within constrained resources.

ALTERNATIVE OPTIONS CONSIDERED AND NOT RECOMMENDED

5. Retaining separate governance and monitoring arrangements for CIL and Section 106 has been considered but is not recommended because it would continue current inconsistencies in prioritisation, decision-making routes and reporting.

POST DECISION IMPLEMENTATION

6. Subject to Executive approval, officers will implement the unified governance framework, update associated guidance and decision pathways, and align monitoring and reporting of CIL and Section 106 schemes with existing capital monitoring arrangements.

BACKGROUND INFORMATION

7. This report builds on the council’s strengthened capital governance arrangements introduced in 2024–25, including the capital bid process and Capital Board assurance. It proposes to bring CIL and Section 106 bids and delivery monitoring within a single overarching framework so that local infrastructure funding is prioritised transparently, approved through consistent routes, and monitored proportionately.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Governance ProcessAppendix A 6 pages Download
PDF
Report: Governance arrangements for the monitoring of Community Infrastructure Levy (CIL) and Section 106 projectsReport 7 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Southwark

Search all
  1. Governance arrangements for the monitoring of Community Infrastructure Levy (CIL) and Section 106 ProjectsThis decision
  2. Governance topic: Southwark local government pensions scheme - governance arrangementsNoted

More from Southwark Executive

All decisions
MeetingDecisionOutcome
13 Oct 2026 MinutesThat the minutes of the meeting held on 15 September 2026 be approved as a correct record and signed by the chair. Approved Open
13 Oct 2026 Deputation requestsRESOLVED - That the written statement from Andrew Eke be heard. Deputation to Southwark Council Executive – Tustin Es... Decided Open
13 Oct 2026 Beormund School Expansion and RelocationThat the proposals to relocate and expand the Beormund Special Primary School be agreed. Agreed Open
13 Oct 2026 Gateway 1 - Highway works contractThat the procurement strategy outlined in the report for the provision of Highways Works be approved, comprising: · L... Approved Open
13 Oct 2026 Climate Change Strategy & Action Plan Update and Annual ReportThat the contribution of communities, schools, businesses and council services in tackling the climate crisis over th... Noted Open