Lakanal Inquiry - Progress with Coroners Recommendations
NotedExecutive4 papers
AI summaryLondon Borough of Southwark Cabinet approved £1,263,000 for LD2 type automatic battery powered smoke and heat detection in leasehold homes covered by the coroner’s recommendations [D][P2]. It noted that approval would be sought project by project for remaining borough leasehold homes [D][P28].
What happens nextFuture approval noted [D]Project by project for £8,407,000 borough leasehold installations [P28]
Who it affectsLeaseholders and housing residents [D][P39]Detection across council housing stock [P2][P39]
What was decided
London Borough of Southwark Cabinet noted the contents of the report [D][P1]. Report P1
London Borough of Southwark Cabinet approved installation of LD2 type automatic battery powered smoke and heat detection in leasehold homes in blocks covered by the coroner’s recommendations, at an estimated cost of £1,263,000 [D][P2]. Report P2
London Borough of Southwark Cabinet noted that approval for installations in the remaining leasehold dwellings across the borough would be sought project by project through the appropriate constitutional processes [D][P28]. Report P28
Why
The council responded to the coroner’s recommendations after the Lakanal fire, in which six people died [P5][P12][P14][P16]. Report P5, P12, P14, P16
Legal advice supported HRA funding where each installation formed part of a scheme designed to reduce fire and smoke spread and protect the building and other residents [P25][P69]. Report P25, P69
The free of charge offer was intended to maximise installations and increase residents’ safety because leaseholders have no obligation to install the detection [P26]. Report P26
What happens next
Approval for LD2 smoke and heat detector installations in the remaining leasehold dwellings across the borough will be sought project by project through the appropriate constitutional processes [P28]. Report P28
The sprinkler retrofit to all hostels, supported hostels and sheltered housing units was due to complete by the end of the financial year 2016/17 [P50]. Report P50
Lakanal House refurbishment is proposed to include Decent Homes Standard works, fire safety works, replacement lifts and internal district heating works [P30]. Report P30
The money
£1,263,000 Approved LD2 detection for leasehold homes in recommended blocks Report P2
£8,407,000 Estimated remaining leasehold installations across the borough Report P28
£42,617,000 Total estimated cost of the programme Report P44
£42,152,000 Capital allocation for the programme Report P45, P47
£465,000 HRA funding for block plans and signage Report P44, P45
£32,482,000 Budget for smoke and heat detection and sprinklers Report P47
£9,670,000 Budget for LD2 alarms in leasehold dwellings Report P47
4,851,000 Estimated total cost of LD2 detection in recommended general needs blocks Report P42, P43
Options considered
Chosen: Offer LD2 detection free of charge to leaseholders, with ongoing maintenance becoming their responsibility. The offer was intended to maximise installations and increase residents’ safety Report P26
Chosen: Seek approval for remaining borough leasehold installations project by project. The method allows maximum efficiencies to be gained Report P26, P28
Rejected: Compel leaseholders to maintain the detection. The council cannot force leaseholders to maintain the detection Report P26, P70
Implications
Financial: The wider programme has a total estimated cost of £42,617,000, funded by £465,000 from the HRA and a £42,152,000 capital allocation [P44][P45]. Report P44, P45
Legal: Legal advice said leaseholder alarm costs may properly be debited to the HRA where each installation forms part of a block wide preventative scheme [P25][P69]. Report P25, P69
Risk: The council cannot force leaseholders to maintain the detection, so dwelling systems could become less effective over time [P26]. Report P26
Legal: The council must protect relevant persons from fire where required precautions are within its control [P56][P57]. Report P56, P57
Legal: As occupier of tenanted and leased properties, the council owes visitors a common duty of reasonable care [P61]. Report P61
Legal: The required standard of care for leasehold flats is lower because the council has fewer rights of entry and alteration [P62]. Report P62
Staffing: Staffing costs were not included in the cost table [P41]. Report P41
Other: The coroner’s recommendations affect residents across the council’s housing stock across the borough [P39]. Report P39
Who and where
Leaseholders in blocks covered by the coroner’s recommendations Report P2
Leaseholders in remaining leasehold dwellings across the borough Report P28
Residents across the council’s housing stock Report P39
Council tenants Report P20, P27
Residents of sheltered housing schemes and temporary accommodation units Report P17, P20
Leaseholders, tenants and visitors to council premises Report P54, P61
Vulnerable residents considered for alternative fire safety solutions through Southwark SAIL Report P20, P29
Timeline
3 July 2009: The Lakanal fire occurred and six people died Report P5
14 January 2013: The coroner’s inquest into the fire commenced Report P12
28 March 2013: The jury returned narrative verdicts and the coroner sent a Rule 43 letter to the council Report P12, P13
23 May 2013: The council responded with details of action taken and still to be taken Report P16
10 December 2013: Cabinet approved measures for sprinklers and LD2 detection Report P19, P20
August 2014: The offer and installation of detection to leaseholders commenced Report P27
March 2015: LD2 detection in council homes forming part of the study was to be installed by March 2015 Report P20
end of the financial year 2016/17: The sprinkler retrofit to all hostels, supported hostels and sheltered housing units was due to complete Report P50
Plain English for the jargon
LD2: A type of automatic battery powered smoke and heat detection [P2][P20].
HRA: Housing Revenue Account, the account for the council’s general housing stock [P64][P66].
FRA: Fire Risk Assessment [P6].
HMOs: Houses in Multiple Occupation [P7].
SAIL: Southwark safe and independent living project [P20][P29].
Fire Safety Order: The Regulatory Reform (Fire Safety) Order 2005, which imposes fire safety duties on the council [P56][P57].
Occupiers Liability Act 1957: Legislation setting the council’s common duty of care to visitors in tenanted and leased properties [P60][P61].
Decent Homes Standard: The standard proposed for refurbishing Lakanal dwellings [P30].
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13
Resolved
That the contents of the report be noted. 2. That the installation of LD2 type automatic battery powered smoke/heat detection to the leasehold homes in the blocks to which the coroner’s recommendations refer (see paragraph 13 of the report) in the estimated sum of £1,263,000 be approved. 3. That the method for approval for the installation of LD2 type automatic battery powered smoke/heat detection to the leasehold homes in blocks across the borough as set out in paragraph 22 of the report, be noted.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 9 pages
Recommendations
1. That cabinet notes the contents of this report.
2. That cabinet approves the installation of LD2 type automatic battery powered smoke/heat detection to the leasehold homes in the blocks to which the coroner’s recommendations refer (see paragraph 13) in the estimated sum of £1,263,000.
3. That cabinet notes the method for approval for the installation of LD2 type automatic battery powered smoke/heat detection to the leasehold homes in blocks across the borough as set out in paragraph 22.
BACKGROUND INFORMATION
4. The Lakanal fire on 3 July 2009 in which six people died was a dreadful tragedy. In response to the fire the council quickly made a number of improvements to its management of fire safety, including:
• the creation and establishment of the in-house fire safety team; • the immediate undertaking of the programme of Fire Risk Assessments (FRAs) to all blocks of five storey and above, completed by April 2010; • the prioritisation of FRA works carried out, with £48m spent/committed to date;
1 • the professionalisation of the FRA responsibility, with the in house fire safety team having responsibility for blocks of four storey and below and new FRAs completed in March 2013; • achieving full compliance with the Regulatory Reform (Fire Safety) Order 2005 (the legislation which governs the need for fire risk assessment) by having suitable and sufficient FRAs in place for all blocks where required; • the forging and maintenance of a strong relationship with the London Fire Brigade (LFB) operationally and strategically, initially with the co-signed Memorandum of Understanding; • clear advice, information and guidance given to residents including use of secondary means of escapes, the removal of grilles and gates, the need for clear walkways, stairs and common areas, the disposal of refuse; • working toward a strategy for enforcing fire regulations in leasehold properties sub-let as Houses in Multiple Occupation (HMOs).
KEY ISSUES FOR CONSIDERATION
5. The creation and establishment of the in-house fire safety team has proved to be very successful, and it has grown over the last few years, mostly as a result of taking over the Fire Risk Assessments (FRA) process for blocks of four storeys and below, and more recently in order to meet the requirements borne out of the Lakanal Coroners recommendations.
6. The fire safety team leads the way across the country, and is quite unique insofar as most other housing providers still use consultancy firms, at great cost, to provide the FRA service. This is slowly changing and the creation of in-house fire safety teams is starting to gather pace.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.